| 1. INFRASTRUCTURE PROJECTS | |||||||||||||
| Name of Project | Location | Contractor | Final Project Cost | Date Completed | Remarks | ||||||||
| 1.0 | Proposed Ø200mm x 454.0LM DI Rehabilitation Project at Pulpogan, Consolacion | Pulpogan, Consolacion | FDRCon Co., Inc. | Php | 5,250,000.98 | May 31, 2016 | Awaiting for the Contractor to submit the as-built drawings. | ||||||
| 2.0 | Construction of Proposed Man-1 Pumping Station for the MCWD In-House Water Sourcing Program | Sitio Pilit, Brgy. Cabancalan, Mandaue City, Cebu | Dakay Construction and Development Corporation | Php | 5,739,002.00 | May 6, 2016 | The Contractor has yet to submit the As-Built Drawings, Operation and Maintenance Manual, and the Defects Liability Bond. | ||||||
| 3.0 | Prop. DI Rehabilitation Project at Pajac, Lapulapu City | Brgy. Pajac, Lapulapu City | Rex E. Morales Construction | Php | 7,093,788.30 | Mar 27, 2016 | Awaiting for the Contractor to submit the as-built drawings. | ||||||
| 4.0 | Prop. Pipeline Expansion for Cabancalan Bulk Water Supply | Brgy. Cabancalan, Mandaue City | Felman Builders and Contractors | Php | 16,744,730.61 | Feb 29, 2016 | Joint final inspection was conducted on February 29, 2016. Contractor has yet to submit the as-built drawings. | ||||||
| 5.0 | Proposed Expansion/Lateral Project for Bacayan, Pit-os | Bacayan, Pit-os, Cebu City | New Culion Builders Co. | Php | 22,019,495.65 | Jun 5, 2015 | |||||||
| 6.0 | Proposed Ø300 mm D.I. Water Distribution Main - Canduman, Mandaue City to Tigbao, Talamban, Cebu City | Canduman, Mandaue City to Tigbao, Talamban, Cebu City | Geo Transport & Construction, Inc. | Php | Project is physically completed. The Mandaue section of the project had been deleted. PMO is processing the final amount for the closing of the project. | ||||||||
| 7.0 | Construction of Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program | Brgy. Cubacub, Mandaue City | Geo Transport & Construction, Inc. | Php | 9,001,428.00 | Dec 2, 2015 | The Certificate of Project Completion had been issued to the Contractor. | ||||||
| 2. SUPPLY AND DELIVERY OF GOODS | |||||||||||||
| Name of Project | Location | Supplier | Final Project Cost | Date Completed | Remarks | ||||||||
| 3. JOINT VENTURE PROJECTS | |||||||||||||
| Name of Project | Location | JV Partner | Final Project Cost | Date Completed | Remarks | ||||||||
| Section V. Projects Completed in 2016 12 | |||||||||||||
| 4. SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS | |||||||||||||
| 4. 1 WATER SYSTEM | |||||||||||||
| Name of Project | Location | Owner/Developer | Final Project Cost | Date Completed | Remarks | ||||||||
| 1.0 | Prop. Water Distribution System for Villa Azalea Subdivision Phase 2 | Brgy. Cotcot, Liloan, Cebu | Mega Crown Realty and Development Corp. | Php | 5,964,029.61 | Feb 17, 2016 | Awaiting for the Developer to submit the as-built drawing. | ||||||
| 2.0 | Prop. Water Sytem for Graceland 1 & Graceland Annex Subdivision | Brgy. Buaya, Mactan, Lapulapu City | Kaiser Urban Development Corp. | Php | 858,046.50 | Mar 22, 2016 | |||||||
| 3.0 | Prop. PVC Water Distribution System for Kaiser Townhouse II | Estancia, Mandaue City | Kaiser Urban Development Corp. | Php | 1,687,773.35 | Mar 11, 2016 | |||||||
| 4. 2 FLOWMETER ASSEMBLY AND VAULT | |||||||||||||
| Name of Project | Location | Owner/Developer | Final Project Cost | Date Completed | Remarks | ||||||||
| 1.0 | Prop. Ø75mm Flowmeter Assembly for Midori | A.S. Fortuna Avenue, Mandaue City | Cebu Landmasters, Inc. | Php | 439,333.20 | Awaiting for the hydrotesting and disinfection result, and as-built plan. | |||||||
| 2.0 | Prop. Ø75mm Surface Flow Meter for Mabolo Garden Flats | Tres Borces St., Mabolo, Cebu City | Primary Homes, Incorporated | Php | 334,970.76 | Project is physically completed. However, the Developer has yet to pay for the guarantee deposit. Thus, the project is still awaiting for the final inspection. | |||||||
| 3.0 | Prop. Ø100mm Surface FlowMeter for Almiya Subdivision | Brgy. Canduman, Mandaue City, Cebu | Aboitizland, Inc. | Php | 378,540.42 | Jan 19, 2016 | Final inspection was conducted on January 19, 2016. | ||||||
| 4.0 | Prop. Ø100mm Surface FlowMeter for Mivesa Garden Residences | Salinas Drive Extension, Brgy. Lahug, Cebu City | Cebu Landmasters, Inc. | Php | 793,185.53 | Jan 18, 2016 | Final inspection was conducted on January 18, 2016. Awaiting for the Developer to submit the as-built drawings. | ||||||
| Section V. Projects Completed in 2016 13 | 11 | ||||||||||||