1. INFRASTRUCTURE PROJECTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Contractor |
Final Project Cost |
Date
Completed |
Remarks |
|
|
|
|
1.0 |
Proposed
Expansion/Lateral Project for Bacayan, Pit-os |
Bacayan, Pit-os, Cebu City |
New Culion
Builders Co. |
Php |
22,019,495.65 |
Jun 5, 2015 |
|
|
|
|
|
2.0 |
Proposed Ø300 mm
D.I. Water Distribution Main -
Canduman, Mandaue City to Tigbao, Talamban, Cebu City |
Canduman, Mandaue City to
Tigbao, Talamban, Cebu City |
Geo Transport
& Construction, Inc. |
Php |
|
|
Project is physically completed. The Mandaue
section of the project had been deleted. PMO is processing the final amount
for the closing of the project. |
|
|
|
|
3.0 |
Construction of
Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Brgy. Cubacub, Mandaue City |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
Joint final inspection was conducted on
December 2, 2015. Contractor has yet to submit the as-built drawings and the
occupancy permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2. SUPPLY AND DELIVERY OF GOODS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Supplier |
Final Project Cost |
Date
Completed |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3. JOINT VENTURE PROJECTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
JV Partner |
Final Project Cost |
Date
Completed |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS |
|
|
|
|
|
|
|
4. 1 WATER SYSTEM |
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Owner/Developer |
Final Project Cost |
Date
Completed |
Remarks |
|
|
|
|
1.0 |
Prop. Water Sytem Design for
Zariville Subdivision |
Brgy. Lagtang, Talisay City |
Citrineland Corp. |
Php |
961,739.22 |
Feb 16, 2015 |
|
|
|
|
|
|
2.0 |
Prop. Water Distribution Lines
for Colorado Dos |
Brgy. Cotcot, Liloan, Cebu |
Primary Homes, Incorporated |
Php |
2,813,740.02 |
Nov 11, 2015 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. 2 FLOWMETER ASSEMBLY
AND VAULT |
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Owner/Developer |
Final Project Cost |
Date
Completed |
Remarks |
|
|
|
1.0 |
Prop. Ø75mm
Flowmeter Assembly for Midori |
A.S. Fortuna Avenue, Mandaue City |
Cebu
Landmasters, Inc. |
Php |
439,333.20 |
|
Awaiting
for the hydrotesting and disinfection result, and as-built plan. |
|
|
|
2.0 |
Prop.
Ø150mm and Ø100mm Bulk Meter
Connections for Norkis Cyberpark |
A.S.
Fortuna and L. Jaime Sts., Mandaue City |
Norkis
Cyberpark |
Php |
1,055,960.34 |
Apr 14, 2015 |
|
|
|
|
3.0 |
Prop. Ø150mm
Surface Flow Meter for Monterrazas Subd. |
Brgy. Guadalupe, Cebu City |
GENVI
Development Corp. |
Php |
481,029.27 |
Jun 10, 2015 |
|
|
|
|
4.0 |
Prop. Ø100mm
Flow Meter for Andalucia Crest Subdivision |
Brgy.
Gabi, Cordova, Cebu |
Myvan
Properties & Development, Inc. |
Php |
464,612.05 |
Jun 9, 2015 |
|
|
|
|
5.0 |
Prop. Ø75mm
Surface Flow Meter for Mabolo Garden Flats |
Tres
Borces St., Mabolo, Cebu City |
Primary
Homes, Incorporated |
Php |
334,970.76 |
|
Project
is physically completed. However, the Developer has yet to pay for the
guarantee deposit. Thus, the project is still awaiting for the final
inspection. |
|
|
|
6.0 |
Prop. Ø100mm
Surface Flow Meter for Grand Residences (Tower 1 and 2) |
Archbishop
Reyes Ave., Cebu City |
Grand
Land, Inc. |
Php |
474,041.64 |
Jul 3, 2015 |
|
|
|
|
7.0 |
Prop. PVC Water
Distribution System for South Glendale Subdivision |
San
Isidro Road, San Isidro, Talisay City, Cebu |
Primary
Homes, Inc. |
Php |
1,247,851.98 |
Jul 15, 2015 |
|
|
|
|
8.0 |
Prop.
Ø100mm Surface FlowMeter for Robinsons
Galleria |
Gen.
Maxilom Ave., Tejero, Cebu City |
Robinsons
Land Corporation |
Php |
599,885.68 |
Sep 15, 2015 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section V. Projects Completed in 2015 12 |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|