Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks (November) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 9 |
JFAP Construction |
PhP |
49,856,139.71 |
|
49,856,139.71 |
22 Oct 2015 |
17 Jul 2016 |
- |
0.00% |
0.00% |
0.00% |
The pipes and
fittings from India are in transit. It is expected to arrive at the port of
Cebu by mid-January 2016. |
|
Five MCWD personnel had already
conducted the in-plant inspection in India on November 4 - 7, 2015.
Contractor is awaiting for the delivery of the DI pipe and fittings from
India to Cebu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 11 |
A.L. Gantuangco Construction |
PhP |
9,214,465.00 |
|
9,214,465.00 |
10 Sep 2015 |
07 Mar 2016 |
- |
24.61% |
0.00% |
-24.61% |
The pipes and
fittings from India have already arrived at the port of Cebu in the later
part of December 2015. Contractor was advised to make a written request for
inspection of said materials. Implementation of the project is expected to
start by January 2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Five MCWD personnel had already
conducted the in-plant inspection in India on November 4 - 7, 2015.
Contractor is awaiting for the delivery of the DI pipe and fittings from
India to Cebu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 7 |
JFAP Construction |
PhP |
35,078,950.22 |
|
35,078,950.22 |
10 Sep 2015 |
16 May 2016 |
- |
12.44% |
0.00% |
-12.44% |
The pipes and
fittings from India have already arrived at the port of Cebu in the later
part of December 2015. Contractor was advised to make a written request for
inspection of said materials. Implementation of the project is expected to
start by January 2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Five MCWD personnel had already
conducted the in-plant inspection in India on November 4 - 7, 2015.
Contractor is awaiting for the delivery of the DI pipe and fittings from
India to Cebu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
- |
84.66% |
0.00% |
-84.66% |
The pipes and
fittings from India have already arrived at the port of Cebu in the later
part of December 2015. Contractor was advised to make a written request for
inspection of said materials. Implementation of the project is expected to
start by January 2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Five MCWD personnel had already
conducted the in-plant inspection in India on November 4 - 7, 2015.
Contractor is awaiting for the delivery of the DI pipe and fittings from
India to Cebu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
100.00% |
47.13% |
-52.87% |
Contractor is already in full
swing with the project implementation. They have two (2) teams working on
different areas of the project.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavation works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
may be reduced once the revised PERT/CPM will be approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
98.46% |
11.30% |
-87.16% |
Contractor is already in full
swing with the project implementation.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavation works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
may be reduced once the revised PERT/CPM will be approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
91.32% |
50.14% |
-41.18% |
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavation works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
may be reduced once the revised PERT/CPM will be approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
93.44% |
27.55% |
-65.89% |
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavation works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
may be reduced once the revised PERT/CPM will be approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
0.00% |
-100.00% |
The Contractor has already
started project implementation on December 22, 2015. Project is ongoing with
liquidated damages to be imposed upon the Contractor. |
|
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. Despite several follow-ups
by PMO, Contractor has still not submitted the crash program which is part of
the latter's commitment. Contractor has tentatively scheduled to start
project works by December 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
54.89% |
-45.11% |
Remaining works of the project
are the following: hydrotesting, interconnection, installation of valves, and
disinfection. Liquidated damages shall be imposed upon the Contractor for its
failure to complete the project within the contract duration. |
|
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. Despite several follow-ups
by PMO, Contractor has still not submitted the crash program which is part of
the latter's commitment. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The termination of this project
is being handled by the Legal Department. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The termination of this project
is being handled by the Legal Department. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay Construction and
Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
84.81% |
-15.19% |
OIC - AGM Tabasa had informed the
PMO that the proposed Variation Order No.1 deleting the interconnection work
from the Contract ensuing from the non-issuance by DPWH of the necessary
excavation permit was approved by the BOD. The PMO is awaiting the BOD
Resolution before it will inform the Contractor about this. |
|
The installed pump and motor at MAN-1 had passed the field
testing on September 11, 2015. OIC - AGM Tabasa had informed the PMO that the
proposed Variation Order No.1 deleting the interconnection work from the
Contract ensuing from the non-issuance by DPWH of the necessary excavation
permit was approved by the BOD. The PMO is awaiting the BOD Resolution before
it will inform the Contractor about this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from January 1, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from January 1, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. PMO is still awaiting for the said letter. |
|
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
The Contractor
has already made exploration for the interconnection works in Brgy. Tabok,
Mandaue City. Interconnection works is expected to be completed by January
2016. |
|
The repiping along Brgy. Tabok
was already completed and passed hydrotesting. It is awaiting for the
disinfection. Contractor is expected to explore the area for the
interconnection. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|