| REPORT SUMMARY AS OF MAY 2013 | ||||||||||||||||||
| D. SECTION V. ON-GOING SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS | ||||||||||||||||||
| Under a Memorandum of Agreement (MOA), the developer/owner shall fund and implement the project and turn-over it to MCWD upon completion. MCWD is obligated to prepare the detailed design and estimates and provide supervision during the implementation of the project. | ||||||||||||||||||
| Name of Project | Brief Description of the Project | Subdivision/Hotel/Condo Name | Developer / Owner | MCWD Supervising Unit | Project Amount | Project Duration | Date Started | Target Completion Date | Accomplish- ment To Date | Remarks | LATEST UPDATE AS OF MAY 2013 | |||||||
| D.1 Water System | ||||||||||||||||||
| 1.0 | Prop. Water Distribution System for EastGate Subdivision (Matumbo, Pusok, Lapulapu) | 49.54 LM x 75mm dia | EastGate Subdivision | Urban Enclaves Inc. | Project Management Office | PhP | 514,061.34 | 11 CD | 15 Jul 2011 | 26 Jul 2011 | 0.00% | No activity conducted for the month. | contractor and subcontractor is on meeting… | |||||
| Related Project: | ||||||||||||||||||
| 1.0 Pusok, Lapu-Lapu (Matumbo), Pipe laying 96 LM x 75mm dia. & 126 LM x 150mm dia. D.I. | See Part C Section IV Subsection C.1 of the Report Summary | |||||||||||||||||
| 2.0 | Prop. Water Distribution System for Modena Mactan Subdivision (Basak, Lapu-lapu City) | 166 LM x 100mm dia., 1016 LM x 75mm dia. | Modena Mactan Subdivision | Juanito King & Sons, Inc. | Project Management Office | PhP | 4,011,373.95 | 95 CD | 25 Apr 2011 | 28 Jul 2011 | 97.00% | No activity conducted for the month. The only remaining work is restoration. | Corplan has worked out the minor problems. | |||||
| Related Project: | ||||||||||||||||||
| 1.0 Modena Subdivision (Interconnecting Pipeline) | See Part A Section II Subsection 10 of the Report Summary | |||||||||||||||||
| 3.0 | Prop. PVC Water Distribution System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) | 484 LM x 75mm dia., 781 LM x 100mm dia., 167 LM x 150mm dia. | Amara Subdivision | Cebu Holdings, Inc. | Project Management Office | PhP | 92 CD | 15 May 2012 | 14 Aug 2012 | 96.00% | Contractor is on the process of purchasing the handhole cover and AV/AR head. | A meeting was held. It will be turned-over by July 2013. | ||||||
| Related Project: | ||||||||||||||||||
| 1.0 Amara Waterline Project (MCWD Counterpart) | See Part C Section IV of the Report Summary | |||||||||||||||||
| 2.0 Prop. Rerouting of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu) | See Part D Section V of the Report Summary | |||||||||||||||||
| 4.0 | Prop. Rerouting of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu) | 1,650 LM x 150mm dia. | Amara Subdivision | Cebu Holdings, Inc. | Project Management Office | PhP | 92 CD | 15 May 2012 | 14 Aug 2012 | 96.00%[1] | Remaining work is only disinfection. | This will be included with the project turnover above. | ||||||
| Related Project: | ||||||||||||||||||
| 1.0 Amara Waterline Project (MCWD Counterpart) | See Part C Section IV of the Report Summary | |||||||||||||||||
| 2.0 Prop. PVC Water Distribution System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) | See Part D Section V of the Report Summary | |||||||||||||||||
| Section I. Summary 8 | ||||||||||||||||||
| REPORT SUMMARY AS OF MAY 2013 | ||||||||||||||||||
| D. SECTION V. ON-GOING SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS | ||||||||||||||||||
| Name of Project | Brief Description of the Project | Subdivision/Hotel/Condo Name | Developer / Owner | MCWD Supervising Unit | Project Amount | Project Duration | Date Started | Target Completion Date | Accomplish- ment To Date | Remarks | ||||||||
| 5.0 | Prop. Water Distribution System for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City)[2] | 6,920 LM x 75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia., 151 LM x 250mm dia. | Pueblo De Oro Communities (Horizon, La Aldea Del Mar, and Parkplace) | Pueblo De Oro Development Corp. | Project Management Office | PhP | 22,980,152.33 | 15.00% | Currently doing the pipelaying works | currently doing pipelaying works.. | ||||||||
| 6.0 | Prop. Water Distribution System for Portville Subdivision (Aviation Road, Brgy. Buaya, Lapu-lapu City)[3] | 982 LM x 75mm dia., 269 LM x 100mm dia., 17 LM x 150mm dia. | Portville Subdivision | Johndorf Venture Corp. | Project Management Office | PhP | 3,430,246.86 | 94 CD | 3-Sep-12 | 6-Dec-12 | 60.00% | Waiting for the materials that were allegedly stolen. | ||||||
| 7.0 | Prop. Water Distribution Lines for Northwoods Residences (H. Abellana St., Canduman, Mandaue City, Cebu | 386 LM x 75mm dia. PVC water distribution line | Northwoods Residence | Priland Development Corp. | Project Management Office | PhP | 1,250,000.00 | 14-Feb-13 | ||||||||||
| 8.0 | Prop. Water Distribution System for Summer Ville 3 Subdivision (Brgy. Buagsong, Cordova, Cebu) | 362 LM x 75mm dia. PVC water distribution line | Summer Ville 3 Subdivision | ABQ & Sons Realty and Development Corp. | Project Management Office | PhP | 2,117,087.90 | 52 CD | 30-May-13 | 20-Jul-13 | ||||||||
| D.2 Flowmeter Assembly and Vault | ||||||||||||||||||
| 1.0 | Prop. Ø150mm Large Meter Assembly for Urban Homes Mandaue | dia.150mm large meter, large meter assembly & interconnection | Urban Homes | Fog Horn, Inc. | Project Management Office | PhP | 1,428,658.31 | 46 CD | Developer has requested the testing of materials. | Request material inspection | ||||||||
| 2.0 | Prop. Ø75mm Flowmeter and Construction of Reinforced Concrete Meter Vault for 1016 Residences | dia.75mm flowmeter, flowmeter assembly & interconnection | 1016 Residences | Ayala Land, Inc. and Cebu Holdings, Inc. | Project Management Office | PhP | 952,133.26 | 30 CD | No communication with the developer. | suggested for follow up. | ||||||||
| 3.0 | Prop. Ø75mm Surface Flowmeter Assembly for the Padgett Place | dia.75mm large meter, large meter assembly & interconnection | Padgett Place | Cebu Green Peaks Development, Inc. | Project Management Office | PhP | 685,113.03 | 28 CD | 19-Mar-13 | 15-Apr-13 | Procurement stage. | |||||||
| 4.0 | Prop. Ø75mm Surface Mounted Flowmeter Assembly for Spianada Condominium (Cor. Rahman and E. Benedicto Sts., Cebu City) | dia.75mm large meter, large meter assembly & interconnection | Spianada Condominium | Land Caster Estate Ventures, Inc. | Project Management Office | PhP | 638,081.16 | 20 CD | 26-Mar-13 | 14-Apr-13 | Procurement stage. | |||||||
| 5.0 | Prop. Ø100mm Surface-Mounted Bulkmeter for Citylights Garden Phase 2 (Towers 3 & 4) (Lahug, Cebu City) | dia.100mm Large Meter, Large Meter Assembly & Interconnection | Citylights Gardens Phase 2 | Citylights Garden Tower 3 & 4 Condominium Corporation | Project Management Office | PhP | 774,000.00 | 31 CD | 24-Apr-13 | 24-May-13 | Procurement stage. | |||||||
| 6.0 | Prop. Ø75mm Surface-Mounted Bulkmeter for Citylights Garden Phase 1 (Towers 1 & 2) (Lahug, Cebu City) | dia.75mm large meter, large meter assembly & interconnection | Citylights Gardens Phase 1 | Citylights Garden Condominium Corporation | Project Management Office | PhP | 689,000.00 | 37 CD | 9-May-13 | 14-Jun-13 | Procurement stage. | |||||||
| 7.0 | Prop. Ø100mm Flowmeter Enclosed in Reinforced Concrete Vault for Alegria Palms Subdivision 2 (Brgy. Gabi, Cordova, Cebu) | dia.100mm flowmeter, construction of reinforced concrete vault & interconnection | Alegria Palms Subdivision 2 | Commonwealth Estate, Inc. | Project Management Office | PhP | 1,216,026.49 | 50 CD | 29-May-13 | 17-Jul-13 | Procurement stage. | |||||||
| Section I. Summary 9 | ||||||||||||||||||