1. INFRASTRUCTURE PROJECTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of
Project |
Location |
Final Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
1.0 |
Prop. Tennis
Court Resurfacing |
MCWD
Compound, Talamban, Cebu City |
PhP |
124,000.00 |
February 28,
2013 |
Certification of Project Completion was already
issued to the Contractor |
|
|
|
|
|
|
2.0 |
Prop. D.I.
Rehabilitation Project for DMA-25A, W. Cabalse and Holyname Sts. |
Mabolo,
Cebu City |
PhP |
2,449,834.22 |
May 6, 2013 |
Awaiting submission by Contractor of the
Certificate of Acceptance of Road Restoration from Cebu City before PMO will
issue the Certificate of project Completion. |
|
|
|
|
|
|
3.0 |
Prop. Ø 300 mm
D.I Distribution Line along Pit-os, Talamban, Cebu City |
Talamban, Cebu
City |
PhP |
54,080,280.37 |
06 Nov 2013 |
Awaiting submission by contractor of the
as-built drawings. |
|
|
|
|
|
|
4.0 |
Prop. Ø150mm
& Ø100mm D.I Distribution Line along Umapad-Opao, Mandaue City |
Umapad-Opao,
Mandaue City |
PhP |
13,515,695.33 |
10 Sep 2013 |
Awaiting submission by contractor of the
as-built drawings. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2. SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2. 1 WATER SYSTEM |
|
|
|
|
|
|
|
|
|
|
Name of
Project |
Location |
Final Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
1.0 |
Prop. Water Distribution Main
for CBP Resort Development Project |
Negros St., Cebu Business Park,
Cebu City |
PhP |
544,278.79 |
January 8,
2013 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
2.0 |
Prop. Water Distribution System
for Alberlyn South Subdivision |
Cansojong, Talisay City, Cebu |
PhP |
1,122,690.12 |
April 16,
2013 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
|
|
|
|
|
2. 2 FLOWMETER ASSEMBLY
AND VAULT |
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Final Project Cost |
Date Completed |
Remarks |
|
|
|
|
1.0 |
Prop. Ø150mm
Flowmeter and Construction of Reinforced Concrete Vault for Amisa Private
Residences |
Punta Engaño,
Lapu-lapu City |
Php |
1,346,387.53 |
March 8, 2013 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
2.0 |
Prop. Ø75mm
Surface Flowmeter for Baseline Condominium |
J. Osmeña
Street, Capitol, Cebu City |
Php |
363,410.90 |
November 29, 2013 |
Awaiting for the as-built plans. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Projects Completed in 2013 |
11 |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|