Name of Project |
Brief Description of the Project |
Subdivision/Hotel/Condo Name |
Developer / Owner |
MCWD Supervising Unit |
Project Amount |
Project Duration |
Date Started |
Target Completion Date |
Accomplish-
ment
To Date |
Remarks |
|
|
|
1. Water System |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Water Distribution System
for EastGate Subdivision (Matumbo, Pusok, Lapulapu) |
49.54 LM x
75mm dia |
EastGate Subdivision |
Urban Enclaves Inc. |
Project Management Office |
PhP |
514,061.34 |
11 CD |
15 Jul 2011 |
26 Jul 2011 |
0.00% |
Excavation works on for the water
system of the subdivision is on-going. |
|
2.0 |
Prop. Water Distribution System
for Modena Mactan Subdivision (Basak, Lapu-lapu City) |
166 LM x 100mm
dia., 1016 LM x 75mm dia. |
Modena Mactan Subdivision |
Juanito King & Sons, Inc. |
Project Management Office |
PhP |
4,011,373.95 |
95 CD |
25 Apr 2011 |
28 Jul 2011 |
97.00% |
No activity
conducted during the month. |
|
3.0 |
Prop. PVC Water Distribution
System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) |
484 LM x 75mm dia., 781 LM x 100mm dia., 167
LM x 150mm dia. |
Amara Subdivision |
Cebu Holdings, Inc. |
Project Management Office |
PhP |
|
92 CD |
15 May 2012 |
14 Aug 2012 |
96.00% |
Contractor is on the process of
purchasing the handhole cover and AV/AR head. |
|
4.0 |
Prop. Rerouting
of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu) |
1,650 LM x 150mm dia. |
Amara
Subdivision |
Cebu Holdings, Inc. |
Project
Management Office |
PhP |
|
92 CD |
15 May 2012 |
14 Aug 2012 |
98.00% |
The only
remaining work is the disinfection of portion of water system of the
subdivision at phase 3b. |
|
5.0 |
Prop. Water Distribution System
for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City)[1] |
6,920 LM x
75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia.,
151 LM x 250mm dia. |
Pueblo De Oro Communities
(Horizon, La Aldea Del Mar, and Parkplace) |
Pueblo De Oro Development Corp. |
Project
Management Office |
PhP |
22,980,152.33 |
|
|
|
20.00% |
A portion of the water
system of the subdivision is already
ready for partial turn-over to MCWD. Pipelaying works for the other portions
of the subdivision is on-going. |
|
6.0 |
Prop. Water Distribution System
for Portville Subdivision (Aviation Road, Brgy. Buaya, Lapu-lapu City)[2] |
982 LM x 75mm
dia., 269 LM x 100mm dia., 17 LM x 150mm dia. |
Portville Subdivision |
Johndorf Venture Corp. |
Project
Management Office |
PhP |
3,430,246.86 |
94 CD |
3-Sep-12 |
6-Dec-12 |
80.00% |
Remaining works are
disinfection, installation of concrete pads and barricades for stub-outs,
interconnection to overhead water tank. |
|
7.0 |
Prop. Water
Distribution Lines for Northwoods Residences (H. Abellana St., Canduman,
Mandaue City, Cebu |
386
LM x 75mm dia. PVC water distribution line |
Northwoods
Residence |
Priland
Development Corp. |
Project
Management Office |
PhP |
1,250,000.00 |
|
14-Feb-13 |
|
|
|
|
8.0 |
Prop. Water
Distribution System for Summer Ville 3 Subdivision (Brgy. Buagsong, Cordova,
Cebu) |
362
LM x 75mm dia. PVC water distribution line |
Summer Ville 3
Subdivision |
ABQ & Sons
Realty and Development Corp. |
Project
Management Office |
PhP |
2,117,087.90 |
52 CD |
30-May-13 |
20-Jul-13 |
|
|
|
9.0 |
Prop. PVC Water
Distribution System for Kaiser Townhouse II |
510
LM x 100mm dia. PVC and 75mm dia. PVC water distribution line |
Kaiser
Townhouse II |
Kaiser Urban
Development Corp. |
Project
Management Office |
PhP |
1,687,773.35 |
|
24-Jun-13 |
|
|
Developer has
acquired permit for the excavation at the interconnection point. |
|
10.0 |
Prop. Water
Distribution Systems for Mactan Plains Subdivision |
114
LM x 100mm dia. PVC and 810 LM 75mm dia. PVC water distribution line |
Mactan Plains
Subdivision |
Pacific Land
Ventures and Property Development, Inc. |
Project
Management Office |
PhP |
1,617,764.80 |
|
25-Jun-13 |
|
|
|
|
11.0 |
Prop. Water
Distribution Systems for Capitol Residences |
153
LM x 75mm dia. PVC |
Capitol
Residences |
Urban Enclaves
Inc. |
Project
Management Office |
PhP |
678,670.75 |
|
12-Sep-13 |
|
60.00% |
Pipelaying is
in halted. Awaiting for the delivery of other materials. |
|
12.0 |
Prop. Water
System Design for Goldmine Residences (Bangkal-Mahayahay-Soong, Lapulapu
City) |
236
LM x 150mm dia. PVC, 32 LM 100mm dia. PVC, 152 LM 75mm dia. PVC, 617 LM 50mm
dia. PVC |
Goldmine
Residences |
Heritage Supreme
Land Developer, Inc. |
Project
Management Office |
PhP |
3,215,481.65 |
|
14-Oct-13 |
|
|
Conducted
pre-construction meeting with developer. |
|
13.0 |
Prop. Water
Distribution Systems for City Homes - Mandaue (J.S. Alinsug St., Mandaue
City, Cebu) |
42
LM 75mm dia. PVC, 218 LM 50mm dia. PVC |
City Homes
Mandaue |
Grand Land, Inc. |
Project
Management Office |
PhP |
870,061.25 |
|
23-Oct-13 |
|
20.00% |
Pipelaying for
the water system of the subdivision is ongoing. |
|
14.0 |
Prop. Water
Distribution Systems for Anami Homes - Mactan (Sudtungan, Basak, Lapulapu
City) |
518
LM 75mm dia. PVC |
Anami Homes
Mactan |
Softouch
Property |
Project
Management Office |
PhP |
1,312,868.15 |
|
24-Oct-13 |
|
|
Conducted
pre-construction meeting with developer. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Ongoing Subdivision/Hotel/Condo Water System Projects 8 |
|
|
|
|
|
|
|
|
|
|
Name
of Project |
Brief Description of the Project |
Subdivision/Hotel/Condo Name |
Developer / Owner |
MCWD Supervising Unit |
Project Amount |
Project Duration |
Date Started |
Target Completion Date |
Accomplish-
ment
To Date |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2. Flowmeter Assembly
and Vault |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Ø150mm Large Meter
Assembly for Urban Homes Mandaue |
dia.150mm
large meter, large meter assembly & interconnection |
Urban
Homes |
Fog Horn, Inc. |
Project
Management Office |
PhP |
1,428,658.31 |
46 CD |
|
|
100.00% |
Awaiting for
the final project inspection and the as-built plan. |
|
2.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Meter Vault for 1016
Residences |
dia.75mm
flowmeter, flowmeter assembly & interconnection |
1016
Residences |
Ayala
Land, Inc. and Cebu Holdings, Inc. |
Project
Management Office |
PhP |
952,133.26 |
30 CD |
|
|
|
Conducted
material testing. |
|
3.0 |
Prop. Ø75mm
Surface Flowmeter Assembly for the Padgett Place |
dia.75mm
large meter, large meter assembly & interconnection |
Padgett
Place |
Cebu
Green Peaks Development, Inc. |
Project
Management Office |
PhP |
685,113.03 |
28 CD |
19-Mar-13 |
15-Apr-13 |
60% |
Contractor
is still awaiting for the delivery of the flowmeter. |
|
4.0 |
Prop. Ø75mm
Surface Mounted Flowmeter Assembly for Spianada Condominium (Cor. Rahman and
E. Benedicto Sts., Cebu City) |
dia.75mm
large meter, large meter assembly & interconnection |
Spianada
Condominium |
Land
Caster Estate Ventures, Inc. |
Project
Management Office |
PhP |
638,081.16 |
20 CD |
26-Mar-13 |
14-Apr-13 |
|
Procurement
stage. |
|
5.0 |
Prop. Ø100mm
Surface-Mounted Bulkmeter for Citylights Garden Phase 2 (Towers 3 & 4)
(Lahug, Cebu City) |
dia.100mm
Large Meter, Large Meter Assembly & Interconnection |
Citylights
Gardens Phase 2 |
Citylights
Garden Tower 3 & 4 Condominium Corporation |
Project
Management Office |
PhP |
774,000.00 |
31 CD |
24-Apr-13 |
24-May-13 |
|
Procurement
stage. |
|
6.0 |
Prop. Ø75mm
Surface-Mounted Bulkmeter for Citylights Garden Phase 1 (Towers 1 & 2)
(Lahug, Cebu City) |
dia.75mm
large meter, large meter assembly & interconnection |
Citylights
Gardens Phase 1 |
Citylights
Garden Condominium Corporation |
Project
Management Office |
PhP |
689,000.00 |
37 CD |
9-May-13 |
14-Jun-13 |
|
Procurement
stage. |
|
7.0 |
Prop. Ø100mm
Flowmeter Enclosed in Reinforced Concrete Vault for Alegria Palms Subdivision
2 (Brgy. Gabi, Cordova, Cebu) |
dia.100mm
flowmeter, construction of reinforced concrete vault & interconnection |
Alegria
Palms Subdivision 2 |
Commonwealth
Estate, Inc. |
Project
Management Office |
PhP |
1,216,026.49 |
50 CD |
29-May-13 |
17-Jul-13 |
|
No
activity conducted during the month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Ongoing Subdivision/Hotel/Condo Water System Projects 9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|