Name of Contract |
Joint Venture Partner |
Minimum Volume |
Supply Cost |
Date of Contract Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
Previous Report |
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On the
required Data Monitoring Software (calculate/tabulate data, show graphs,
indicate under- or over-supply), AWC has the option to use either the Premier
Portal Web or the PWRI-developed software. The latter is still subject to a
test run but AWC intimated to use it. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the succesful installation and
operation of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unreliable reading due to
defective SIM. Information Technology (IT) expert recommended that we replace
the SIM, however, we could not replace
the said SIM as soon as possible as we are to coordinate with Mr. Felisisimo
Salcedo of the Meter Mainenance. We have already informed the concern and are
waiting for their availability. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply Program - Talamban Injection Point |
Pilipinas Water Resources, Inc. |
3,592 |
m3/day |
PhP |
14.21 |
/m3 |
19 Nov 2010 |
19 May 2011 |
5 Dec 2011 |
The Talamban
Injection Point has been supplying water to MCWD since December 6, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unreliable reading due to
defective SIM. Information Technology (IT) expert recommended that we replace
the SIM, however, we could not replace
the said SIM as soon as possible as we are to coordinate with Mr. Felisisimo
Salcedo of the Meter Mainenance. We have already informed the concern and are
waiting for their availability. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MRII had
informed PMO it will use the PWRI-developed Data Monitoring Software. MRII is
just awaiting the successful trial run and approval by MCWD of said software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the succesful installation and
operation of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section II. On-going
Joint Venture Undertakings
|
5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Contract |
Joint Venture Partner |
Minimum Volume |
Supply Cost |
Date of Contract Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
Time Extension on process |
This JV
Contract has 3 injection points spread over Brgy. Guadalupe: Guadalajara,
Kabajar, and Quijada. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Guadalajara
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
Guadalajara injection point has been
operational since September 2012. It
supplies an average of 2,400m3 of water daily. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kabajar
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Kabajar
injection point has been operational
since November 8, 2012. It supplies an average of 600m3 of water daily. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Quijada
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Start of asphalt breaking last
November 18, 2013 of the proposed flowmeter vault meter however, the
excavation was stopped due to the forthcoming Feast of Our Lady of Guadalupe.
Expected date to resume activity will be on December 12, 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Bulk Water Supply Program - Pit-os Injection Point |
Abejo Waters Corporation |
4,800 |
m3/day |
PhP |
15.68 |
/m3 |
19 June 2013 |
18 June 2014 |
|
Under this
joint venture, AWC will deliver a minimum of 4,800 m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC reported
that the proposed Amendment to its existing MOA with the Municipality of
Consolacion that will allow AWC to extract additional volume of water from
within the municipality is still with the Mayor's Office for
signature/approval. AWC will make a follow up with the Mayor's Office first
week next month. Works (e.g. well drilling, pipelaying, etc.) can not start
until the Amendment is approved and the necessary permits secured. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Ø300mm
HDPE pipes including fittings and appurtenances intended for the raw water
collector/transmission mains are already delivered at AWC Warehouse. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Bulk Water Supply Program - Cabancalan Injection Point |
Abejo Waters Corporation |
5,000 |
m3/day |
PhP |
14.78 |
/m3 |
25 Sept. 2013 |
24 Sept. 2014 |
|
Ongoing
negotiation of pump station. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section II. Ongoing Joint
Venture Undertakings |
6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|