1.0 |
MCWD Bulk Water
Supply Contract (Compostela-Liloan-Consolacion Injection Points) |
Cebu Manila
Water Development Incorporated |
Php |
24.59 / cu.m. |
Year 1
: |
18,000 m3/day |
18 Dec 2013 |
*09 Dec 2014 |
|
MCWD had extended the
Day 1 of the year 2 of delivery to October 1, 2016. CMWD however, had failed
to fully complete the main injection
point at Casili in Consolacion and the final (i.e. approved) drop-off points
in Compostela, Liloan, and Consolacion on the above date. |
|
Works at the 3
drop-off points to comply with the approved flowmeter assembly and injection
scheme are ongoing. |
|
|
|
|
|
|
|
Year 2 to Year 20 : |
35,000 m3/day |
|
09 Dec 2015 |
1 Oct 2016 |
|
|
|
|
|
|
|
|
|
|
|
|
* - Day 1
of the 1st
year of delivery per MCWD letter to CMWD dated December 5, 2014 |
|
CMWD had
requested another time extension of the Day 1 of the year 2 in order to fully
complete the required main injection and 3 drop-off points. MCWD is open to
grant another time extension on the condition that liquidated damages will be
imposed upon CMWD if it failed to complete the required injection points
within the new time extension. The parties had agreed to execute a
Supplemental Agreement for the liquidated damages. |
|
At the Casili injection point, works to
complete the flowmeter assembly is ongoing. The ultrasonic level instrument
to be installed at the CMWD reservoirs that will trigger the start/stop of
the booster pumps have yet to be delivered. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Acting GM Dalena on his June 28, 2016 letter had informed
CMWD that the previously scheduled June 28-30, 2016 interconnection at the
Casili injection point will be moved to another date. Further, MCWD will
extend the Day 1 of the Year 2 of delivery correspondingly if the
interconnection is scheduled beyond the approved July 16, 2016 Day 1 of Year
2. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Under the Contract, the Service
Provider will construct a Septage Treatment Facility at the MCWD property in
Cordova, Cebu and shall collect, transport and treat the septage and dispose
the bio-solids. The term of the service contract is five (5) years from the
Day One of operation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|