Name of Project  Contractor  Supply Cost Volume Contract Signing Day 1 of Delivery  Revised                                Day 1 of Delivery  Remarks
                 
1.0 MCWD Bulk Water Supply Contract (Compostela-Liloan-Consolacion Injection Points) Cebu Manila Water Development Incorporated Php 24.59 / cu.m. Year 1                    : 18,000 m3/day 18 Dec 2013 *09 Dec 2014   MCWD had extended the Day 1 of the year 2 of delivery to October 1, 2016. CMWD however, had failed to fully  complete the main injection point at Casili in Consolacion and the final (i.e. approved) drop-off points in Compostela, Liloan, and Consolacion on the above date.
      Year 2 to Year 20 : 35,000 m3/day   09 Dec 2015 1 Oct 2016
            * - Day 1 of the 1st year of delivery per MCWD letter to CMWD dated December 5, 2014   CMWD had requested another time extension of the Day 1 of the year 2 in order to fully complete the required main injection and 3 drop-off points. MCWD is open to grant another time extension on the condition that liquidated damages will be imposed upon CMWD if it failed to complete the required injection points within the new time extension. The parties had agreed to execute a Supplemental Agreement for the liquidated damages.
                MCWD early this month had sent to CMWD for comment/concurrence a draft Supplemental Agreement that will cover the new Day 1 of the year 2 of delivery and provisions for liquidated damages. CMWD has yet to return the draft Supplemental Agreement.  
                 
                 
                 
                     
             Section II.  Goods and Services Contracts     5