Name of Project  Contractor  Supply Cost Volume Contract Signing Day 1 of Delivery  Revised                                Day 1 of Delivery  Remarks
                 
1.0 MCWD Bulk Water Supply Contract (Compostela-Liloan-Consolacion Injection Points) Cebu Manila Water Development Incorporated Php 24.59 / cu.m. Year 1                    : 18,000 m3/day 18 Dec 2013 *09 Dec 2014   AGM Gabriente had informed the PMO that the BOD had approved the request of CMWD to extend the Day 1 of the year 2 of delivery to December 1, 2016. 
      Year 2 to Year 20 : 35,000 m3/day   09 Dec 2015 1 Dec 2016
            * - Day 1 of the 1st year of delivery per MCWD letter to CMWD dated December 5, 2014   To date, the CMWD has yet to complete the main injection point in Casili and the remaining works at the three (3) drop off points in Compostela, Liloan and Consolacion. 
                   
                 
                 
                 
                     