1.  INFRASTRUCTURE PROJECTS
Name of Project  Location Contractor Final Project Cost Date Completed Remarks
    1.0 Proposed Ø200mm x 454.0LM DI Rehabilitation Project at Pulpogan, Consolacion Pulpogan, Consolacion FDRCon Co., Inc. Php 5,250,000.98 May 31, 2016 Awaiting for the Contractor to submit the as-built drawings.
    2.0 Construction of Proposed Man-1 Pumping Station for the MCWD In-House Water Sourcing Program Sitio Pilit, Brgy. Cabancalan, Mandaue City, Cebu Dakay Construction and Development Corporation Php 5,739,002.00 May 6, 2016 The Contractor has yet to submit the As-Built Drawings, Operation and Maintenance Manual, and the Defects Liability Bond.
    3.0 Prop. DI Rehabilitation Project at Pajac, Lapulapu City Brgy. Pajac, Lapulapu City Rex E. Morales Construction Php 7,093,788.30 Mar 27, 2016 Awaiting for the Contractor to submit the as-built drawings.
    4.0 Prop. Pipeline Expansion for Cabancalan Bulk Water Supply Brgy. Cabancalan, Mandaue City Felman Builders and Contractors Php 16,744,730.61 Feb 29, 2016 Joint final inspection was conducted on February 29, 2016. Contractor has yet to submit the as-built drawings.
    5.0 Proposed Expansion/Lateral Project for Bacayan, Pit-os Bacayan, Pit-os, Cebu City New Culion Builders Co. Php 22,019,495.65 Jun 5, 2015  
    6.0 Proposed Ø300 mm D.I. Water Distribution Main  - Canduman, Mandaue City to Tigbao, Talamban, Cebu City Canduman, Mandaue City to Tigbao, Talamban, Cebu City Geo Transport & Construction, Inc. Php     Project is physically completed. The Mandaue section of the project had been deleted. PMO is processing the final amount for the closing of the project.
    7.0 Construction of Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program Brgy. Cubacub, Mandaue City Geo Transport & Construction, Inc. Php 9,001,428.00 Dec 2, 2015 The Certificate of Project Completion had been issued to the Contractor.
2. SUPPLY AND DELIVERY OF GOODS
Name of Project  Location Supplier Final Project Cost Date Completed Remarks
               
3. JOINT VENTURE PROJECTS
Name of Project  Location JV Partner Final Project Cost Date Completed Remarks
                 
       Section V.      Projects Completed in 2016         12
4. SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS
4. 1 WATER SYSTEM
Name of Project  Location Owner/Developer Final Project Cost Date Completed Remarks
    1.0 Prop. Water Distribution System for Villa Azalea Subdivision Phase 2 Brgy. Cotcot, Liloan, Cebu Mega Crown Realty and Development Corp. Php       5,964,029.61 Feb 17, 2016 Awaiting for the Developer to submit the as-built drawing.
    2.0 Prop. Water Sytem for Graceland 1 & Graceland Annex Subdivision Brgy. Buaya, Mactan, Lapulapu City Kaiser Urban Development Corp. Php          858,046.50 Mar 22, 2016  
    3.0 Prop. PVC Water Distribution System for Kaiser Townhouse II Estancia, Mandaue City Kaiser Urban Development Corp. Php       1,687,773.35 Mar 11, 2016  
4. 2 FLOWMETER ASSEMBLY AND VAULT                
  Name of Project  Location Owner/Developer Final Project Cost Date Completed Remarks
    1.0 Prop. Ø75mm Flowmeter Assembly for Midori  A.S. Fortuna Avenue, Mandaue City Cebu Landmasters, Inc. Php          439,333.20   Awaiting for the hydrotesting and disinfection result, and as-built plan.
    2.0 Prop. Ø75mm Surface Flow Meter for Mabolo Garden Flats Tres Borces St., Mabolo, Cebu City Primary Homes, Incorporated Php          334,970.76   Project is physically completed. However, the Developer has yet to pay for the guarantee deposit. Thus, the project is still awaiting for the final inspection.
    3.0 Prop. Ø100mm  Surface FlowMeter for Almiya Subdivision  Brgy. Canduman, Mandaue City, Cebu Aboitizland, Inc. Php          378,540.42 Jan 19, 2016 Final inspection was conducted on January 19, 2016.
    4.0 Prop. Ø100mm  Surface FlowMeter for Mivesa Garden Residences Salinas Drive Extension, Brgy. Lahug, Cebu City Cebu Landmasters, Inc. Php          793,185.53 Jan 18, 2016 Final inspection was conducted on January 18, 2016. Awaiting for the Developer to submit the as-built drawings.
       Section V.      Projects Completed in 2016         13 11