|
Name of
Project |
Contractor |
Supply Cost |
Volume |
Contract Signing |
Day 1 of Delivery |
Revised Day 1 of
Delivery |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
MCWD Bulk Water
Supply Contract (Compostela-Liloan-Consolacion Injection Points) |
Cebu Manila
Water Development Incorporated |
Php |
24.59 / cu.m. |
Year 1
: |
18,000 m3/day |
18 Dec 2013 |
*09 Dec 2014 |
|
The EXECOM had
approved the supply line lay-out and operational scheme proposed
by CMWD at the Casili injection point. The installation of the supply
line and the booster station at Casili is ongoing. |
|
CMWD has been
delivering 18,000 cu.m./day at the 3 drop-off points (Compostela, Liloan and
Consolacion) and at the Consolacion temporary main delivery point since January 5, 2015. Under the Contract,
CMWD will deliver 35,000 cu.m./day at the start of the second year. |
|
|
|
|
|
Year 2 to Year 20 : |
35,000 m3/day |
|
+09 Dec 2015 |
|
|
|
|
|
|
|
|
|
|
|
* - Day 1
of the 1st
year of delivery per MCWD letter to CMWD dated December 5, 2014 |
|
Acting GM Dalena on his May 5,
2016 letter to CMWD had suspended to a later time the interconnection at the
main injection point at Casili because of the El Niño. |
|
After it failed to replace the
temporary flowmeters and complete the flowmeter vaults within the specified
period, CMWD had asked for an extension on or before the day 1 of the Year 2
of delivery. During the July 15, 2015 EXECOM Meeting attended by CMWD, the
MCWD had granted CMWD's request but until October 2015 only. October 2015 had
ended but CMWD still failed to comply the above requirement. |
|
|
|
|
|
|
|
|
|
+ - Day 1 of the 2nd year of delivery |
|
Works at the temporary meter
vault and flowmeter assembly at the 3 drop-off points are still ongoing. The
BOD had given CMWD until the end of May 2016 to fully complete the 3 drop-off
points but the later had failed to do so. |
|
The installation of CMWD's
Ø700mm transmission line going to the existing Casili Reservoirs is about 98%
complete. Then AGM Singson informed PMO that the 3 reservoirs proposed by
CMWD were approved by the BOD. The PMO has yet to receive copy of said BOD Resolution.
The construction of the 3 reservoirs by CMWD has been going on without
coordination with the PMO. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
MCWD Septage Management Service
Contract (Phase I - Mactan Septage Management Service) |
Envirokonsult Equipment
Services, Incorporated |
Php |
800.00 / m3 |
Year 1 to Year 5 : |
150 m3/day |
23 Apr 2015 |
23 Apr 2016 |
30 Jul 2016 |
Under the
Contract, the Service Provider will construct a Septage Treatment Facility at
the MCWD property in Cordova, Cebu and shall collect, transport and treat the
septage and dispose the bio-solids. The term of the service contract is five
(5) years from the Day One of operation. |
|
|
|
|
|
|
|
|
|
|
|
(The Day 1 was
suspended on February 23, 2016 pending negotiations of the site development
works) |
|
The
installation of the septage treatment plant now nears completion. The Service
Provider is still working on the necessary permits and clearances to operate
the plant. |
|
|
|
|
|
|
|
|
|
|
|
|
The
Supplemental Agreement for the site development works at the MCWD Cordova
property where the septage treatment plant is constructed had been
approved. The site development cost is
PhP 818,315.86 with 45 calendar days duration. The Notice to Proceed was
issued last May 30, 2016. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Parallel with the issuance of
the NTP for the site development works, the Suspension Order dated February
23, 2016 suspending the Day 1 of operation was likewise lifted on May 30,
2016. Effectively, the new Day 1 will be on July 30, 2016. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
In its November 2015 letter to
Acting GM Dalena, CMWD had requested that it be allowed to start the year 2
of delivery (35,000 m3/day) thru the temporary injection point at Consolacion and
also asked an extension until May 2016 for the required storage tank. The
MCWD EXECOM has yet to decide on this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
II. Ongoing Supply and Installation of Goods 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|