Name of
Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply
Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. To date, however, the Supplier has yet to comply
with the data transmission requirement. |
|
The Apas Injection Point
(originally at BC Homes) has been supplying water to MCWD since December 21,
2011. To date, however, the Supplier has yet to comply with the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply
Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. To
date, however, the Supplier has yet to comply with the data transmission
requirement. |
|
The Banawa Injection Point has
been supplying water to MCWD since December 9, 2011. To date, however, the
Supplier has yet to comply with the data transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply
Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
The Marigondon-Gabi Injection
Point has been supplying water to MCWD since February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply
Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
10 Jun 2014 |
This JV
Contract has 3 injection points located at Guadalajara, Kabajar, and Quijada
in Brgy. Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has
been delivering water to MCWD since September, November and March,
respectively. |
|
This JV Contract has 3
injection points located at Guadalajara, Kabajar, and Quijada in Brgy.
Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has been
delivering water to MCWD since September, November and March, respectively. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The drop-off
point to be provided by the Supplier under the Amendment to TOR dated July
11, 2014, remains uncompleted. |
|
The drop-off point to be
provided by the Supplier under the Amendment to TOR dated July 11, 2014,
remains uncompleted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has yet to
comply with the data transmission requirement. AWC's hired IT Professional is
still working on this. |
|
AWC has yet to comply with the
data transmission requirement. AWC's hired IT Professional is still working
on this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have completed the
drop-off point and complied the data transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have completed the drop-off
point and complied the data transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply
Program - Pit-os Injection Point |
Abejo Waters Corporation |
4,800 |
m3/day |
PhP |
15.68 |
/m3 |
19 June 2013 |
18 June 2014 |
18 Jan 2015 |
The Pit-os
Injection Point has been delivering water into the MCWD distribution system
since March 12, 2015. |
|
|
Under this joint venture, AWC
will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has no
action until now on the installed flowmeters that were declared 'not fully complying with the
specifications' by the MSSD. AWC has the option to either upgrade the
existing flowmeters or replace them with new units. |
|
|
The Pit-os Injection Point has
been delivering water into the MCWD distribution system since March 12, 2015.
The volume of delivery however is below the required minimum. AWC is
presently working on one additional well to supplement its supply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has yet to
comply with the data transmission requirement. AWC's hired IT Professional is
still working on this. |
|
PMO had informed AWC that the
installed flowmeters do not fully meet the specifications per MSSD memo to
the PMO. AWC has the option to either upgrade the existing flowmeters as
suggested by the MSSD or replace them with new units. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Bulk Water Supply
Program - Cabancalan Injection Point |
Abejo Waters Corporation |
5,000 |
m3/day |
PhP |
15.68 |
/m3 |
25 Sept. 2013 |
24 Sept. 2014 |
30-Apr-16 |
Under this
joint venture, AWC will supply a minimum of 5,000m3 of water daily to MCWD . |
|
Under this joint venture, AWC
will supply a minimum of 5,000m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
The MCWD
EXECOM had approved the location of the meter vault proposed by AWC. It also
decided that the maximum pressure at the Cabancalan injection point shall
be115 psi. The corresponding amendment to the TOR is on process. |
|
AWC informed PMO that it will
operate 2 production wells only for this supply contract instead of the
previously planned 4 wells since the combined discharge of the completed 2
wells is more than enough to meet the required supply volume. |
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC reported
that the DPWH until now has not issued
an excavtion permit for the interconnection work. AWC continues to make
follow ups with the DPWH. |
|
AWC has asked approval for the
location of the meter vault about 100 meters away from the injection point.
The EXECOM has yet to rule on this request. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint Venture Projects |
7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|