Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks (February 2016) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
Under HA1 Package 8 (Corner Poblacion Cordova to Corner Basak-Marigondon
Road, Lapulapu City) |
Rex E. Morales Construction |
PhP |
65,115,509.33 |
|
65,115,509.33 |
04 Mar 2016 |
28 Nov 2016 |
|
0.00% |
0.00% |
0.00% |
PMO is
awaiting for the BAC's endorsement of this project. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
Under Hydraulic Area 1 Package 5 (Brgy. Pajo & Pusok, Lapulapu City) |
M.E. Sicat Construction, Inc. |
PhP |
100,237,800.00 |
|
100,237,800.00 |
15 Feb 2016 |
11 Sep 2016 |
|
0.00% |
0.00% |
0.00% |
Contractor is
on the process of procurement of materials. It is coordinating with PMO
regarding the MCWD personnel who will be conducting the in-plant inspection
of the pipes and fittings in India.
MCWD has already released the 15% advance payment to the Contractor. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
Under Hydraulic Area 1 Package 10 (Pusok-Matumbo Road and Mustang Road, Brgy.
Pusok and Brgy. Mactan, Lapulapu City) |
M.E. Sicat Construction, Inc. |
PhP |
30,800,000.00 |
|
30,800,000.00 |
15 Feb 2016 |
12 Aug 2016 |
|
0.00% |
0.00% |
0.00% |
Contractor is
on the process of procurement of materials. It is coordinating with PMO
regarding the MCWD personnel who will be conducting the in-plant inspection
of the pipes and fittings in India. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 9 (Juan Sitoy St., Brgy. Catarman, Cordova and
M.V. Patalinghug Avenue, Lapulapu City) |
JFAP Construction |
PhP |
49,856,139.71 |
|
49,856,139.71 |
22 Oct 2015 |
17 Jul 2016 |
- |
43.09% |
0.00% |
-43.09% |
Majority of
the materials that were intended for this project have already been delivered
and passed MCWD testing. Contractor is expected to start pipelaying on April
2016. |
|
Portions of the materials
imported from India have already arrived. The Contractor have already
requested for the testing of these materials. Full delivery of the materials
is expected on March 2016. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 11 (Brgy. Jubay, Liloan, Cebu) |
A.L. Gantuangco Construction |
PhP |
9,214,465.00 |
|
9,214,465.00 |
10 Sep 2015 |
07 Mar 2016 |
11 Apr 2016 |
92.89% |
56.44% |
-36.45% |
This project
consists of pipelaying in a single stretch only. Except for the bridge
crossing pipe and a small portionof the pipeline which is yet to be
installed, pipeline installation is already complete and passed hydrotesting.
Other works which have yet to be accomplished include: hydrotesting,
disinfection, restoration and interconnection. PMO instructed the Contractor
to resubmit the detailed structural design with computation for the bridge
crossing using approved parameters. |
|
Pipelaying is almost complete.
The Contractor intends to submit the detailed structural design with
computation and costing for the bridge crossing pipeline on March 2016.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 7 (M.L. Quezon Avenue and Babag, Lapulapu
City) |
JFAP Construction |
PhP |
35,078,950.22 |
|
35,078,950.22 |
10 Sep 2015 |
16 May 2016 |
20 Jun 2016 |
48.40% |
50.32% |
1.92% |
The pipelaying
works for this project is substantially completed and passed hydrotesting.
Works remaining include: installation of assemblies/valves, hydrotesting,
restoration, disinfection and interconnection. |
|
The Contractor started
pipelaying activities with two teams working separately on two areas.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
27 Mar 2016 |
100.00% |
100.00% |
0.00% |
Project is
already completed on March 27, 2016. Awaiting for the Contractor to submit
the as-built drawings. |
|
The Contractor has started and completed the actual pipelaying works
within this month. Contractor is still awaiting for the delivery of the
fittings to be used for the installation of the appurtenances.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 (Mandaue City and Lapulapu City, Cebu) |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
25 Feb 2016 |
100.00% |
78.31% |
-21.69% |
The project is composed of
several areas in Lapulapu City and Mandaue City. Pipelaying works for both
areas is physically complete. Works remaining include asphalt restoration,
painting of the barricades for stub-outs and disinfection. |
|
The project is composed of
several areas in Lapulapu City and Mandaue City. Pipelaying works for the
areas in Lapulapu City is complete. Most of the pipelines have already passed
the hydrotesting. The Contractor is focused on the pipelaying works on the remaining
areas in Mandaue City.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 (Consolacion, Cebu) |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
10 Apr 2016 |
97.38% |
35.08% |
-62.30% |
Pipelaying works is completed
except for the two areas namely: road to LDU and the road to Redwood
Subdivision. Contractor is preparing the newly installed pipeline for
hydrotesting. |
|
The project is composed of
several areas in Consolacion, Cebu. Pipelaying works for the area along the
North Coastal Road is completed. Contractor is preparing this completed
pipeline for hydrotesting.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 (Consolacion & Liloan, Cebu) |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
09 May 2016 |
87.06% |
68.59% |
-18.47% |
Pipelaying works for all the
areas under this project is completed and passed hydrotesting. Remaining
works are:disinfection, interconnection and restoration. |
|
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 (Compostela and Liloan, Cebu) |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
09 May 2016 |
88.88% |
35.88% |
-53.00% |
PIpelaying works is almost
complete. PMO advised the Contractor for the former's cost estimates of a
possible variation order brought about by the obstruction caused by the box
culvert embankment. PMO and the Contractor will be negotiating the cost for this
matter. The same will be submitted to the BOD for approval. |
|
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
Also, the revised PERT/CPM of the project had been approved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
15.37% |
-84.63% |
The Contractor has already
started project implementation on December 22, 2015. Project is ongoing with
liquidated damages to be imposed upon the Contractor. |
|
The Contractor has already
started project implementation on December 22, 2015. Project is ongoing with
liquidated damages to be imposed upon the Contractor. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
85.83% |
-14.17% |
Pipelaying works is physically
completed. Works that are not yet accomplished include pipeline disinfection,
asphalt restoration, and installation of AV/AR. |
|
Remaining works of the project
are the following: hydrotesting, interconnection, installation of valves, and
disinfection. Liquidated damages shall be imposed upon the Contractor for its
failure to complete the project within the contract duration. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The termination of this project
is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The termination of this project
is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay Construction and
Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
95.66% |
-4.34% |
Since January this year when the
Contractor was informed of the approval by the BOD of the deletion of the
interconnection work, it's only this month that the Contractor has resumed
work to complete the remaining works. The installation of the AV/AR and BOV
assemblies and road-crossing restoration are the remaining works. The
installation of the BOV assembly is ongoing. |
|
Variation Order No.1 that covers, among others, the deletion
of the interconnection work ensuing from the non-issuance by DPWH of the
excavation permit was approved by the BOD. With its approval, the PMO had
ordered the Contractor to complete the remaining works. Works to complete the
remaining works is ongoing and
expected to be completed by March 2016. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from January 1, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from January 1, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17.0 |
Proposed Mactan Water Supply
Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
The EXECOM has instructed the PMO to submit to LD all
pertinent documents for the mutual termination of the project. |
|
Dr. Pericles Dakay, the CEO of
Dakay Construction, has sent a letter to MCWD Acting General Manager Noel R.
Dalena informing the latter of the former's intention to mutually terminate
the project. During its meeting, the EXECOM had agreed to recommend to the
BOD the Contractor's intention to terminate the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|