Name of
Project |
Contractor |
Supply Cost |
Volume |
Contract Signing |
Day 1 of Delivery |
Revised Day 1 of
Delivery |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
MCWD Bulk Water
Supply Contract (Compostela-Liloan-Consolacion Injection Points) |
Cebu Manila
Water Development Incorporated |
Php |
24.59 / cu.m. |
Year 1
: |
18,000 m3/day |
18 Dec 2013 |
*09 Dec 2014 |
|
Works at the 3
drop-off points to comply with the approved flowmeter assembly and injection
scheme are ongoing. |
|
Works at the 3
drop-off points to comply with the approved flowmeter assembly and injection
scheme are ongoing. |
|
|
|
|
|
|
|
Year 2 to Year 20 : |
35,000 m3/day |
|
+09 Dec 2015 |
+16 Jul 2016 |
|
|
|
|
|
|
|
|
|
|
|
|
* - Day 1
of the 1st
year of delivery per MCWD letter to CMWD dated December 5, 2014 |
+ - Revise Day 1 of
Year 2 based on the June 28, 2016 letter of Acting GM Dalena |
The
synchronized interconnection of CMWD and MCWD-JICA funded project has been
concluded. However, CMWD has yet to install the ultrasonic water level
equipment that is necessary to prompt operation of the booster pump at a set
elevation. |
|
At the Casili injection point, works to
complete the flowmeter assembly is ongoing. The ultrasonic level instrument
to be installed at the CMWD reservoirs that will trigger the start/stop of
the booster pumps have yet to be delivered. |
|
|
|
|
|
|
|
|
|
|
|
+ - Day 1 of
the 2nd year of
delivery |
MCWD had
ordered the Contractor to fully backfill the interconnection point to allow
passage of JICA equipment until advised by MCWD to dig-up the same. |
|
Acting GM Dalena on his June 28, 2016 letter had informed
CMWD that the previously scheduled June 28-30, 2016 interconnection at the
Casili injection point will be moved to another date. Further, MCWD will
extend the Day 1 of the Year 2 of delivery correspondingly if the
interconnection is scheduled beyond the approved July 16, 2016 Day 1 of Year
2. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
MCWD Septage Management Service
Contract (Phase I - Mactan Septage Management Service) |
Envirokonsult Equipment
Services, Incorporated |
Php |
800.00 / m3 |
Year 1 to Year 5 : |
150 m3/day |
23 Apr 2015 |
23 Apr 2016 |
30 Jul 2016 |
Under the
Contract, the Service Provider will construct a Septage Treatment Facility at
the MCWD property in Cordova, Cebu and shall collect, transport and treat the
septage and dispose the bio-solids. The term of the service contract is five
(5) years from the Day One of operation. |
|
Under the Contract, the Service
Provider will construct a Septage Treatment Facility at the MCWD property in
Cordova, Cebu and shall collect, transport and treat the septage and dispose
the bio-solids. The term of the service contract is five (5) years from the
Day One of operation. |
|
|
|
|
|
|
|
|
|
|
|
(The Day 1 was
suspended on February 23, 2016 pending negotiations of the site development
works) |
|
Construction
of the septage treatment plant is now completed except for the
electromagnetic flowmeter. Contractor has proposed to use AC powered IP65
rating flowmeter in lieu of the DC powered IP65 rating that is required by
MCWD. The matter is with the EXECOM for decision.
The approved Day 1 of operation had lapsed last July 30, 2016.
Sludge seeding is ongoing. |
|
The installation of the septage
treatment plant is nearing completion.
Meanwhile, the site development work had already started and is now
75% complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Service Provider is still
working on the necessary permits and clearances to operate the plant. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
II. Ongoing Supply and Installation of Goods 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|