Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks (December 2015) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 9 |
JFAP Construction |
PhP |
49,856,139.71 |
|
49,856,139.71 |
22 Oct 2015 |
17 Jul 2016 |
- |
6.31% |
0.00% |
-6.31% |
The Contractor
has informed PMO that their (Contractor) supplier has reset the delivery of
the DI pipes and fittings to mid February 2016. |
|
The pipes and fittings from
India are in transit. It is expected to arrive at the port of Cebu by
mid-January 2016. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 11 |
A.L. Gantuangco Construction |
PhP |
9,214,465.00 |
|
9,214,465.00 |
10 Sep 2015 |
07 Mar 2016 |
- |
65.90% |
13.82% |
-52.08% |
PIpelaying is
ongoing. The bridge crossing portion had to be revised since the DPWH does
not allow the pipe to be attached to the bridge. The Engineering Department
had already made the initial design of the bridge crossing pipeline. PMO has
advised the Contractor for the cost negotiation of the newdesign. Once PMO
and the Contractor reached an agreement for the cost, PMO will make a
variation order of the new bridge crossing design and endorse the same to the
BOD.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. If approved, the target accomplishment may
be lower and so wilth the slippage. |
|
The pipes and fittings from
India have already arrived at the port of Cebu in the later part of December
2015. Contractor was advised to make a written request for inspection of said
materials. Implementation of the project is expected to start by January
2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 7 |
JFAP Construction |
PhP |
35,078,950.22 |
|
35,078,950.22 |
10 Sep 2015 |
16 May 2016 |
- |
32.83% |
0.00% |
-32.83% |
The Contractor
has started breaking of the concrete pavement along the concrete gutter
during the last week of January 2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. If approved, the target accomplishment may
be lower and so wilth the slippage. |
|
The pipes and fittings from
India have already arrived at the port of Cebu in the later part of December
2015. Contractor was advised to make a written request for inspection of said
materials. Implementation of the project is expected to start by January
2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
- |
100.00% |
0.00% |
-100.00% |
Contractor has
conducted stake-out and pavement breaking along the sidewalk during the last
week of January 2016. Pipelaying works is expected to start on February
2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. If approved, the target accomplishment may
be lower and so wilth the slippage. |
|
The pipes and fittings from
India have already arrived at the port of Cebu in the later part of December
2015. Contractor was advised to make a written request for inspection of said
materials. Implementation of the project is expected to start by January
2016.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
100.00% |
66.74% |
-33.26% |
Contractor is already in full
swing with the project implementation.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. If approved, the target accomplishment may
be lower and so wilth the slippage. |
|
Contractor is already in full
swing with the project implementation. They have two (2) teams working on
different areas of the project.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
100.00% |
19.25% |
-80.75% |
Contractor is already in full
swing with the project implementation.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. If approved, the target accomplishment may
be lower and so with the slippage. |
|
Contractor is already in full
swing with the project implementation.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
99.16% |
62.06% |
-37.10% |
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. If approved, the target
accomplishment may be lower and so with the slippage. |
|
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
98.83% |
35.88% |
-62.95% |
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. If approved, the target accomplishment may
be lower and so with the slippage. |
|
Contractor is already in full
swing with the project implementation. Some of the already installed pipes
has passed hydrotesting.
The MCWD BOD on its Resolution No. 184-2015 dated October 13, 2015 had
approved and authorized the contractor to suspend digging activities and/or
excavation works effective July 15, 2015 until October 14, 2015 in compliance
with the directive of DPWH without penalty. Consequently, the PERT/CPM had to
be revised and it is on process. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
8.87% |
-91.13% |
The Contractor has already
started project implementation on December 22, 2015. Project is ongoing with
liquidated damages to be imposed upon the Contractor. |
|
The Contractor has already
started project implementation on December 22, 2015. Project is ongoing with
liquidated damages to be imposed upon the Contractor. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
61.12% |
-38.88% |
Remaining works of the project
are the following: hydrotesting, interconnection, installation of valves, and
disinfection. Liquidated damages shall be imposed upon the Contractor for its
failure to complete the project within the contract duration. |
|
Remaining works of the project
are the following: hydrotesting, interconnection, installation of valves, and
disinfection. Liquidated damages shall be imposed upon the Contractor for its
failure to complete the project within the contract duration. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The termination of this project
is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The termination of this project
is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay Construction and
Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
84.81% |
-15.19% |
OIC - AGM Tabasa had informed the
PMO that the proposed Variation Order No.1 deleting the interconnection work
from the Contract ensuing from the non-issuance by DPWH of the necessary
excavation permit was approved by the BOD. The PMO is awaiting the BOD
Resolution before it will inform the Contractor about this. |
|
OIC - AGM Tabasa had informed the PMO that the proposed
Variation Order No.1 deleting the interconnection work from the Contract
ensuing from the non-issuance by DPWH of the necessary excavation permit was
approved by the BOD. The PMO is awaiting the BOD Resolution before it will
inform the Contractor about this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from January 1, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from January 1, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. PMO is still awaiting for the said letter. |
|
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. PMO is still awaiting for the said letter. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
Contractor has
made repairs for the barricades that were damaged. Contractor has also
installed 2 unit blow-off valves and 1 unit commercial fire hydrant. Hopefully the interconnection works could
be completed by February 2016. |
|
The Contractor has already made
exploration for the interconnection works in Brgy. Tabok, Mandaue City.
Interconnection works is expected to be completed by January 2016. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|