Name of Project  Brief Description of the Project Subdivision/Hotel/Condo Name Developer / Owner MCWD Supervising Unit Project Amount Project Duration Date Started Target Completion Date Accomplish-          ment                             To Date Remarks Previous Month's Remarks (November 2015)
1. Water System                  
1.0 Prop. Water Distribution System for EastGate Subdivision (Matumbo, Pusok, Lapulapu) 49.54 LM x 75mm dia EastGate Subdivision Urban Enclaves Inc. Project Management Office PhP      514,061.34 11 CD Jul 15, 2011 Jul 26, 2011 20.00% Upon site inspection by MCWD inspector, developer has installed individual service connections directly to the MCWD stub-out outside of the subdivision. It is suggesting a possibility that the contractor may cancel the project. Upon site inspection by MCWD inspector, developer has installed individual service connections directly to the MCWD stub-out outside of the subdivision. It is suggesting a possibility that the contractor may cancel the project.
2.0 Prop. PVC Water Distribution System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) 484 LM x 75mm dia., 781 LM x 100mm dia., 167 LM x 150mm dia. Amara Subdivision Cebu Holdings, Inc. Project Management Office PhP   92 CD May 15, 2012 Aug 14, 2012 96.00% Contractor is on the process of purchasing the handhole cover and AV/AR head. Contractor is on the process of purchasing the handhole cover and AV/AR head.
3.0 Prop. Rerouting of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu)  1,650 LM x 150mm dia. Amara Subdivision Cebu Holdings, Inc. Project Management Office PhP   92 CD May 15, 2012 Aug 14, 2012 98.00% The only remaining work is the disinfection of a portion of the water system of the subdivision at phase 3b. The only remaining work is the disinfection of a portion of the water system of the subdivision at phase 3b.
4.0 Prop. Water Distribution System for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City) 6,920 LM x 75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia., 151 LM x 250mm dia. Pueblo De Oro Communities (Horizon, La Aldea Del Mar, and Parkplace) Pueblo De Oro Development Corp. Project Management Office PhP ############       40.00% Developer is implementing the pipelaying works on this project area by area. Seven areas have already been turned-over to MCWD. Pipelaying is ongoing for the next area. Developer is implementing the pipelaying works on this project area by area. Five areas have already been turned-over to MCWD. Pipelaying is ongoing for the next area.
5.0 Prop. PVC Water Distribution System for Kaiser Townhouse II 510 LM x 100mm dia. PVC and 75mm dia. PVC water distribution line Kaiser Townhouse II Kaiser Urban Development Corp. Project Management Office PhP   1,687,773.35   Jun 24, 2013   80.00% This project is composed of two phases - Phase 1 and Phase 2. Phase 1 and Phase 2 have been completed and is expected for final inspection next month. Remaining works are hydrotesting, disinfection and interconnection. Developer has already developed the Phase 2 area. Following this, PMO has instructed the Developer to conduct re-hydrotesting for this area. Developer is expected to conduct the re-hydrotesting by December 2015.
6.0 Prop. Water Distribution Systems for Mactan Plains Subdivision 114 LM x 100mm dia. PVC and 810 LM 75mm dia. PVC water distribution line Mactan Plains Subdivision Pacific Land Ventures and Property Development, Inc. Project Management Office PhP   1,617,764.80   Jun 25, 2013     Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
7.0 Prop. Water System Design for Goldmine Residences (Bangkal-Mahayahay-Soong, Lapulapu City) 236 LM x 150mm dia. PVC, 32 LM 100mm dia. PVC, 152 LM 75mm dia. PVC, 617 LM 50mm dia. PVC Goldmine Residences Heritage Supreme Land Developer, Inc. Project Management Office PhP   3,215,481.65   Oct 14, 2013     Developer is awaiting for the well to be constructed by EWRD-KC. After the well, the installation of the interconnecting pipeline will have to be done by MCWD before the water system of the subdivision will be implemented. Developer is awaiting for the well to be constructed by EWRD-KC. After the well, the installation of the interconnecting pipeline will have to be done by MCWD before the water system of the subdivision will be implemented.
8.0 Prop. Water Distribution Systems for City Homes - Mandaue (J.S. Alinsug St., Mandaue City, Cebu) 42 LM 75mm dia. PVC, 218 LM 50mm dia. PVC City Homes Mandaue Grand Land, Inc. Project Management Office PhP      870,061.25   Oct 23, 2013   85.00% Remaining works are hydrotesting, flushing and disinfection. Remaining works are hydrotesting, flushing and disinfection.
9.0 Prop. Water Sytem for Graceland 1 & Graceland Annex Subdivision (Brgy. Buaya, Mactan, Lapulapu City) 39 lm x 100mm dia PVC, 29 lm x 50mm dia PVC Graceland 1 and Graceland Annex Subdivision Kaiser Urban Development Corp. Project Management Office PhP      858,046.50 11 Working Days Jul 7, 2014 Jul 21, 2014 50.00% Pipelaying for the Phase 1 section of the project has already passed hydrotesting. It is awaiting for disinfection. Pipelaying is ongoing.
10.0 Prop. Water System Design for South Covina Subdivision (Brgy. Dumlog, Talisay City, Cebu) 42 lm x 100mm dia PVC, 110 lm x 75mm dia PVC, and 346 lm x 50mm dia PVC South Covina Subdivision Athecor Development Corporation Project Management Office PhP   1,177,338.75 71 Working Days Sep 18, 2014 Dec 17, 2014   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
11.0 Prop. Water Distribution System for Peninsula Subdivision (Sudtungan Road, Brgy. Basak, Lapulapu City) 42 lm x 100mm dia PVC, 110 lm x 75mm dia PVC, and 346 lm x 50mm dia PVC Peninsula Place Subdivision Peninsula Resort Corporation Project Management Office PhP   1,196,027.58 52 Calendar Days Oct 1, 2014 Nov 21, 2014 60.00% Remaining works are: installation of stubouts, fire hydrants, and av/ar. Pipelaying is ongoing.
12.0 Prop. Water Distribution System for Rose Pike Subdivision (Forest Hills, Kalubihan, Banawa, Brgy. Guadalupe, Cebu City) 228 lm x 50mm dia PVC Rose Pike Subdivision F.S. Baltazar Builders Project Management Office PhP   1,415,707.20 45 Calendar Days Feb 17, 2015 Apr 2, 2015 80.00% This project project is composed of two phases - Phase 1 and Phase 2. Phase 1 is physically completed. Developer has requested for the partial turn-over of this. Phase 2 is ongoing at 30% accomplishment. Pipelaying is ongoing.
13.0 Prop. Ø100mm x 373.0 lm UPVC Expansion Project for Colorado Homes Dos (Brgy. Jubay, Liloan, Cebu) 373 lm x 100mm dia PVC Colorado Homes Dos Commonwealth Estate, Inc. Project Management Office PhP   1,640,244.69 45
Calendar Days
Jul 15, 2015 Aug 28, 2015 65% Remaining works are: bridge crossing pipeline, fire hydrant installation,  disinfection and interconnection. Pipelaying is ongoing.
14.0 Prop.Water Distribution System for Villa Sebastiana Subdivision (Brgy. Tawason, Mandaue City, Cebu) 126 lm x 100mm dia PVC, 72 lm x 75mm dia PVC, 438 lm x 50mm dia PVC Villa Sebastiana Subdivision Aidfaz Development Corporation Project Management Office PhP   1,343,438.70 38
Working Days
Jul 29, 2015 Sep 14, 2015   Developer is on the process of procurement of materials and excavation permit. Developer is on the process of procurement of materials and excavation permit.
15.0 Prop.Water Distribution System for Blessed Sacrament Subdivision (Kagudoy Road, Brgy. Basak, Lapulapu City) 96 lm x 100mm dia PVC, 162 lm x 75mm dia PVC, 588 lm x 50mm dia PVC Blessed Sacrament Subdivision Cebu Peoples Multi Purpose Cooperative Project Management Office PhP   2,673,187.14 - Nov 16, 2015 -   Developer is on the process of procurement of materials and excavation permit. Developer is on the process of procurement of materials and excavation permit.
16.0 Prop.Water Distribution System for Brookridge Subdivision (Dr. Pablo Abella St., Labangon, Cebu City) 140 lm x 100mm dia PVC, 201 lm x 50mm dia PVC, 12 lm x 50mm dia GI Brookridge Subdivision Primary Homes, Incorporated Project Management Office PhP   2,414,108.22 41 Working Days Feb 4, 2016 Mar 22, 2016   Developer is on the process of procurement of materials and excavation permit. Developer is on the process of procurement of materials and excavation permit.
Section IV.      Ongoing Subdivision/Hotel/Condo Water System Projects     9                                                                  
Name of Project  Brief Description of the Project Subdivision/Hotel/Condo Name Developer / Owner MCWD Supervising Unit Project Amount Project Duration Date Started Target Completion Date Accomplish-          ment                             To Date Remarks
2. Flowmeter Assembly and Vault                  
1.0 Prop. Ø100mm Flowmeter Enclosed in Reinforced Concrete Vault for Alegria Palms Subdivision 2 (Brgy. Gabi, Cordova, Cebu) dia.100mm flowmeter, construction of reinforced concrete vault & interconnection Alegria Palms Subdivision 2 Commonwealth Estate, Inc. Project Management Office PhP   1,216,026.49 50 CD May 29, 2013 Jul 17, 2013   No activity conducted during the month. Developer may have problem with the procurement of the excavation permit. No activity conducted during the month. Developer may have problem with the procurement of the excavation permit.
2.0 Prop. Ø100mm Flow Meter for Marco Polo Residences (Veterans Drive, Nivel Hills, Apas, Cebu City) dia. 100mm large meter assembly & interconnection Marco Polo Residences Federal Land, Inc. Project Management Office PhP      535,054.44 14 WD Mar 10, 2014 Mar 28, 2014   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
3.0 Prop. Ø100mm Surface Mounted Bulkmeter for One Pavilion Place, (Banawa, Guadalupe, Cebu City) dia. 100mm large meter assembly & interconnection One Pavilion Place Goldpeach Properties Corp. Project Management Office PhP      892,244.28 39 CD May 5, 2014     Materials are availlable already. However, DPWH had denied Developer's request for excavation permit. Developer's existing Ø 25mm  pipeline source was already upgraded to Ø 50mm as a temporary source of water supply. Materials are availlable already. However, DPWH had denied Developer's request for excavation permit. Developer's existing Ø 25mm  pipeline source was already upgraded to Ø 50mm as a temporary source of water supply.
4.0 Prop. Ø75mm Surface Flow Meter for Eagle's Nest (Canduman, Mandaue City, Cebu) dia.75mm large meter, large meter assembly & interconnection Eagle's Nest Primary Homes, Incorporated Project Management Office PhP      363,680.52 15 Working Days Aug 18, 2014 Sep 1, 2014   Developer is on the process of procurement of materials and permit. Developer may have a problem  with the excavation permit from the DPWH. Developer is on the process of procurement of materials and permit. Developer may have a problem  with the excavation permit from the DPWH.
5.0 Prop. Ø150mm Surface Flow Meter for Astana Subdivision (Calawisan, Lapulapu City) dia. 150mm large meter, large meter assembly,  10 l.m. of Ø 150mm water distribution line & interconnection Astana Subdivision Johndorf Ventures Corporation Project Management Office PhP      564,233.88 20 Working Days Sep 3, 2014 Sep 26, 2014   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
6.0 Prop. Ø150mm  Bulk Meter Connection for Sunrise Place Subdivision (Sitio Malinao Brgy. Agus, Lapulapu City) dia. 150mm large meter and assembly, 10 l.m. of Ø 150mm PVC water distribution line Sunrise Place Subdivision Filinvest Land, Inc. Project Management Office PhP      573,409.74 25 Working Days Mar 18, 2015 Apr 15, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
7.0 Prop. Ø75mm  Surface FlowMeter for Corinthian Residences (Andres Abellana St., Guadalupe, Cebu City) dia. 75mm large meter and assembly, 12 l.m. of Ø 75mm PVC water distribution line Corinthian Residences Landtraders World Properties Corp. Project Management Office PhP      532,247.12 9
Working Days
May 6, 2015 May 16, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
8.0 Prop. Ø75mm  Surface FlowMeter for Park Point Residences (Ayala Business Park, Cebu City) dia. 75mm large meter and assembly, 6 l.m. of Ø 150mm PVC water distribution line Park Point Residences Ayala Land, Inc. Project Management Office PhP      545,657.97 8
Working Days
Jun 3, 2015 Jun 21, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
9.0 Prop. Ø150mm  Surface FlowMeter for Priveya Hills Subdivision (Talamban, Cebu City) dia. 150mm large meter and assembly, 18 l.m. of Ø 150mm PVC water distribution line Priveya Hills Subdivision Aboitizland, Inc. Project Management Office PhP      824,138.35 10
Working Days
Jun 30, 2015 Jul 18, 2015   Developer is on the process of procurement of materials. Pipeline is already interconnected to the MCWD main line. PMO had allowed the interconnection so as to avoid future conflict with the ongoing asphalting works that will affect the interconnecting point. Developer is on the process of procurement of materials.
10.0 Prop. Ø750mm  Surface FlowMeter for San Pio Subdivision (Dumlog, Talisay City, Cebu) dia. 75mm large meter and assembly, 7 l.m. of Ø 75mm PVC water distribution line & interconnection San Pio Subdivision Justice, Peace & Integrity of Creation - Integrated Development Center, Inc. (JPIC-IDC) Project Management Office PhP      527,063.13 15
Calendar Days
Jul 8, 2015 Jul 22, 2015   Some of the already procured materials have undergone testing. Developer is on the process of procurement of the other materials.   
11.0 Prop. Ø150mm  Surface FlowMeter for Eastland Yati Village (Phase 1-3) (Yati, Liloan, Cebu) dia. 150mm large meter and assembly, 282 l.m. of Ø 150mm PVC water distribution line & interconnection Eastland Yati Village (Phase 1-3) Eastland Property Ventures, Inc. Project Management Office PhP   1,618,076.10 45
Calendar Days
Jul 14, 2015 Aug 27, 2015   Developer had already the materials and permit. Awaiting for the developer to start work on the interconnecting pipeline. Developer is on the process of procurement of materials.
12.0 Prop. Ø100mm  Surface FlowMeter for Filinvest Cyberzone (Salinas Drive corner Geonson St., Lahug, Cebu City) dia. 100mm large meter and assembly & interconnection Filinvest Cyberzone Cyberzone Properties, Inc. Project Management Office PhP      430,929.12 20 Working Days Aug 4, 2015 Aug 31, 2015   Project works is ongoing. Developer is on the process of procurement of materials. Completed on February 9, 2016
13.0 Revised Ø75mm Surface Flow Meter for Bamboo Bay Community (Subangdaku, Mandaue City) dia. 75mm large meter and assembly, 55 l.m. of Ø 75mm PVC water distribution line & interconnection Bamboo Bay Community Contempo Property Holdings, Inc. Project Management Office PhP      725,460.93 30 Calendar Days Sep 11, 2015 Oct 10, 2015   Materials are already available. Developer is awaiting for the permit from DPWH. Developer is on the process of procurement of materials.
14.0 Prop. Ø75mm  Surface Flow Meter for Palm River Phase 1 (Biasong, Pooc, Talisay City) dia. 75mm large meter and assembly,  24 l.m. of Ø 75mm uPVC water distribution line Palm River Phase 1 Deo Homes and Property Development, Inc. Project Management Office PhP      548,568.09 9 Calendar Days Dec 14, 2015 Dec 22, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
Section IV.      Ongoing Subdivision/Hotel/Condo Water System Projects    10