Name of
Project |
Brief Description of
the Project |
Subdivision/Hotel/Condo
Name |
Developer / Owner |
MCWD Supervising Unit |
Project
Amount |
Project Duration |
Date Started |
Target Completion Date |
Accomplish- ment To Date |
Remarks |
|
Previous Month's
Remarks (November 2015) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Water System |
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Water Distribution System
for EastGate Subdivision (Matumbo, Pusok, Lapulapu) |
49.54 LM x
75mm dia |
EastGate Subdivision |
Urban Enclaves Inc. |
Project Management Office |
PhP |
514,061.34 |
11 CD |
Jul 15, 2011 |
Jul 26, 2011 |
20.00% |
Upon site inspection by MCWD
inspector, developer has installed individual service connections directly to
the MCWD stub-out outside of the subdivision. It is suggesting a possibility
that the contractor may cancel the project. |
|
Upon site inspection by MCWD inspector, developer has
installed individual service connections directly to the MCWD stub-out
outside of the subdivision. It is suggesting a possibility that the
contractor may cancel the project. |
|
|
|
2.0 |
Prop. PVC Water Distribution
System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) |
484 LM x 75mm
dia., 781 LM x 100mm dia., 167 LM x 150mm dia. |
Amara Subdivision |
Cebu Holdings, Inc. |
Project Management Office |
PhP |
|
92 CD |
May 15, 2012 |
Aug 14, 2012 |
96.00% |
Contractor is on the process of
purchasing the handhole cover and AV/AR head. |
|
Contractor is on the process of
purchasing the handhole cover and AV/AR head. |
|
|
|
3.0 |
Prop. Rerouting
of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu) |
1,650 LM x 150mm dia. |
Amara
Subdivision |
Cebu Holdings, Inc. |
Project
Management Office |
PhP |
|
92 CD |
May 15, 2012 |
Aug 14, 2012 |
98.00% |
The only
remaining work is the disinfection of a portion of the water system of the
subdivision at phase 3b. |
|
The only
remaining work is the disinfection of a portion of the water system of the
subdivision at phase 3b. |
|
|
|
4.0 |
Prop. Water Distribution System
for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City) |
6,920 LM x
75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia.,
151 LM x 250mm dia. |
Pueblo De Oro Communities
(Horizon, La Aldea Del Mar, and Parkplace) |
Pueblo De Oro Development Corp. |
Project
Management Office |
PhP |
############ |
|
|
|
40.00% |
Developer is implementing the
pipelaying works on this project area by area. Seven areas have already been
turned-over to MCWD. Pipelaying is ongoing for the next area. |
|
Developer is implementing the
pipelaying works on this project area by area. Five areas have already been
turned-over to MCWD. Pipelaying is ongoing for the next area. |
|
|
|
5.0 |
Prop. PVC Water
Distribution System for Kaiser Townhouse II |
510
LM x 100mm dia. PVC and 75mm dia. PVC water distribution line |
Kaiser
Townhouse II |
Kaiser Urban
Development Corp. |
Project
Management Office |
PhP |
1,687,773.35 |
|
Jun 24, 2013 |
|
80.00% |
This project is
composed of two phases - Phase 1 and Phase 2. Phase 1 and Phase 2 have been
completed and is expected for final inspection next month. |
|
Remaining works
are hydrotesting, disinfection and interconnection. Developer has already
developed the Phase 2 area. Following this, PMO has instructed the Developer
to conduct re-hydrotesting for this area. Developer is expected to conduct
the re-hydrotesting by December 2015. |
|
|
6.0 |
Prop. Water
Distribution Systems for Mactan Plains Subdivision |
114
LM x 100mm dia. PVC and 810 LM 75mm dia. PVC water distribution line |
Mactan Plains
Subdivision |
Pacific Land
Ventures and Property Development, Inc. |
Project
Management Office |
PhP |
1,617,764.80 |
|
Jun 25, 2013 |
|
|
Developer is on
the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
7.0 |
Prop. Water
System Design for Goldmine Residences (Bangkal-Mahayahay-Soong, Lapulapu
City) |
236
LM x 150mm dia. PVC, 32 LM 100mm dia. PVC, 152 LM 75mm dia. PVC, 617 LM 50mm
dia. PVC |
Goldmine
Residences |
Heritage Supreme
Land Developer, Inc. |
Project
Management Office |
PhP |
3,215,481.65 |
|
Oct 14, 2013 |
|
|
Developer is
awaiting for the well to be constructed by EWRD-KC. After the well, the
installation of the interconnecting pipeline will have to be done by MCWD
before the water system of the subdivision will be implemented. |
|
Developer is
awaiting for the well to be constructed by EWRD-KC. After the well, the
installation of the interconnecting pipeline will have to be done by MCWD
before the water system of the subdivision will be implemented. |
|
|
8.0 |
Prop. Water
Distribution Systems for City Homes - Mandaue (J.S. Alinsug St., Mandaue
City, Cebu) |
42
LM 75mm dia. PVC, 218 LM 50mm dia. PVC |
City Homes
Mandaue |
Grand Land, Inc. |
Project
Management Office |
PhP |
870,061.25 |
|
Oct 23, 2013 |
|
85.00% |
Remaining works
are hydrotesting, flushing and disinfection. |
|
Remaining works
are hydrotesting, flushing and disinfection. |
|
|
9.0 |
Prop. Water
Sytem for Graceland 1 & Graceland Annex Subdivision (Brgy. Buaya, Mactan,
Lapulapu City) |
39
lm x 100mm dia PVC, 29 lm x 50mm dia PVC |
Graceland 1 and
Graceland Annex Subdivision |
Kaiser Urban
Development Corp. |
Project
Management Office |
PhP |
858,046.50 |
11 Working Days |
Jul 7, 2014 |
Jul 21, 2014 |
50.00% |
Pipelaying for
the Phase 1 section of the project has already passed hydrotesting. It is
awaiting for disinfection. |
|
Pipelaying is
ongoing. |
|
|
10.0 |
Prop. Water
System Design for South Covina Subdivision (Brgy. Dumlog, Talisay City, Cebu) |
42
lm x 100mm dia PVC, 110 lm x 75mm dia PVC, and 346 lm x 50mm dia PVC |
South Covina
Subdivision |
Athecor
Development Corporation |
Project
Management Office |
PhP |
1,177,338.75 |
71 Working Days |
Sep 18, 2014 |
Dec
17, 2014 |
|
Developer is on the
process of procurement of materials. |
|
Developer is on the process of
procurement of materials. |
|
|
11.0 |
Prop. Water
Distribution System for Peninsula Subdivision (Sudtungan Road, Brgy. Basak,
Lapulapu City) |
42
lm x 100mm dia PVC, 110 lm x 75mm dia PVC, and 346 lm x 50mm dia PVC |
Peninsula Place
Subdivision |
Peninsula Resort
Corporation |
Project
Management Office |
PhP |
1,196,027.58 |
52 Calendar Days |
Oct 1, 2014 |
Nov
21, 2014 |
60.00% |
Remaining works are:
installation of stubouts, fire hydrants, and av/ar. |
|
Pipelaying is ongoing. |
|
|
12.0 |
Prop. Water
Distribution System for Rose Pike Subdivision (Forest Hills, Kalubihan,
Banawa, Brgy. Guadalupe, Cebu City) |
228
lm x 50mm dia PVC |
Rose Pike
Subdivision |
F.S. Baltazar
Builders |
Project
Management Office |
PhP |
1,415,707.20 |
45 Calendar Days |
Feb 17, 2015 |
Apr
2, 2015 |
80.00% |
This project project
is composed of two phases - Phase 1 and Phase 2. Phase 1 is physically
completed. Developer has requested for the partial turn-over of this. Phase 2
is ongoing at 30% accomplishment. |
|
Pipelaying is ongoing. |
|
|
13.0 |
Prop. Ø100mm x
373.0 lm UPVC Expansion Project for Colorado Homes Dos (Brgy. Jubay, Liloan,
Cebu) |
373
lm x 100mm dia PVC |
Colorado
Homes Dos |
Commonwealth
Estate, Inc. |
Project
Management Office |
PhP |
1,640,244.69 |
45
Calendar Days |
Jul 15, 2015 |
Aug 28, 2015 |
65% |
Remaining
works are: bridge crossing pipeline, fire hydrant installation, disinfection and interconnection. |
|
Pipelaying is
ongoing. |
|
|
14.0 |
Prop.Water
Distribution System for Villa Sebastiana Subdivision (Brgy. Tawason, Mandaue
City, Cebu) |
126
lm x 100mm dia PVC, 72 lm x 75mm dia PVC, 438 lm x 50mm dia PVC |
Villa
Sebastiana Subdivision |
Aidfaz
Development Corporation |
Project
Management Office |
PhP |
1,343,438.70 |
38
Working Days |
Jul 29, 2015 |
Sep 14, 2015 |
|
Developer
is on the process of procurement of materials and excavation permit. |
|
Developer is on
the process of procurement of materials and excavation permit. |
|
|
15.0 |
Prop.Water
Distribution System for Blessed Sacrament Subdivision (Kagudoy Road, Brgy.
Basak, Lapulapu City) |
96
lm x 100mm dia PVC, 162 lm x 75mm dia PVC, 588 lm x 50mm dia PVC |
Blessed
Sacrament Subdivision |
Cebu
Peoples Multi Purpose Cooperative |
Project
Management Office |
PhP |
2,673,187.14 |
- |
Nov 16, 2015 |
- |
|
Developer
is on the process of procurement of materials and excavation permit. |
|
Developer is on
the process of procurement of materials and excavation permit. |
|
|
16.0 |
Prop.Water
Distribution System for Brookridge Subdivision (Dr. Pablo Abella St.,
Labangon, Cebu City) |
140
lm x 100mm dia PVC, 201 lm x 50mm dia PVC, 12 lm x 50mm dia GI |
Brookridge
Subdivision |
Primary
Homes, Incorporated |
Project
Management Office |
PhP |
2,414,108.22 |
41
Working Days |
Feb 4, 2016 |
Mar 22, 2016 |
|
Developer
is on the process of procurement of materials and excavation permit. |
|
Developer is on
the process of procurement of materials and excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Ongoing Subdivision/Hotel/Condo Water System Projects 9 |
|
|
Name of Project |
Brief Description of
the Project |
Subdivision/Hotel/Condo
Name |
Developer / Owner |
MCWD Supervising Unit |
Project
Amount |
Project Duration |
Date Started |
Target Completion Date |
Accomplish- ment To Date |
Remarks |
|
|
|
|
|
|
|
|
|
2. Flowmeter Assembly
and Vault |
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Ø100mm Flowmeter Enclosed
in Reinforced Concrete Vault for Alegria Palms Subdivision 2 (Brgy. Gabi,
Cordova, Cebu) |
dia.100mm
flowmeter, construction of reinforced concrete vault & interconnection |
Alegria
Palms Subdivision 2 |
Commonwealth
Estate, Inc. |
Project
Management Office |
PhP |
1,216,026.49 |
50 CD |
May 29, 2013 |
Jul 17, 2013 |
|
No activity
conducted during the month. Developer may have problem with the procurement
of the excavation permit. |
|
No activity conducted during
the month. Developer may have problem with the procurement of the excavation
permit. |
|
|
|
2.0 |
Prop. Ø100mm
Flow Meter for Marco Polo Residences (Veterans Drive, Nivel Hills, Apas, Cebu
City) |
dia.
100mm large meter assembly & interconnection |
Marco
Polo Residences |
Federal
Land, Inc. |
Project
Management Office |
PhP |
535,054.44 |
14
WD |
Mar 10, 2014 |
Mar 28, 2014 |
|
Developer
is on the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
|
3.0 |
Prop. Ø100mm
Surface Mounted Bulkmeter for One Pavilion Place, (Banawa, Guadalupe, Cebu
City) |
dia.
100mm large meter assembly & interconnection |
One
Pavilion Place |
Goldpeach
Properties Corp. |
Project
Management Office |
PhP |
892,244.28 |
39
CD |
May 5, 2014 |
|
|
Materials
are availlable already. However, DPWH had denied Developer's request for
excavation permit. Developer's existing Ø 25mm pipeline source was already upgraded to Ø
50mm as a temporary source of water supply. |
|
Materials are
availlable already. However, DPWH had denied Developer's request for
excavation permit. Developer's existing Ø 25mm pipeline source was already upgraded to Ø
50mm as a temporary source of water supply. |
|
|
|
4.0 |
Prop. Ø75mm
Surface Flow Meter for Eagle's Nest (Canduman, Mandaue City, Cebu) |
dia.75mm
large meter, large meter assembly & interconnection |
Eagle's
Nest |
Primary
Homes, Incorporated |
Project
Management Office |
PhP |
363,680.52 |
15
Working Days |
Aug 18, 2014 |
Sep 1, 2014 |
|
Developer
is on the process of procurement of materials and permit. Developer may have
a problem with the excavation permit
from the DPWH. |
|
Developer is on
the process of procurement of materials and permit. Developer may have a
problem with the excavation permit
from the DPWH. |
|
|
5.0 |
Prop. Ø150mm
Surface Flow Meter for Astana Subdivision (Calawisan, Lapulapu City) |
dia.
150mm large meter, large meter assembly,
10 l.m. of Ø 150mm water distribution line & interconnection |
Astana
Subdivision |
Johndorf
Ventures Corporation |
Project
Management Office |
PhP |
564,233.88 |
20
Working Days |
Sep 3, 2014 |
Sep 26, 2014 |
|
Developer
is on the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
6.0 |
Prop.
Ø150mm Bulk Meter Connection for
Sunrise Place Subdivision (Sitio Malinao Brgy. Agus, Lapulapu City) |
dia.
150mm large meter and assembly, 10 l.m. of Ø 150mm PVC water distribution
line |
Sunrise
Place Subdivision |
Filinvest
Land, Inc. |
Project
Management Office |
PhP |
573,409.74 |
25
Working Days |
Mar 18, 2015 |
Apr 15, 2015 |
|
Developer
is on the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
7.0 |
Prop.
Ø75mm Surface FlowMeter for Corinthian
Residences (Andres Abellana St., Guadalupe, Cebu City) |
dia.
75mm large meter and assembly, 12 l.m. of Ø 75mm PVC water distribution line |
Corinthian
Residences |
Landtraders
World Properties Corp. |
Project
Management Office |
PhP |
532,247.12 |
9
Working Days |
May 6, 2015 |
May 16, 2015 |
|
Developer
is on the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
8.0 |
Prop.
Ø75mm Surface FlowMeter for Park Point
Residences (Ayala Business Park, Cebu City) |
dia.
75mm large meter and assembly, 6 l.m. of Ø 150mm PVC water distribution line |
Park
Point Residences |
Ayala
Land, Inc. |
Project
Management Office |
PhP |
545,657.97 |
8
Working Days |
Jun 3, 2015 |
Jun 21, 2015 |
|
Developer
is on the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
9.0 |
Prop.
Ø150mm Surface FlowMeter for Priveya
Hills Subdivision (Talamban, Cebu City) |
dia.
150mm large meter and assembly, 18 l.m. of Ø 150mm PVC water distribution
line |
Priveya
Hills Subdivision |
Aboitizland,
Inc. |
Project
Management Office |
PhP |
824,138.35 |
10
Working Days |
Jun 30, 2015 |
Jul 18, 2015 |
|
Developer
is on the process of procurement of materials. Pipeline is already
interconnected to the MCWD main line. PMO had allowed the interconnection so
as to avoid future conflict with the ongoing asphalting works that will
affect the interconnecting point. |
|
Developer is on
the process of procurement of materials. |
|
|
10.0 |
Prop.
Ø750mm Surface FlowMeter for San Pio
Subdivision (Dumlog, Talisay City, Cebu) |
dia.
75mm large meter and assembly, 7 l.m. of Ø 75mm PVC water distribution line
& interconnection |
San
Pio Subdivision |
Justice,
Peace & Integrity of Creation - Integrated Development Center, Inc.
(JPIC-IDC) |
Project
Management Office |
PhP |
527,063.13 |
15
Calendar Days |
Jul 8, 2015 |
Jul 22, 2015 |
|
Some
of the already procured materials have undergone testing. Developer is on the
process of procurement of the other materials. |
|
|
|
|
11.0 |
Prop.
Ø150mm Surface FlowMeter for Eastland
Yati Village (Phase 1-3) (Yati, Liloan, Cebu) |
dia.
150mm large meter and assembly, 282 l.m. of Ø 150mm PVC water distribution
line & interconnection |
Eastland
Yati Village (Phase 1-3) |
Eastland
Property Ventures, Inc. |
Project
Management Office |
PhP |
1,618,076.10 |
45
Calendar Days |
Jul 14, 2015 |
Aug 27, 2015 |
|
Developer
had already the materials and permit. Awaiting for the developer to start
work on the interconnecting pipeline. |
|
Developer is on
the process of procurement of materials. |
|
|
12.0 |
Prop.
Ø100mm Surface FlowMeter for Filinvest
Cyberzone (Salinas Drive corner Geonson St., Lahug, Cebu City) |
dia.
100mm large meter and assembly & interconnection |
Filinvest
Cyberzone |
Cyberzone
Properties, Inc. |
Project
Management Office |
PhP |
430,929.12 |
20
Working Days |
Aug 4, 2015 |
Aug 31, 2015 |
|
Project
works is ongoing. |
|
Developer is on
the process of procurement of materials. Completed on February 9, 2016 |
|
|
13.0 |
Revised Ø75mm
Surface Flow Meter for Bamboo Bay Community (Subangdaku, Mandaue City) |
dia.
75mm large meter and assembly, 55 l.m. of Ø 75mm PVC water distribution line
& interconnection |
Bamboo
Bay Community |
Contempo
Property Holdings, Inc. |
Project
Management Office |
PhP |
725,460.93 |
30
Calendar Days |
Sep 11, 2015 |
Oct 10, 2015 |
|
Materials
are already available. Developer is awaiting for the permit from DPWH. |
|
Developer is on
the process of procurement of materials. |
|
|
14.0 |
Prop.
Ø75mm Surface Flow Meter for Palm
River Phase 1 (Biasong, Pooc, Talisay City) |
dia.
75mm large meter and assembly, 24 l.m.
of Ø 75mm uPVC water distribution line |
Palm
River Phase 1 |
Deo
Homes and Property Development, Inc. |
Project
Management Office |
PhP |
548,568.09 |
9
Calendar Days |
Dec 14, 2015 |
Dec 22, 2015 |
|
Developer
is on the process of procurement of materials. |
|
Developer is on
the process of procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Ongoing Subdivision/Hotel/Condo Water System Projects 10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|