Name of Project  Contractor  Supply Cost Volume Contract Signing Day 1 of Delivery  Revised                                Day 1 of Delivery  Remarks
                 
1.0 MCWD Bulk Water Supply Contract (Compostela-Liloan-Consolacion Injection Points) Cebu Manila Water Development Incorporated Php 24.59 / cu.m. Year 1                    : 18,000 m3/day 18 Dec 2013 *09 Dec 2014   The BOD had approved the request of CMWD to extend the Day 1 of the year 2 of delivery to December 1, 2016.
      Year 2 to Year 20 : 35,000 m3/day   09 Dec 2015 1 Dec 2016
            * - Day 1 of the 1st year of delivery per MCWD letter to CMWD dated December 5, 2014   The commissionining of the main injection point in Casili is scheduled on January 5, 2017.  However, the remaining works of the three (3) drop off point s in Compostel, Liloan, and Consolacion have yet to be completed.
2.0 MCWD Bulk Water Supply (Suba-Basbas, Lapulapu Injection Point) Abejo Waters Corporation Php 26.39 / cu.m. 7000 m³/day 08 Oct 2015 April 2016 15 Jun 2017 The supplier had informed MCWD that its right of way problem had been resolved.  Further, that it  shall proceed with the construction of its treatment facility by next year.   
                The January 15, 2017 Revised Day 1 of Delivery had been approved by the BOD.
                 
                 
                     