Name of
Project |
Contractor |
Supply Cost |
Volume |
Contract Signing |
Day 1 of Delivery |
Revised Day 1 of
Delivery |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
MCWD Bulk Water
Supply Contract (Compostela-Liloan-Consolacion Injection Points) |
Cebu Manila
Water Development Incorporated |
Php |
24.59 / cu.m. |
Year 1
: |
18,000 m3/day |
18 Dec 2013 |
*09 Dec 2014 |
|
The steel pipes
intended as supply line for the 3 drop-off points had been delivered.
Installation of the supply pipes for the Liloan Injection Point is ongoing. |
|
Works at the 3
drop-off points to comply with the approved flowmeter assembly and injection
scheme are ongoing. |
|
|
|
|
|
|
|
Year 2 to Year 20 : |
35,000 m3/day |
|
09 Dec 2015 |
+16 Jul 2016 |
|
|
|
|
|
|
|
|
|
|
|
|
* - Day 1
of the 1st
year of delivery per MCWD letter to CMWD dated December 5, 2014 |
+ - Revise Day 1 of Year 2
based on the June 28, 2016 letter of Acting GM Dalena |
The MCWD had
ordered CMWD to fully backfill the interconnection point area to allow the
passage of heavy equipment for the JICA-funded project. The said order has
yet to be lifted by MCWD. |
|
At the Casili injection point, works to
complete the flowmeter assembly is ongoing. The ultrasonic level instrument
to be installed at the CMWD reservoirs that will trigger the start/stop of
the booster pumps have yet to be delivered. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Acting GM Dalena on his June 28, 2016 letter had informed
CMWD that the previously scheduled June 28-30, 2016 interconnection at the
Casili injection point will be moved to another date. Further, MCWD will
extend the Day 1 of the Year 2 of delivery correspondingly if the
interconnection is scheduled beyond the approved July 16, 2016 Day 1 of Year
2. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
MCWD Septage Management Service
Contract (Phase I - Mactan Septage Management Service) |
Envirokonsult Equipment
Services, Incorporated |
Php |
800.00 / m3 |
Year 1 to Year 5 : |
150 m3/day |
23 Apr 2015 |
23 Apr 2016 |
30 Jul 2016 |
Under the
Contract, the Service Provider will construct a Septage Treatment Facility at
the MCWD property in Cordova, Cebu and shall collect, transport and treat the
septage and dispose the bio-solids. The term of the service contract is five
(5) years from the Day One of operation. |
|
Under the Contract, the Service
Provider will construct a Septage Treatment Facility at the MCWD property in
Cordova, Cebu and shall collect, transport and treat the septage and dispose
the bio-solids. The term of the service contract is five (5) years from the
Day One of operation. |
|
|
|
|
|
|
|
|
|
|
|
(The Day 1 was
suspended on February 23, 2016 pending negotiations of the site development
works) |
|
With the
approval of the EXECOM that the testing of the sludge effluent and bio-solids
be done during the plant operation, the PMO on its August 22, 2016 memo to GM
Dalena had recommended the start of operation of the Septage Treatment Plant.
Further, the PMO had turned-over to the Septage Monitoring Team the
responsibility to ensure completion by the Service Provider of the remaining
works except for the site development works which shall be monitored by the
PMO. |
|
The installation of the septage
treatment plant is nearing completion.
Meanwhile, the site development work had already started and is now
75% complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Service Provider is still
working on the necessary permits and clearances to operate the plant. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
II. Ongoing Supply and Installation of Goods 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|