Name of
Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply
Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. To date, however, the Supplier has yet to comply
with the data transmission requirement. |
|
The Apas Injection Point
(originally at BC Homes) has been supplying water to MCWD since December 21,
2011. To date, however, the Supplier has yet to comply with the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply
Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. To
date, however, the Supplier has yet to comply with the data transmission
requirement. |
|
The Banawa Injection Point has
been supplying water to MCWD since December 9, 2011. To date, however, the
Supplier has yet to comply with the data transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply
Program - Talamban Injection Point |
Pilipinas Water Resources, Inc. |
3,592 |
m3/day |
PhP |
14.21 |
/m3 |
19 Nov 2010 |
19-May-11 |
5 Dec 2011 |
The Talamban
Injection Point had started the supply of water to MCWD on December 6,
2011. |
|
The Talamban Injection Point
had started the supply of water to MCWD on December 6, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO learned
from PDD that PWRI had stopped supplying water to MCWD since June 2, 2015.
The PDD is handling this supply stoppage issue. |
|
PMO learned from PDD that PWRI
had stopped supplying water to MCWD since June 2, 2015. The PDD is handling
this supply stoppage issue. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply
Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
The Marigondon-Gabi Injection
Point has been supplying water to MCWD since February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply
Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
10 Jun 2014 |
This JV
Contract has 3 injection points located at Guadalajara, Kabajar, and Quijada
in Brgy. Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has
been delivering water to MCWD since September, November and March,
respectively. |
|
This JV Contract has 3
injection points located at Guadalajara, Kabajar, and Quijada in Brgy.
Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has been
delivering water to MCWD since September, November and March, respectively. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The drop-off
point to be provided by the Supplier under the Amendment to TOR dated July
11, 2014, remains uncompleted. |
|
The drop-off point to be
provided by the Supplier under the Amendment to TOR dated July 11, 2014,
remains uncompleted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have completed the
drop-off point and complied the data transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have completed the drop-off
point and complied the data transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Bulk Water Supply
Program - Pit-os Injection Point |
Abejo Waters Corporation |
4,800 |
m3/day |
PhP |
15.68 |
/m3 |
19 June 2013 |
18 June 2014 |
18 Jan 2015 |
Under this
joint venture, AWC will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
Under this joint venture, AWC
will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Pit-os
Injection Point has been delivering water into the MCWD distribution system
since March 12, 2015. The volume of delivery however is below the required
minimum. AWC is presently working on one additional well to supplement its
supply. |
|
|
The Pit-os Injection Point has
been delivering water into the MCWD distribution system since March 12, 2015.
The volume of delivery however is below the required minimum. AWC is
presently working on one additional well to supplement its supply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC was
allowed to start the delivery of water under
BOD Resolution No.025-2015 with conditions, among others, that AWC
will install the lacking fittings (4 support bush and 2 harness sets) within
4 months from the start of the water delivery. The 4-month period has ended on July 12, 2015. On June
24, 2015, AWC had requested for water interruption to install the lacking
fittings but was denied by PMO since the fabricated harness sets are
unacceptable. Until now, AWC is still working to comply with the harness set
requirement. The Contractor has committed to
install the lacking materials for the reconnection by the end of October
2015. |
|
AWC was allowed to start the
delivery of water under BOD Resolution
No.025-2015 with conditions, among others, that AWC will install the lacking
fittings (4 support bush and 2 harness sets) within 4 months from the start
of the water delivery. The 4-month period will end on July 12, 2015. On June
24, 2015, AWC had requested for water interruption to install the lacking
fittings but was denied by PMO since the fabricated harness sets are
unacceptable. Until now, AWC is still working to comply with the harness set
requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has yet to
comply with the data transmission requirement. AWC informed PMO that it is
hiring an IT Professional to work on the compliance of this requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
has requested for time extension from the GM's Office. The request was
granted subject to several conditions. |
|
AWC has yet to comply with the
data transmission requirement. AWC informed PMO that it is hiring an IT
Professional to work on the compliance of this requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint
Venture Projects
|
7 |
|
|
|
|
Name of Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Bulk Water Supply
Program - Cabancalan Injection Point |
Abejo Waters Corporation |
5,000 |
m3/day |
PhP |
15.68 |
/m3 |
25 Sept. 2013 |
24 Sept. 2014 |
Extended to 6 months
from issuance of Excavation Permit by Mandaue City per BOD Resolution
No.111-2014 |
Under this
joint venture, AWC will supply a minimum of 5,000m3 of water daily to MCWD . |
|
Under this joint venture, AWC
will supply a minimum of 5,000m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC informed
PMO that it will operate 2 production wells only for this supply contract
instead of the previously planned 4 wells since the combined discharge of the
completed 2 wells is more than enough to meet the required supply volume. |
|
AWC informed PMO that it will
operate 2 production wells only for this supply contract instead of the
previously planned 4 wells since the combined discharge of the completed 2
wells is more than enough to meet the required supply volume. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Only 600
meters of AWC's 2,000-meter long Ø250mm transmission line had been installed
as Mandaue City granted excavation permit for 600m only. The rest, Mandaue
City did not issue excavation permit for the reason that the concrete road is still under warranty and still subject
to COA audit. |
|
Only 600 meters of AWC's
2,000-meter long Ø250mm transmission line had been installed as Mandaue City
granted excavation permit for 600m only. The rest, Mandaue City did not issue
excavation permit for the reason that the concrete road is still under warranty and still subject
to COA audit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The pipe route
and the injection point has been approved subject to the conditions set on
the PMO's August 17, 2015 letter that
was sent to the contractor. |
|
PMO had endorsed to the
Engineering Department for evaluation/approval AWC's proposed new pipe route
and injection point. The evaluation by ED is ongoing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
will be resubmitting another shop drawings since the previous shop drawings
that it submitted was disapproved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint
Venture Projects |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|