|
Name of
Project |
Contractor |
Supply Cost |
Volume |
Contract Signing |
Day 1 of Delivery |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
MCWD Bulk Water
Supply Contract (Compostela-Liloan-Consolacion Injection Points) |
Cebu Manila
Water Development Incorporated |
Php |
24.59 / cu.m. |
Year 1
: |
18,000 m3/day |
18 Dec 2013 |
*09 Dec 2014 |
CMWD has been
delivering 18,000 cu.m./day at the 3 drop-off points (Compostela, Liloan and
Consolacion) and at the Consolacion temporary main delivery point since January 5, 2015. Under the Contract,
CMWD will deliver 35,000 cu.m./day at the start of the second year. |
|
CMWD has been
delivering 18,000 cu.m./day at the 3 drop-off points (Compostela, Liloan and
Consolacion) and at the Consolacion temporary main delivery point since January 5, 2015. Under the Contract,
CMWD will deliver 35,000 cu.m./day at the start of the second year which will
be on January 2016. |
|
|
|
|
|
Year 2 to Year 20 : |
35,000 m3/day |
|
+09 Dec 2015 |
|
|
|
|
|
|
|
|
|
|
* - Day 1
of the 1st
year of delivery per MCWD letter to CMWD dated December 5, 2014 |
After it failed the replacement
of the temporary flowmeters, construction of flowmeter vaults, and
replacement of the temporary pipes within the agreed period, CMWD had asked
for an extension on or before the day 1 of the Year 2 of delivery. During the
July 15, 2015 meeting of the EXECOM and PMO with CMWD, the EXECOM had granted
CMWD's request but until October 2015 only. |
|
CMWD had failed to meet its
commitment, as part of the agreed conditions set by MCWD for allowing CMWD to
start the delivery of water, to replace the temporary flowmeters wit the
approved ones and construct the flowmeter vaults by end of January and February,
respectively. Construction of the flowmeter vaults has yet to start while the
approved flowmeters are yet to be delivered by the supplier. |
|
|
|
|
|
|
|
|
|
+ - Day 1 of the 2nd year of delivery |
The installation of CMWD's
Ø700mm transmission line going to the Casili Reservoirs has already started
and ongoing. |
|
In lieu of the required 5,000m3 capacity tank (start
of the 2nd year of delivery), CMWD had proposed to construct 4 tanks with
combined storage capacity of 5,000m3 and with the same hydraulic grade as the existing Casili
Reservoirs. MCWD in concept had approved the proposal and required CMWD to
submit the piping details and the detailed design of the tanks. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
II. Ongoing Supply and Installation of Goods 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|