Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 11 |
A.L. Gantuangco Construction |
PhP |
9,214,465.00 |
|
9,214,465.00 |
10 Sep 2015 |
07 Mar 2016 |
- |
0.00% |
0.00% |
0.00% |
A
Pre-Construction Meeting with PMO and the Contractor was conducted on
September 24, 2015. Contractor has already requested for the in-plant
inspection of the pipes in India. Said inspection is expected to be conducted
by October 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 7 |
JFAP Construction |
PhP |
35,078,950.22 |
|
35,078,950.22 |
10 Sep 2015 |
16 May 2016 |
- |
0.00% |
0.00% |
0.00% |
A
Pre-Construction Meeting with PMO and the Contractor was conducted on
September 24, 2015. Contractor has already requested for the in-plant
inspection of the pipes in India. Said inspection is expected to be conducted
by October 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
- |
0.00% |
0.00% |
0.00% |
Contractor has
already requested for the in-plant inspection of the pipes in India. Said
inspection is expected to be conducted by October 2015. |
|
A Pre-Construction Meeting with
PMO and the Contractor was conducted on August 18, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
78.29% |
26.24% |
-52.05% |
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs.
Contractor has already hydrotested more than 1000 linear meters of pipes.
The same has passed hydrotesting. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
55.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
52.76% |
0.00% |
-52.76% |
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
37.24% |
0.00% |
-37.24% |
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
44.21% |
0.00% |
-44.21% |
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
0.00% |
-100.00% |
The MCWD Execom has instructed
PMO to inform the Contractor to have a notarized reply regarding its
(Contractor) intention and commitment to complete the project. Included in
the reply will be the time table, crash program, and the Contractor's
commitment to complete the project with liquidated damages imposed.
PMO had already sent a letter to the Contractor on September 24, 2015 regarding the matter. Contractor is given
one (1) week to have its reply. |
|
Contractor is still securing
the remaining materials for the project as PMO is strictly imposing that the
Contractor is not allowed to start unless all the materials have been
inspected and passed testing. PMO had sent a letter to the Contractor
reminding the latter of the status of the project and instructing them
(Contractor) to expedite the purchase of the pipes. PMO had also follow-up on
the Contractor's acquisition of excavation permit from the concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
43.92% |
-56.08% |
The MCWD Execom has instructed
PMO to inform the Contractor to have a notarized reply regarding its
(Contractor) intention and commitment to complete the project. Included in
the reply will be the time table, crash program, and the Contractor's
commitment to complete the project with liquidated damages imposed.
PMO had already sent a letter to the Contractor on September 24, 2015 regarding the matter. Contractor is given
one (1) week to have its reply. |
|
Contractor is still securing
the remaining materials for the project as PMO is strictly imposing that the
Contractor is not allowed to start unless all the materials have been
inspected and passed testing. PMO had sent a letter to the Contractor
reminding the latter of the status of the project and instructing them
(Contractor) to expedite the purchase of the pipes. PMO had also follow-up on
the Contractor's acquisition of excavation permit from the concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of
Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
13 Mar 2015 |
100.00% |
88.90% |
-11.10% |
Leaks of the
installed DI collector pipeline has been found. Disinfection, interconnection
and commissioning is expected to be completed by September. Field testing of
the submersible pump was done. |
|
Leaks of the
installed DI collector pipeline has been found. Disinfection, interconnection
and commissioning is expected to be completed by September. Field testing of
the submersible pump was done. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from March 14, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from March 14, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
82.37% |
-17.63% |
Field testing of the pump and motor was conducted last
September 11, 2015. |
|
The pump and the motor has been installed. Field testing of
the pump and motor is expected to be conducted by September. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
Finally, the
Contractor has started works on the pipe replacement last September 28, 2015.
It is estimated that the project will be completed by November 2015. |
|
The Contractor has wrote to PMO
formally informing the latter of the former's commitment to complete the
project in three (3) months starting on August 1, 2015 to November 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|