|
Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks (September) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 9 |
JFAP Construction |
PhP |
49,856,139.71 |
|
49,856,139.71 |
22 Oct 2015 |
17 Jul 2016 |
- |
0.00% |
0.00% |
0.00% |
The project is
yet to be endorsed to the PMO. It is expected to be endorsed by the first
week of November 2015. |
|
A Pre-Construction Meeting with
PMO and the Contractor was conducted on September 24, 2015. Contractor has
already requested for the in-plant inspection of the pipes in India. Said
inspection is expected to be conducted by October 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 11 |
A.L. Gantuangco Construction |
PhP |
9,214,465.00 |
|
9,214,465.00 |
10 Sep 2015 |
07 Mar 2016 |
- |
0.00% |
0.00% |
0.00% |
The in-plant
inspection for this project will be conducted simultaneously with 'Package 7'
and the negoatiated project at Pajac, Lapulapu City. Five MCWD personnels who
will conduct the in-plant inspection in India has already made their
appearance at the Indian Embassy in Manila. This is a requirement for the
visa application for the in-plant inspection which is scheduled on the first
week of November 2015. |
|
A Pre-Construction Meeting with
PMO and the Contractor was conducted on September 24, 2015. Contractor has
already requested for the in-plant inspection of the pipes in India. Said
inspection is expected to be conducted by October 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 7 |
JFAP Construction |
PhP |
35,078,950.22 |
|
35,078,950.22 |
10 Sep 2015 |
16 May 2016 |
- |
0.00% |
0.00% |
0.00% |
The in-plant
inspection for this project will be conducted simultaneously with 'Package
11' and the negoatiated project at Pajac, Lapulapu City. Five MCWD personnels
who will conduct the in-plant inspection in India has already made their
appearance at the Indian Embassy in Manila. This is a requirement for the
visa application for the in-plant inspection which is scheduled on the first
week of November 2015. |
|
A Pre-Construction Meeting with
PMO and the Contractor was conducted on September 24, 2015. Contractor has
already requested for the in-plant inspection of the pipes in India. Said
inspection is expected to be conducted by October 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
- |
0.00% |
0.00% |
0.00% |
The in-plant
inspection for this project will be conducted simultaneously with 'Package
11' and 'Package 7'. Five MCWD personnels who will conduct the in-plant
inspection in India has already made their appearance at the Indian Embassy
in Manila. This is a requirement for the visa application for the in-plant
inspection which is scheduled on the first week of November 2015. |
|
Contractor has already
requested for the in-plant inspection of the pipes in India. Said inspection
is expected to be conducted by October 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
93.60% |
26.72% |
-66.88% |
Recently, the pipes and
fittings which have been put on hold at the PPA Cebu due to the expired ICC
of the pipe supplier have been released. The same has been inspected and
passed MCWD-QC.
The Contractor has resumed pipelaying works on October 23, 2015 along
Angasil Road. |
|
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
73.45% |
1.06% |
-72.39% |
Recently, the pipes and
fittings which have been put on hold at the PPA Cebu due to the expired ICC
of the pipe supplier have been released. The same has been inspected and
passed MCWD-QC.
The Contractor has just started pipelaying works after the APEC Conference
in Cebu. |
|
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
53.81% |
0.00% |
-53.81% |
The pipes and fittings which
have been put on hold at the PPA Cebu due to the expired ICC of the pipe
supplier has been released recently. The same has been inspected and passed
MCWD-QC.
The Contractor has just started pipelaying works. |
|
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
65.40% |
0.00% |
-65.40% |
The pipes and fittings which
have been put on hold at the PPA Cebu due to the expired ICC of the pipe
supplier has been released recently. The same has been inspected and passed
MCWD-QC.
The Contractor has just started pipelaying works. |
|
The Contractor has requested
that project works be suspended due to the new policy of Bureau of Customs
regarding the renewal of broker's ICC which has caused the delay in the
release of the pipes from the Port of Cebu, and the ongoing APEC Summit. PMO
is still evaluating the said request.
On September 24, 2015, BOD Elizalde, PMO and the Contractor had a meeting
to discuss the issues regarding the delay in project implementation. It was
decided to hold the suspension of works and to await for the renewal of ICC
of the custom broker and the conclusion of the APEC Summit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
0.00% |
-100.00% |
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. However, the Contractor has
not yet submitted the crash program which is part of its commitment. PMO will
be sending a letter to the Contractor next month to instruct the latter to
submit the crash program. |
|
The MCWD Execom has instructed
PMO to inform the Contractor to have a notarized reply regarding its
(Contractor) intention and commitment to complete the project. Included in
the reply will be the time table, crash program, and the Contractor's
commitment to complete the project with liquidated damages imposed.
PMO had already sent a letter to the Contractor on September 24, 2015 regarding the matter. Contractor is given
one (1) week to have its reply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
43.92% |
-56.08% |
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. However, the Contractor has
not yet submitted the crash program which is part of its commitment. PMO will
be sending a letter to the Contractor next month to instruct the latter to
submit the crash program. |
|
The MCWD Execom has instructed
PMO to inform the Contractor to have a notarized reply regarding its
(Contractor) intention and commitment to complete the project. Included in
the reply will be the time table, crash program, and the Contractor's
commitment to complete the project with liquidated damages imposed.
PMO had already sent a letter to the Contractor on September 24, 2015 regarding the matter. Contractor is given
one (1) week to have its reply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Construction of
Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
13 Mar 2015 |
100.00% |
100.00% |
0.00% |
The CUB-1
Pumping Station was commissioned on October 16, 2015. The pumping station has
been supplying 50 m3/hr
of water since. |
|
Leaks of the
installed DI collector pipeline has been found. Disinfection, interconnection
and commissioning is expected to be completed by September. Field testing of
the submersible pump was done. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The pavement
restoration was fully completed last October 28, 2015. The joint Final
Inspection of the project will be conducted next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from March 14, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from March 14, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Construction of
Proposed Man-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay Construction and
Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
84.81% |
-15.19% |
The installed pump and motor had
passed the field testing jointly conducted by MCWD and the Contractor on
September 11, 2015. |
|
Field testing of the pump and motor was conducted last
September 11, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The remaining works include the
completion of the installation of of the collector line and appurtenances,
hydrotesting, disinfection, and interconnection. To date, the DPWH has not
issued the necessary Excavation Permit for the interconnection work. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from January 1, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. |
|
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
Contractor has
already made significant progress in the repiping along Brgy. Tabok, Mandaue
City. Hydrotesting for this area is expected to be conducted by the early
week of November 2015. |
|
Finally, the Contractor has
started works on the pipe replacement last September 28, 2015. It is
estimated that the project will be completed by November 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|