|
Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks (October) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 9 |
JFAP Construction |
PhP |
49,856,139.71 |
|
49,856,139.71 |
22 Oct 2015 |
17 Jul 2016 |
- |
0.00% |
0.00% |
0.00% |
Five MCWD
personnel had already conducted the in-plant inspection in India on November
4 - 7, 2015. Contractor is awaiting for the delivery of the DI pipe and
fittings from India to Cebu. |
|
The project is yet to be
endorsed to the PMO. It is expected to be endorsed by the first week of
November 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 11 |
A.L. Gantuangco Construction |
PhP |
9,214,465.00 |
|
9,214,465.00 |
10 Sep 2015 |
07 Mar 2016 |
- |
0.00% |
0.00% |
0.00% |
Five MCWD
personnel had already conducted the in-plant inspection in India on November
4 - 7, 2015. Contractor is awaiting for the delivery of the DI pipe and
fittings from India to Cebu. |
|
The in-plant inspection for
this project will be conducted simultaneously with 'Package 7' and the
negoatiated project at Pajac, Lapulapu City. Five MCWD personnels who will
conduct the in-plant inspection in India has already made their appearance at
the Indian Embassy in Manila. This is a requirement for the visa application
for the in-plant inspection which is scheduled on the first week of November
2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 7 |
JFAP Construction |
PhP |
35,078,950.22 |
|
35,078,950.22 |
10 Sep 2015 |
16 May 2016 |
- |
0.00% |
0.00% |
0.00% |
Five MCWD
personnel had already conducted the in-plant inspection in India on November
4 - 7, 2015. Contractor is awaiting for the delivery of the DI pipe and
fittings from India to Cebu. |
|
The in-plant inspection for
this project will be conducted simultaneously with 'Package 11' and the
negoatiated project at Pajac, Lapulapu City. Five MCWD personnels who will
conduct the in-plant inspection in India has already made their appearance at
the Indian Embassy in Manila. This is a requirement for the visa application
for the in-plant inspection which is scheduled on the first week of November
2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
- |
32.38% |
0.00% |
-32.38% |
Five MCWD
personnel had already conducted the in-plant inspection in India on November
4 - 7, 2015. Contractor is awaiting for the delivery of the DI pipe and
fittings from India to Cebu. |
|
The in-plant inspection for
this project will be conducted simultaneously with 'Package 11' and 'Package
7'. Five MCWD personnels who will conduct the in-plant inspection in India
has already made their appearance at the Indian Embassy in Manila. This is a
requirement for the visa application for the in-plant inspection which is
scheduled on the first week of November 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
100.00% |
35.59% |
-64.41% |
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavtion works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
will be reduced once the PERT/CPM will be revised. |
|
Recently, the pipes and
fittings which have been put on hold at the PPA Cebu due to the expired ICC
of the pipe supplier have been released. The same has been inspected and
passed MCWD-QC.
The Contractor has resumed pipelaying works on October 23, 2015 along
Angasil Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
89.95% |
7.87% |
-82.08% |
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavtion works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
will be reduced once the PERT/CPM will be revised. |
|
Recently, the pipes and
fittings which have been put on hold at the PPA Cebu due to the expired ICC
of the pipe supplier have been released. The same has been inspected and
passed MCWD-QC.
The Contractor has just started pipelaying works after the APEC Conference
in Cebu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
71.91% |
39.32% |
-32.59% |
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavtion works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
will be reduced once the PERT/CPM will be revised. |
|
The pipes and fittings which
have been put on hold at the PPA Cebu due to the expired ICC of the pipe
supplier has been released recently. The same has been inspected and passed
MCWD-QC.
The Contractor has just started pipelaying works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
83.51% |
18.82% |
-64.69% |
Pipelaying works for the
project is ongoing. The MCWD BOD on its Resolution No. 184-2015 dated October
13, 2015 had approved and authorized the contractor to suspend digging
activities and/or excavtion works effective July 15, 2015 until October 14,
2015 in compliance with the directive of DPWH without penalty. Consequently,
the PERT/CPM needs to be revised. Revision is on process. The big slippage
will be reduced once the PERT/CPM will be revised. |
|
The pipes and fittings which
have been put on hold at the PPA Cebu due to the expired ICC of the pipe
supplier has been released recently. The same has been inspected and passed
MCWD-QC.
The Contractor has just started pipelaying works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
0.00% |
-100.00% |
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. Despite several follow-ups
by PMO, Contractor has still not submitted the crash program which is part of
the latter's commitment. Contractor has tentatively scheduled to start
project works by December 2015. |
|
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. However, the Contractor has
not yet submitted the crash program which is part of its commitment. PMO will
be sending a letter to the Contractor next month to instruct the latter to
submit the crash program. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
54.89% |
-45.11% |
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. Despite several follow-ups
by PMO, Contractor has still not submitted the crash program which is part of
the latter's commitment. |
|
The Contractor has already
submitted to PMO the former's notarized reply regarding the Contractor's
intention and commitment to complete the project. However, the Contractor has
not yet submitted the crash program which is part of its commitment. PMO will
be sending a letter to the Contractor next month to instruct the latter to
submit the crash program. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Construction of
Proposed Man-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay Construction and
Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
84.81% |
-15.19% |
The installed pump and motor at
MAN-1 had passed the field testing on September 11, 2015. |
|
The installed pump and motor at MAN-1 had passed the field
testing on September 11, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OIC - AGM Tabasa had informed the
PMO that the proposed Variation Order No.1 deleting the interconnection work
from the Contract ensuing from the non-issuance by DPWH of the necessary
excavation permit was approved by the BOD. The PMO is awaiting the BOD
Resolution before it will inform the Contractor about this. |
|
OIC - AGM Tabasa had informed the PMO that the proposed
Variation Order No.1 deleting the interconnection work from the Contract
ensuing from the non-issuance by DPWH of the necessary excavation permit was
approved by the BOD. The PMO is awaiting the BOD Resolution before it will
inform the Contractor about this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from January 1, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from January 1, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. |
|
PMO has kept following up the
Contractor regarding the latter's letter indicating that the Contractor will
continue works for the areas under LGU and the Contractor's request for the
deletion of the areas under DPWH. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
The repiping
along Brgy. Tabok was already completed and passed hydrotesting. It is
awaiting for the disinfection. Contractor is expected to explore the area for
the interconnection. |
|
Contractor has already made
significant progress in the repiping along Brgy. Tabok, Mandaue City.
Hydrotesting for this area is expected to be conducted by the early week of
November 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|