Name of
Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply
Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. |
|
The Apas Injection Point
(originally at BC Homes) has been supplying water to MCWD since December 21,
2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The PMO had
issued a notice giving the Supplier until the end of 2014 to put in place the
Data Monitoring Software and data transmission. Ending December however, the
Supplier has yet to fully comply. |
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the succesful installation and
operation of the data monitoring software. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply
Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. |
|
The Banawa Injection Point has
been supplying water to MCWD since December 9, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply
Program - Talamban Injection Point |
Pilipinas Water Resources, Inc. |
3,592 |
m3/day |
PhP |
14.21 |
/m3 |
19 Nov 2010 |
19 May 2011 |
5 Dec 2011 |
The Talamban
Injection Point has been supplying water to MCWD since December 6, 2011. |
|
The Talamban Injection Point
has been supplying water to MCWD since December 6, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The PMO had
issued a notice giving the Supplier until the end of 2014 to put in place the
Data Monitoring Software and data transmission. Ending December however, the
Supplier has yet to fully comply. |
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply
Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
The Marigondon-Gabi Injection
Point has been supplying water to MCWD since February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The PMO had
issued a notice giving the Supplier until the end of 2014 to put in place the
Data Monitoring Software and data transmission. Ending December however, the
Supplier has yet to fully comply. |
|
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the succesful installation and
operation of the data monitoring software. |
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply
Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
10 Jun 2014 |
This JV
Contract has 3 injection points located at Guadalajara, Kabajar, and Quijada
in Brgy. Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has
been delivering water to MCWD since September, November and March,
respectively. |
|
This JV Contract has 3
injection points located at Guadalajara, Kabajar, and Quijada in Brgy.
Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has been
delivering water to MCWD since September, November and March, respectively. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has
already installed the Mechanical Flowmeter for the Drop-Off Point near Well
G-4. However, the Data Monitoring Software and data transmission have yet to
be put in place. |
|
AWC has yet to install the
Mechanical Flowmeter for the Drop-Off Point near Well G-4 to be provided by
AWC under the Amendment To Contract No.1. According to AWC, the delivery of
the Flowmeter is delayed but expecting it to be delivered and eventually installed
January 2015. Likewise, the Data Monitoring Software and data transmission
have yet to be put in place. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint
Venture Projects
|
7 |
|
|
Name of Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Bulk Water Supply
Program - Pit-os Injection Point |
Abejo Waters Corporation |
4,800 |
m3/day |
PhP |
15.68 |
/m3 |
19 June 2013 |
18 June 2014 |
18 Jan 2015 |
Under this
joint venture, AWC will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
Under this joint venture, AWC
will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The BOD had
granted the request of AWC for the extension of the Day 1 of delivery. The
new day-1 of delivery will be on January 18, 2015. |
|
|
The BOD had granted the request
of AWC for the extension of the Day 1 of delivery. The new day-1 of delivery
will be on January 18, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For this
supply contract, AWC will construct 3
production wells and 1 observation well. Pump testing of Well No. 3 had been
completed while the drilling of Well No. 4 is still at 68 meters of the
target depth at 100 meters and Well No. 2
had already been completed. The installation of AWC's 4,312 meter
transmission line is completed. The pipelaying from the flowmeter vault to
the injection point was also completed. |
|
For this supply contract,
AWC will construct 3 production wells
and 1 observation well. Pump testing of Well No. 3 had been completed while
the drilling of Well No. 4 is still at 68 meters of the target depth at 100
meters and Well No. 2 still at 65
meters of the target depth of 100 meters. The installation of AWC's 4.25km
transmission line is now almost complete with less than 100m left. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The concrete
vault that will house the flowmeter assembly had been completed. The
flowmeters were already delivered, tested, and ready for installation. |
|
The concrete vault that will
house the flowmeter assembly had been completed. The flowmeters were already
delivered, tested, and ready for installation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Bulk Water Supply
Program - Cabancalan Injection Point |
Abejo Waters Corporation |
5,000 |
m3/day |
PhP |
15.68 |
/m3 |
25 Sept. 2013 |
24 Sept. 2014 |
24 Mar 2015 |
Under this
joint venture, AWC will supply a minimum of 5,000m3 of water daily to MCWD . |
|
Under this joint venture, AWC
will supply a minimum of 5,000m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The BOD had
granted the 6 months Day 1 extension requested by AWC. The new Day-1 of
delivery will be on March 14, 2015. |
|
The BOD had granted the 6
months Day 1 extension requested by AWC. The new Day-1 of delivery will be on
March 14, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For this
supply contract, AWC will construct 4
production wells. The pump testing of Well No. 4 and Well No.5 had been
completed while the drilling of the remaining 2 wells is ongoing. |
|
For this supply contract,
AWC will construct 4 production wells.
The pump testing of Well No. 4 and Well No.5 had been completed while the
drilling of the remaining 2 wells is ongoing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC had
installed 600 meters only of its 2000-meter Ø250mm transmission line since
Mandaue City had granted excavation permit for 600m only. The reason for this
is that the concrete road where AWC will lay the rest of the transmisssion
line is still under warranty period. |
|
AWC had installed 600 meters
only of its 2000-meter Ø250mm transmission line since Mandaue City had
granted excavation permit for 600m only. The reason for this is that the
concrete road where AWC will lay the rest of the transmisssion line is still
under warranty period. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has not
yet submitted the final location of the meter vault to PMO for evaluation and
approval. |
|
AWC has not yet submitted the
final location of the meter vault to PMO for evaluation and approval. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint
Venture Projects |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|