|
Name of
Project |
Contractor |
Supply Cost |
Volume |
Contract Signing |
Delivery Period |
Day 1 of Delivery |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
MCWD Bulk Water
Supply Contract (Compostela-Liloan-Consolacion Injection Points) |
Cebu Manila
Water Development Inc. |
Php |
24.59 / cu.m. |
Year 1
: |
18,000 m3/day |
18 Dec 2013 |
6 Months from
Contract Signing |
|
CMWD has been
delivering 18,000 cu.m./day at the 3 drop-off points (Compostela, Liloan and
Consolacion) and at the Consolacion temporary main delivery point since January 5, 2015. Under the Contract,
CMWD will deliver 35,000 cu.m./day at the start of the second year which will
be on January 2016. |
|
Following the
approval by LWUA of the MCWD's request for Water Rate Adjustment, the MCWD
has notified CMWD that the effective Day 1 of delivery for this bulk supply
contract is December __, 2014. |
|
|
|
|
|
Year 2 to Year 20 : |
35,000 m3/day |
|
(The Terms of
Reference has Prefatory Condition that the Contract is binding and
enforceable only upon approval of the Water Rate Adjustment requested by MCWD
with the Local Water Utilities Administration) |
|
|
|
|
|
|
|
|
|
|
|
|
CMWD had failed to meet its
commitment, as part of the agreed conditions set by MCWD for allowing CMWD to
start the delivery of water, to replace the temporary flowmeters wit the
approved ones and construct the flowmeter vaults by end of January and February,
respectively. Construction of the flowmeter vaults has yet to start while the
approved flowmeters are yet to be delivered by the supplier. |
|
CMWD had proposed a temporary
connection scheme for the 3 drop-off points and a temporary Ø1000mm injection
point at Consolacion which the BOD had approved. CMWD's target to inject its
water into MCWD's pipeline system at the latter part of December 2014 did not
materialize. Contractor's promise to construct the permanent meter vaults by
January 2015 was not materialized. Contractor has not yet completed the
design for the same. |
|
|
|
|
|
|
|
|
|
|
In lieu of the required 5,000m3 capacity tank (start
of the 2nd year of delivery), CMWD had proposed to construct 4 tanks with
combined storage capacity of 5,000m3 and with the same hydraulic grade as the existing Casili
Reservoirs. MCWD in concept had approved the proposal and required CMWD to
submit the piping details and the detailed design of the tanks. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
II. Ongoing Supply and Installation of Goods 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|