|
Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100% |
99.66% |
-0.34% |
The additional
fittings for the project have already arrived by the last week of March 2015.
The Contractor is expected to make the request for testing of these materials
by the early week of April 2015. |
|
The City of Mandaue has finally
issued the excavation permit on January 20, 2015. After determining the
actual pipelaying route that is allowed in the excavation permit, the
Contractor has found out the need for additional fittings. The Contractor is
on the process of procuring the additional fittings. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The Legal Department has
already prepared a written report regarding the termination of the project.
Hopefully, this report will be taken up by the BOD Meeting next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Ø300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
17,900,658.75 |
28 Jan 2013 |
26 Jul 2013 |
20 Nov 2013 |
100.00% |
45.50% |
-54.50% |
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The BOD has already granted the
Contractor's request and PMO's recommendation to delete the remaining
uninstalled portion of the project. The materials that were intended for the
remaining portion that is already purchased by the Contractor will not be turned-over
to MCWD. |
|
A meeting between the
Contractor, PMO, and Dir. Eugene Elizalde was conducted on February 26, 2015
to discuss the status of the project. GTCI informed MCWD that the pipelaying
works for the Madaue City component of the project, which component is under
DPWH jurisdiction, is impossible. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO will make the computation
for the final closing of the project. |
|
The Contractor cited that the
DPWH has not yet acquired the lots for its proposed road expansion project
wherein the pipelaying could be carried along the sides adjacent to the
shoulders of said road expansion. The Contractor also added that even if the DPWH
could acquire the lots, these lots will be utilized for the entire roadway.
There will not even be provisions for shoulders, because the sides of this
proposed road expansion is already privately owned. The DPWH does not allow
any construction on its road. Thus, the Contractor has no other place to lay
the pipes.
The Contractor proposed that the Mandaue section of the project be deleted
and that the materials already procured will not be turned-over by
Contractor. GTCI was advised to make a formal letter on this proposal. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The Legal Department has
already prepared a written report regarding the termination of the project.
Hopefully, this report will be taken up by the BOD Meeting next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Mactan Water Supply
Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
The Contractor had sent a
letter to MCWD to follow-up the latter on the formal instruction or directive
on whether or not the Contractor could proceed works on the portions along
Carajay Road and Dad Cleland Avenue in which there is still a pending variation
order. The Contractor pointed out that the total variation orders that will
be incurred is still less than 10% of the project's cost even if the
variation order for the said portions will be appproved. Contractor also
added that these portions are already granted excvation permits from the City
of Lapulapu. |
|
A meeting between the
Contractor, PMO and Director Eugene Elizalde was conducted on February 20,
2015 to discuss the status of the project. Director Elizalde expresses his
concerns about the Variation Orders in that it should not exceed 10% of
Original Contract Cost. Variation
Order No. 1 which was already approved
will cause a 4.02% increase. The pending Variation Order No. 2, which is for
Carajay Road and Dad Cleland Avenue will also cause additional 2.04%, if
approved. Dir. Elizalde instructed the Contractor to complete the remaining
areas such that the total variation orders will not exceed 10% of the
original contract cost. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
MCWD has replied to Contractor
reminding the latter's official reply on the discussion last month related to
the variation order. |
|
Lapulapu City has already
granted excavation permits for Carajay Road and Dad Cleland Avenue. So far,
these and the Cordova component are the only remaining areas of this project
that was granted an excavation permit. The Cordova component is almost complete.
However, no works have been conducted for Carajay Road and Dad Cleland Avenue
since the Contractor is still awaiting either the approval of Variation Order
No. 2 or the permission from BOD to proceed works on these areas. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
6.0 |
Proposed Expansion/Lateral
Project for Bacayan, Pit-os |
New Culion
Builders Co. |
Php |
22,019,495.65 |
|
22,019,495.65 |
20 Nov 2013 |
17 Jun 2014 |
- |
100.00% |
60.65% |
-39.35% |
The partial
suspension of works for the project that was issued on December 15, 2014 was
lifted by PMO on March 3, 2015. The Ø 300mm pipeline had already been
installed and is awaiting for the hydrotesting. Installation of Ø 100mm
pipeline is ongoing. |
|
The pipelaying works for this
project were still suspended by PMO so that Contractor can focus in
rectifying the defects on the asphalt restoration in its previous project in
Pit-os, Talamban. The Contractor is hoping they could complete the said
asphalt restoration so that by early week next month the suspension will be
lifted.
Also during this month, the Contractor is also conducting concrete road
restoration in this project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The negative
slippage may be greatly attributed to the delay in the issuance of the
excavation permit. The PERT/CPM of the project as well as the Time Extension
is being processed. |
|
The negative slippage may be
greatly attributed to the delay in the issuance of the excavation permit. The
PERT/CPM of the project as well as the Time Extension is being processed. |
|
|
|
7.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
- |
100.00% |
25.70% |
-74.30% |
There has been no progress in the implementation of the
project for sometime. The mechanical and electrical equipment/materials that
comprised bulk of the 74.30% uncompleted work have not been
procured/delivered until now. |
|
Most of the mechanical and electrical materials for the Man-1
Pumping Station have yet to be procured/delivered. This, despite PMO's
repeated instruction to the Contractor to speed-up the procurement and
delivery of mechanical and electrical materials. Ending this month, the
combined accomplishment for Civil,
Mechanical, and Electrical Works is at 16.35%. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM
for revision
|
As relayed by the AGM for Technical Services, the BOD had
approved the Revised PERT/CPM prepared by PMO that reflects the delay in the
issuance of both the Building Permit and Excavation Permit. Per Revised
PERT/CPM, the new project completion date will be December 31, 2014. PMO
awaits the Board Resolution before it will prepare the corresponding request
for time extension. |
|
|
Ending February 2015, the
over-all project accomplishment is 25.50% while the slippage is -74.50%.
The PMO is processing a Revised PERT/CPM to reflect the effect of the delay
in the issuance of both the Building Permit and Excavation Permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
PMO had sent a letter to NCBC
General Manager Ma'am Iting asking about the latter's intention to complete
the project. The latter had informed MCWD that they (Contractor) are
processing their letter of credit which will be used to finance the project. |
|
A meeting between NCBC's
General Manager Ma'am Iting, PMO and AGM Eugene Singson was conducted on
February 20, 2015 to inform Ma'am Iting about the BOD's decision to allow the
Contractor to continue the project implementation but subject to liquidated
damages. The meeting will also serve as a new Pre-Construction Meeting for
this project.
Although the Contractor has requested a specific duration to complete the
project, PMO reminded the former that MCWD is not so much after the liquidated
damages but that of the early completion of the project. PMO had also
instructed Ma'am Iting to fast track the procurement of the excavation permit
and that of the materials. Ma'am Iting was also instructed to make the
request of the MCWD personnel who will conduct the in-plant inspection of the
pipes. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
PMO had sent a letter to NCBC
General Manager Ma'am Iting asking about the latter's intention to complete
the project. The latter had informed MCWD that they (Contractor) are
processing their letter of credit which will be used to finance the project. |
|
A meeting between NCBC's
General Manager Ma'am Iting, PMO and AGM Eugene Singson was conducted on
February 20, 2015 to inform Ma'am Iting about the BOD's decision to allow the
Contractor to continue the project implementation but subject to liquidated
damages. The meeting will also serve as a new Pre-Construction Meeting for
this project.
Although the Contractor has requested a specific duration to complete the
project, PMO reminded the former that MCWD is not so much after the liquidated
damages but that of the early completion of the project. PMO had also
instructed Ma'am Iting to fast track the procurement of materials and
excavation permit. Ma'am Iting was also instructed to make the request of the
MCWD personnel who will conduct the in-plant inspection of the pipes. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of Proposed Cub-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
- |
100.00% |
24.25% |
-75.75% |
The DI pipes and fittings had
been delivered and passed the QC inspection, however, the tapping saddles and
PE pipes (for stub-outs) have yet to be delivered. It is PMO's policy not to
allow the start of pipelaying works unless all the needed materials are
available and had passed the QC inspection. The pipelaying woks therefore,
can not start until the lacking materials have been delivered and tested. |
|
The DI pipes are already
available and are inspected by MEQC. The flexible riser accessories had also
been inspected by MEQC and will be delivered by the supplier after full
payment by Contractor. Mechanical and electrical works are ongoing. Civil
works is completed except for the painting of perimeter fence and control
structure. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The pump intended for CUB-1 had
been delivered. Result of the lab test conducted by the MSSD showed it failed to meet the
effeciency requirement. |
|
The negative slippage is
greatly attributable to the delayed procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The uninstalled mechanical,
electrical, and pipeline components of the project have comprised the 75.75%
uncompleted work. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The BOD had approved the
suspension of Contract Time for 40 days retroactive on the day 1 (NTP) of the
Contract. The suspended period is equivalent to the number of days from the
NTP until the Contractor secured the Excavation Permit. Once the Board Resolution
is out, PMO will issue the Suspension Order. With this suspension, the new
contract completion date will be March 13, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
79.95% |
0.00% |
-79.95% |
PMO had already advised the
Contractor of their (Contractor) big slippage which could be a ground for the
termination of the project. The Contractor responded by informing PMO that
they (Contractor) are still willing to complete the project despite the big
slippage. |
|
Several coordination meetings
were conducted reminding the Contractor about fast tracking the procurement
of materials and excavation permit. Contractor is also advised to make the
request for MCWD personnel who will conduct the in-plant inspection. PMO has
also informed the Contractor that based on the PERT/CPM they (Contractor)
submitted, the project will already incur a slippage of 41.51% by the end of
this month. Contractor was also advised that a slippage beyond -15% is a
ground for termination of the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
0.00% |
0.00% |
0.00% |
A Pre-Construction meeting was
conducted on March 6, 2015. |
|
This project is yet to be
endorsed to PMO. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|