Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
0.00% |
6.25% |
6.25% |
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
0.00% |
0.00% |
0.00% |
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
0.00% |
0.00% |
0.00% |
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
0.00% |
0.00% |
0.00% |
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
Contractor is on the process of
procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
76.35% |
0.00% |
-76.35% |
PMO did not allow the
Contractor to start works on the project since they (Contractor) have not
purchased all the materials for the project. PMO had already reminded the
Contractor about their big slippage. Contractor was also instructed to fast
track the procurement of materials. |
|
Materials are already available
and have passed testing. Contractor is expected to start works by next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
0.00% |
-100.00% |
The Contractor has written a
letter to MCWD Management that it (Contractor) commits to continue and
complete the project; and to complete the project in three (3) months time
once all materials of the project is checked and complete. Contractor is
aware of the liquidated damages to be charged against them. They (Contractor)
requested that the liquidated damages be waived by MCWD of which PMO
denied.
Contractor has also requested to start pavement demolition works. PMO
denied this request since Contractor has not yet purchased all the materials
for the project. |
|
The Contractor has written a
letter to MCWD Management that it (Contractor) will complete the project in 3
months and that it will accept liquidated damages. Contractor has started
pavement cutting works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Construction of
Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
13 Mar 2015 |
100.00% |
44.15% |
-55.85% |
The installation of
the collector/distribution pipeline had been completed. Results of the
initial hydrotesting conducted by the Contractor on the installed pipeline
indicated a leakage somewhere. Work to locate the point(s) of leakage is
ongoing. |
|
The installation of the
collector/distribution line is 90%
completed and ongoing. The installed pipeline though has yet to be
hydrotested. |
|
|
|
|
|
|
|
|
|
|
|
|
|
*80.07% |
-19.93% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* -
accomplishment including the installed pipes and appurtenances yet to be
hydrotested and submersible pump assembly still subject to pump testing |
The submersible pump and motor
for Well CUB-1 had been installed. The installed pumpset is subject for
actual pump testing. Since the application for VECO power connection is still
on process, the Contractor plans to undertake the pump testing using Genset. |
|
The installation of the
submersible pump and motor for Well CUB-1 is scheduled early next month. With
most of the needed equipment/materials already available, a substantial
accomplishment is expected next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated damages will be
imposed upon the Contractor reckoned from March 14, 2015 for its failure to
complete the project within the approved time. |
|
Liquidated damages will be
imposed upon the Contractor reckoned from March 14, 2015 for its failure to
complete the project within the approved time. The MCWD on its May 14, 2015 letter,
allowed the Contractor to continue his work for 60 days subject to liquidated
damages. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
Contractor has ignored MCWD's
letter to the former's General Manager Ma'am Iting to submit proof until May
15, 2015 that it had already purchased the materials. PMO is recommending to
MCWD Management the termination of the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
Contractor has ignored MCWD's
letter to the former's General Manager Ma'am Iting to submit proof until May
15, 2015 that it had already purchased the materials. PMO is recommending to
MCWD Management the termination of the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
26.03% |
-73.97% |
There is hardly progress in the implementation of the
project. MCWD invited Dr. Pericles P. Dakay, Dakay Construction CEO, for a
meeting on July 15, 2015 to discuss the project. |
|
There is hardly progress in the implementation of the
project. The major mechanical and electrical equipment/materials that
comprised bulk of the uncompleted work have yet to be procured/delivered. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For failing to complete the project within the approved time,
liquidated damages will be imposed on the Contractor starting January 1,
2015. |
|
|
For failing to complete the project within the approved time,
liquidated damages will be imposed upon the Contractor starting January 1,
2015. The May 14, 2015 letter of MCWD
allowed the Contractor, subject to liquidated damages, 60 calendar days
period to complete the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
PMO has again called the
Contractor for a meeting on July 15, 2015 to settle the issues concerning the
status of the project. |
|
PMO has been trying to set up a
meeting with the Contractor to settle the issue regarding the status of the
project. So far, the Contractor is still unavailable. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100% |
99.66% |
-0.34% |
PMO has again
called the Contractor for a meeting on July to discuss the project. PMO has
found that the Contractor is having a problem about who will be supervising
the project. |
|
PMO has again reminded the
Contractor to start works immediately. Hopefully, the Contractor will
commence works by next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|