Name of
Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply
Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. To date, however, the Supplier has yet to comply
with the data transmission requirement. |
|
The Apas Injection Point
(originally at BC Homes) has been supplying water to MCWD since December 21,
2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. The Phase I of this Joint Venture (i.e.
installation of production and supply facilities) will be declared fully
completed only after the succesful installation and operation of the data
monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply
Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. To
date, however, the Supplier has yet to comply with the data transmission
requirement. |
|
The Banawa Injection Point has
been supplying water to MCWD since December 9, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the Supplier have complied the data
transmission requirement. |
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply
Program - Talamban Injection Point |
Pilipinas Water Resources, Inc. |
3,592 |
m3/day |
PhP |
14.21 |
/m3 |
19 Nov 2010 |
19-May-11 |
5 Dec 2011 |
The Talamban
Injection Point had started the supply of water to MCWD on December 6,
2011. |
|
The Talamban Injection Point
has been supplying water to MCWD since December 6, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO learned
from PDD that PWRI had stopped supplying water to MCWD since June 2, 2015.
The PDD is handling this supply stoppage issue. |
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply
Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
The Marigondon-Gabi Injection
Point has been supplying water to MCWD since February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have complied the
data transmission requirement. |
|
|
The PMO had issued a notice
giving the Supplier until the end of 2014 to put in place the Data Monitoring
Software and data transmission. Ending December however, the Supplier has yet
to fully comply. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply
Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
10 Jun 2014 |
This JV
Contract has 3 injection points located at Guadalajara, Kabajar, and Quijada
in Brgy. Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has
been delivering water to MCWD since September, November and March,
respectively. |
|
This JV Contract has 3
injection points located at Guadalajara, Kabajar, and Quijada in Brgy.
Guadalupe. The Guadalajara, Kabajar and Quijada Injection Points has been
delivering water to MCWD since September, November and March, respectively. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The drop-off
point to be provided by the Supplier under the Amendment to TOR dated July
11, 2014, remains uncompleted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the Supplier have completed the
drop-off point and complied the data transmission requirement. |
|
AWC has already installed the
Mechanical Flowmeter for the Drop-Off Point near Well G-4. However, the Data
Monitoring Software and data transmission have yet to be put in place. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Bulk Water Supply
Program - Pit-os Injection Point |
Abejo Waters Corporation |
4,800 |
m3/day |
PhP |
15.68 |
/m3 |
19 June 2013 |
18 June 2014 |
18 Jan 2015 |
Under this
joint venture, AWC will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
Under this joint venture, AWC
will supply a minimum of 4,800m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Pit-os
Injection Point has been delivering water into the MCWD distribution system
since March 12, 2015. The volume of delivery however is below the required
minimum. AWC is presently working on one additional well to supplement its
supply. |
|
|
The BOD had granted the request
of AWC for the extension of the Day 1 of delivery. The new day-1 of delivery
will be on January 18, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC was
allowed to start the delivery of water under
BOD Resolution No.025-2015 with conditions, among others, that AWC
will install the lacking fittings (4 support bush and 2 harness sets) within
4 months from the start of the water delivery. The 4-month period will end on
July 12, 2015. On June 24, 2015, AWC had requested for water interruption to
install the lacking fittings but was denied by PMO since the fabricated
harness sets are unacceptable. Until now, AWC is still working to comply with
the harness set requirement. |
|
For this supply contract,
AWC will construct 3 production wells
and 1 observation well. Pump testing of Well No. 3 had been completed while
the drilling of Well No. 4 is still at 68 meters of the target depth at 100
meters and Well No. 2 had already been
completed. The installation of AWC's 4,312 meter transmission line is
completed. The pipelaying from the flowmeter vault to the injection point was
also completed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has yet to
comply with the data transmission requirement. AWC informed PMO that it is
hiring an IT Professional to work on the compliance of this requirement. |
|
The concrete vault that will
house the flowmeter assembly had been completed. The flowmeters were already
installed and hydrotested. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint
Venture Projects
|
7 |
|
|
|
|
Name of Contract |
Joint Venture Partner |
Minimum
Volume |
Supply Cost |
Date of Contract
Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Bulk Water Supply
Program - Cabancalan Injection Point |
Abejo Waters Corporation |
5,000 |
m3/day |
PhP |
15.68 |
/m3 |
25 Sept. 2013 |
24 Sept. 2014 |
Extended to 6 months
from issuance of Excavation Permit by Mandaue City per BOD Resolution
No.111-2014 |
Under this
joint venture, AWC will supply a minimum of 5,000m3 of water daily to MCWD . |
|
Under this joint venture, AWC
will supply a minimum of 5,000m3 of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC informed
PMO that it will operate 2 production wells only for this supply contract
instead of the previously planned 4 wells since the combined discharge of the
completed 2 wells is more than enough to meet the required supply volume. |
|
The BOD had granted the 6
months Day 1 extension requested by AWC. The new Day-1 of delivery will be on
March 24, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Only 600
meters of AWC's 2,000-meter long Ø250mm transmission line had been installed
as Mandaue City granted excavation permit for 600m only. The rest, Mandaue
City did not issue excavation permit for the reason that the concrete road is still under warranty and still subject
to COA audit. |
|
For this supply contract,
AWC will construct 4 production wells.
The pump testing of Well No. 4 and Well No.5 had been completed while the
drilling of the remaining 2 wells is ongoing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO had
endorsed to the Engineering Department for evaluation/approval AWC's proposed
new pipe route and injection point. The evaluation by ED is ongoing. |
|
AWC had installed 600 meters
only of its 2000-meter Ø250mm transmission line since Mandaue City had
granted excavation permit for 600m only. The reason for this is that the
concrete road where AWC will lay the rest of the transmisssion line is still
under warranty period. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section III. Ongoing Joint
Venture Projects |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|