Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
17.84% |
16.47% |
-1.37% |
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
12.02% |
0.00% |
-12.02% |
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
7.68% |
0.00% |
-7.68% |
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
7.01% |
0.00% |
-7.01% |
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
Contractor is on the process of
procurement of materials. An in-plant inspection of the DI pipes had been
conducted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
93.83% |
0.00% |
-93.83% |
Contractor is still securing
the remaining materials for the project as PMO is strictly imposing that the
Contractor is not allowed to start unless all the materials have been
inspected and passed testing. |
|
PMO did not allow the
Contractor to start works on the project since they (Contractor) have not
purchased all the materials for the project. PMO had already reminded the
Contractor about their big slippage. Contractor was also instructed to fast
track the procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
0.00% |
-100.00% |
Contractor has started
pipelaying works on July 31, 2015. Full implementation works on the project
is expected on August. |
|
The Contractor has written a
letter to MCWD Management that it (Contractor) commits to continue and
complete the project; and to complete the project in three (3) months time
once all materials of the project is checked and complete. Contractor is
aware of the liquidated damages to be charged against them. They (Contractor)
requested that the liquidated damages be waived by MCWD of which PMO
denied.
Contractor has also requested to start pavement demolition works. PMO
denied this request since Contractor has not yet purchased all the materials
for the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Construction of
Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
13 Mar 2015 |
100.00% |
47.71% |
-52.29% |
The chlorination
equipment (booster pump, suction/discharge pipings, chlorine gas tank, etc.)
have been installed. Work to locate the leak/s of the installed DI collector
pipeline is ongoing. |
|
The installation of
the collector/distribution pipeline had been completed. Results of the
initial hydrotesting conducted by the Contractor on the installed pipeline
indicated a leakage somewhere. Work to locate the point(s) of leakage is
ongoing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
*86.44% |
-13.56% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* - accomplishment including the
installed pipes and appurtenances yet to be hydrotested and submersible pump
assembly still subject to pump testing |
The Visayan Electric
Company (VECO) has energized the power connection for CUB-1 on July 26, 2015.
Following this, the pump field testing is scheduled by the first week of
August. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The submersible pump and motor
for Well CUB-1 had been installed. The installed pumpset is subject for
actual pump testing. Since the application for VECO power connection is still
on process, the Contractor plans to undertake the pump testing using Genset. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from March 14, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages will be
imposed upon the Contractor reckoned from March 14, 2015 for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
26.03% |
-73.97% |
Mr. Petrious P. Dakay represented DCDC during the July 15,
2015 meeting attended by the EXECOM to discuss DCDC's unsatisfactory project
performance. During the meeting, Mr. Dakay owned up the delay and admitted
that the company had problems on the procurement of materials. On the same
meeting, Mr. Dakay asked that DCDC be allowed to continue its work and
committed to finish the project by August 31, 2015. The EXECOM has granted
the request subject to the imposition of liquidated damages. |
|
There is hardly progress in the implementation of the
project. MCWD invited Dr. Pericles P. Dakay, Dakay Construction CEO, for a
meeting on July 15, 2015 to discuss the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The installattion of the pump
and motor for MAN-1 is scheduled by the first week of August. PMO had asked
DCDC to prepare and submit a Work Schedule
until August 31, 2015 for the remaining works. |
|
|
For failing to complete the project within the approved time,
liquidated damages will be imposed on the Contractor starting January 1,
2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
PMO has again called the
Contractor for a meeting on July 15, 2015 to settle the issues concerning the
status of the project. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
The Contractor
has wrote to PMO formally informing the latter of the former's commitment to
complete the project in three (3) months starting on August 1, 2015 to
November 2015. |
|
PMO has again called the
Contractor for a meeting on July to discuss the project. PMO has found that
the Contractor is having a problem about who will be supervising the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|