Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100% |
99.66% |
-0.34% |
The City of
Mandaue has finally issued the excavation permit on January 20, 2015.
Contractor will conduct a final inspection next month to determine the actual
route allowed in the permit. After which, the Contractor will finalize the
material take-off to suit the actual pipe route. |
|
Despite constant follow-ups by
PMO, the Contractor is still on the process of securing the excavation
permit. Contractor has yet to issue the bond to the City of Mandaue which
bond is a requirement for the City to issue the excavation permit.
PMO had set a meeting with the Contractor on the first week of January 2015
to the determine the cause of the delay in securing the excavation permit and
to resolve the same. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The Legal
Department has already prepared a written report regarding the termination of
the project. Hopefully, this report will be taken up by the BOD Meeting next
month. |
|
PMO, GM and Ana Construction
had a meeting to come up with a solution regarding the termination of the
project. The issue was not yet resolve because Ana Construction demanded the
following: that MCWD will pay for the cost of the materials on hand without
material testing, that the pipes intalled will be paid by MCWD even if these
installed pipes are not yet hydrotested, and that MCWD will refund Ana
Construction for the cost of the bidding.
There was also a meeting between MCWD top management and Ana Construction's
joint venture partner Supreme Abf. The latter has denied that it is not in a
joint venture with Ana Construction.
All these matters are already being handled by the Legal Department which
is seeking remedies through legal actions. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Ø300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
17,900,658.75 |
28 Jan 2013 |
26 Jul 2013 |
20 Nov 2013 |
100.00% |
45.50% |
-54.50% |
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor had already
submitted to MCWD BOD the former's request for the termination of the Mandaue
work component of the project. However, the BOD has extended the Contractor
another time to secure the necessary permit. Thus, the Contractor had again
requested the DPWH for an excavation permit on November 2014. However, the
latter has once again denied said request. |
|
The Contractor had already
submitted to MCWD BOD the former's request for the termination of the Mandaue
work component of the project. However, the BOD has extended the Contractor
another time to secure the necessary permit. The Contractor is currently making
follow-ups with the DPWH Mandaue regarding the permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The Legal
Department has already prepared a written report regarding the termination of
the project. Hopefully, this report will be taken up by the BOD Meeting next
month. |
|
The Legal Department is
handling the matters regarding the unilateral termination of this project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
Lapulapu City has already
granted excavation permits for Carajay Road and Dad Cleland Avenue. PMO and
the Contractor had a joint survey for these areas to determine the projected
variation order which is expected due to the conditions imposed in the excavation
permit. PMO had instructed the Contractor to request MCWD BOD for the
approval of this projected variation order together with the variation order
for B. Benedicto Road. |
|
Lapulapu City has already
granted excavation permits for Carajay Road and Dad Cleland Avenue. PMO and
the Contractor had a joint survey for these areas to determine the projected
variation order which is expected due to the conditions imposed in the excavation
permit. PMO had instructed the Contractor to request MCWD BOD for the
approval of this projected variation order together with the variation order
for B. Benedicto Road. |
|
|
|
|
|
|
` |
|
|
|
|
|
PERT/CPM for revision |
The Variation Order for B.
Benedicto Road (V.O. 1) was taken up by the BOD. The project Varation Order
for Carajay Road and Dad Cleland Avenue (V.O. 2) was already endorsed by PMO
to the BOD. Howver, this is yet to be taken up by the latter. There is no physical
activity for this month since the Contractor is still seeking the approval of
the proposed Variation Order for Carajay Road and Dad Cleland Avenue or the
permission from the BOD before Contractor can proceed works. |
|
There is no physical activity
for this month since the Contractor is still seeking the approval of the
proposed Variation Order for Carajay Road and Dad Cleland Avenue before
Contractor can proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Expansion/Lateral
Project for Bacayan, Pit-os |
New Culion
Builders Co. |
Php |
22,019,495.65 |
|
22,019,495.65 |
20 Nov 2013 |
17 Jun 2014 |
- |
100.00% |
30.66% |
-69.34% |
Pipelaying
works of the project is ongoing except for the area going to Sitio Kauswagan
where the Contractor was instructed by the Brgy. Captain not to proceed works
until MCWD could provide water to the Sitio. PMO had advised the Contractor
to secure a certification from Talamban Barangay Council regarding the work
stoppage. Contractor was also advised to make their request regarding time
extension directly to MCWD BOD. |
|
Pipelaying works of the project
is ongoing except for the area going to Sitio Kauswagan where the Contractor
was instructed by the Brgy. Captain not to proceed works until MCWD could
provide water to the Sitio. PMO had advised the Contractor to secure a certification
from Talamban Barangay Council regarding the work stoppage. Contractor was
also advised to make their request regarding time extension directly to MCWD
BOD. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The partial
suspension issued by PMO for the works that are related to pipelaying is
still in effect. Contractor is presently focusing on rectifying the errors in
its previous contract. |
|
PMO had issued the Contractor a
partial suspension for the works that related to pipelaying and instructed
the contractor to focus on the restoration and hydrotesting of the newly
installed pipes. The suspension will be lifted once the restoration and hydrotesting
is already cleared. PMO had stressed out to the Contractor that the
suspension cannot be a ground for time extension. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The negative
slippage may be greatly attributed to the delay in the issuance of the
excavation permit and partly on the instruction of the Brgy. Captain for the
Contractor to not proceed works along Sitio Kauswagan. The PERT/CPM of the
project as well as the Time Extension is being processed. |
|
The negative slippage was
brought about by the delay in the issuance of the excavation permit. The
PERT/CPM of the project as well as the Time Extension is being processed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
06 Jun 2014 |
- |
100.00% |
24.28% |
-75.72% |
Most of the mechanical and electrical materials for the Man-1
Pumping Station have yet to be procured/delivered. This, despite PMO's
repeated instruction to the Contractor to speed-up the procurement and
delivery of mechanical and electrical materials. Ending this month, the
accomplishment on Civil, Mechanical,
and Electrical Works are 85%, 11% and 0.60%, respectively. |
|
Most of the mechanical and electrical materials for the Man-1
Pumping Station have yet to be procured/delivered. This, despite PMO's
repeated instruction to the Contractor to speed-up the procurement and
delivery of mechanical and electrical materials. Ending this month, the
accomplishment on Civil, Mechanical,
and Electrical Works are 85%, 11% and 0.60%, respectively. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM
for revision
|
The installation of the Ø150mm collector pipeline is ongoing;
ending this month, the Contractor had installed 132m of the 156m to be
installed under the Contract. |
|
The installation of the Ø150mm collector pipeline is ongoing;
ending this month, the Contractor had installed 132m of the 156m to be
installed under the Contract. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ending January 2015, the over-all project accomplishment is
24.28% while the slippage is -75.72%. |
|
Ending December 2014, the over-all project accomplishment is
24.28% while the slippage is -75.72%. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The PMO is processing a Revised PERT/CPM to reflect the
effect of the delay in the issuance of both the Building Permit and
Excavation Permit. The GM had informed PMO that the Contractor must be the
one to make the request to the BOD for the revision of the PERT/CPM. PMO had
already informed the Contractor on this. |
|
The PMO is processing a Revised PERT/CPM to reflect the
effect of the delay in the issuance of both the Building Permit and
Excavation Permit. The GM had informed PMO that the Contractor must be the
one to make the request to the BOD for the revision of the PERT/CPM. PMO had
already informed the Contractor on this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
43.70% |
0.00% |
-43.70% |
MCWD Board of Directors had
granted Contractor's request to continue implementation of the project
without time extension and to pay the corresponding liquidated damages. |
|
MCWD top management had allowed
the Contractor to continue works with the project provided that the latter
would commit to the former that the project will be completed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
MCWD Board of Directors had
granted Contractor's request to continue implementation of the project
without time extension and to pay the corresponding liquidated damages. |
|
MCWD top management had allowed
the Contractor to continue works with the project provided that the latter
would commit to the former that the project will be completed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of Proposed Cub-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
- |
91.78% |
14.43% |
-77.35% |
Most of the activities during
this period were focused on concreting works, steel works, and installation
of pumping station discharge line. Steel doors at pump structure and entrance
gate were already installed. Electrical and mechanical conduits at slab on
grade were also installed. |
|
The Mechanical and Electrical
Works represent bulk of the 46.67% target for the month. The Contractor however, is still processing the
procurement of most of the mechanical and electrical items including the DI
pipes and appurtenances for the collector line. As a result, the project
slippage has balooned from -1.40% last month to -39.88% this month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The negative slippage were
greatly attributable to the delayed procurement of materials. |
|
PMO had ordered the Contractor
to speed-up the procurement of materials. PMO will call a meeting early
January next year to discuss the procurement status.
Ending December 2014, the accomplishment for Civil, Mechanical, and
Electrical Works is 88.54%, 14.51% and 7.29%, respectively. Accomplishment
for the collector pipeline is 0%. Over-all, the project has 10.79% physical accomplishment and a
-39.88% slippage. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
0.00% |
0.00% |
0.00% |
Contractor is on the process of
securing the excavation permit and procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|