|
Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100% |
99.66% |
-0.34% |
The City of
Mandaue has finally issued the excavation permit on January 20, 2015. After
determining the actual pipelaying route that is allowed in the excavation
permit, the Contractor has found out the need for additional fittings. The
Contractor is on the process of procuring the additional fittings. |
|
The City of Mandaue has finally
issued the excavation permit on January 20, 2015. Contractor will conduct a
final inspection next month to determine the actual route allowed in the
permit. After which, the Contractor will finalize the material take-off to
suit the actual pipe route. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The Legal
Department has already prepared a written report regarding the termination of
the project. Hopefully, this report will be taken up by the BOD Meeting next
month. |
|
The Legal Department has
already prepared a written report regarding the termination of the project.
Hopefully, this report will be taken up by the BOD Meeting next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Ø300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
17,900,658.75 |
28 Jan 2013 |
26 Jul 2013 |
20 Nov 2013 |
100.00% |
45.50% |
-54.50% |
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
A meeting between the
Contractor, PMO, and Dir. Eugene Elizalde was conducted on February 26, 2015
to discuss the status of the project. GTCI informed MCWD that the pipelaying
works for the Madaue City component of the project, which component is under
DPWH jurisdiction, is impossible. |
|
The Contractor had already
submitted to MCWD BOD the former's request for the termination of the Mandaue
work component of the project. However, the BOD has extended the Contractor
another time to secure the necessary permit. Thus, the Contractor had again
requested the DPWH for an excavation permit on November 2014. However, the
latter has once again denied said request. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor cited that the
DPWH has not yet acquired the lots for its proposed road expansion project
wherein the pipelaying could be carried along the sides adjacent to the
shoulders of said road expansion. The Contractor also added that even if the DPWH
could acquire the lots, these lots will be utilized for the entire roadway.
There will not even be provisions for shoulders, because the sides of this
proposed road expansion is already privately owned. The DPWH does not allow
any construction on its road. Thus, the Contractor has no other place to lay
the pipes. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor proposed that
the Mandaue section of the project be deleted and that the materials already
procured will not be turned-over by Contractor. GTCI was advised to make a
formal letter on this proposal. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The Legal
Department has already prepared a written report regarding the termination of
the project. Hopefully, this report will be taken up by the BOD Meeting next
month. |
|
The Legal Department has
already prepared a written report regarding the termination of the project.
Hopefully, this report will be taken up by the BOD Meeting next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting between the
Contractor, PMO and Director Eugene Elizalde was conducted on February 20,
2015 to discuss the status of the project. Director Elizalde expresses his
concerns about the Variation Orders in that it should not exceed 10% of
Original Contract Cost. Variation
Order No. 1 which was already approved
will cause a 4.02% increase. The pending Variation Order No. 2, which is for
Carajay Road and Dad Cleland Avenue will also cause additional 2.04%, if
approved. Dir. Elizalde instructed the Contractor to complete the remaining
areas such that the total variation orders will not exceed 10% of the
original contract cost. |
|
Lapulapu City has already
granted excavation permits for Carajay Road and Dad Cleland Avenue. PMO and
the Contractor had a joint survey for these areas to determine the projected
variation order which is expected due to the conditions imposed in the excavation
permit. PMO had instructed the Contractor to request MCWD BOD for the
approval of this projected variation order together with the variation order
for B. Benedicto Road. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
Lapulapu City has already
granted excavation permits for Carajay Road and Dad Cleland Avenue. So far,
these and the Cordova component are the only remaining areas of this project
that was granted an excavation permit. The Cordova component is almost complete.
However, no works have been conducted for Carajay Road and Dad Cleland Avenue
since the Contractor is still awaiting either the approval of Variation Order
No. 2 or the permission from BOD to proceed works on these areas. |
|
The Variation Order for B.
Benedicto Road (V.O. 1) was taken up by the BOD. The project Varation Order
for Carajay Road and Dad Cleland Avenue (V.O. 2) was already endorsed by PMO
to the BOD. Howver, this is yet to be taken up by the latter. There is no physical
activity for this month since the Contractor is still seeking the approval of
the proposed Variation Order for Carajay Road and Dad Cleland Avenue or the
permission from the BOD before Contractor can proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Expansion/Lateral
Project for Bacayan, Pit-os |
New Culion
Builders Co. |
Php |
22,019,495.65 |
|
22,019,495.65 |
20 Nov 2013 |
17 Jun 2014 |
- |
100.00% |
34.24% |
-65.76% |
The pipelaying
works for this project were still suspended by PMO so that Contractor can
focus in rectifying the defects on the asphalt restoration in its previous
project in Pit-os, Talamban. The Contractor is hoping they could complete the
said asphalt restoration so that by early week next month the suspension will
be lifted. |
|
Pipelaying works of the project
is ongoing except for the area going to Sitio Kauswagan where the Contractor
was instructed by the Brgy. Captain not to proceed works until MCWD could
provide water to the Sitio. PMO had advised the Contractor to secure a certification
from Talamban Barangay Council regarding the work stoppage. Contractor was
also advised to make their request regarding time extension directly to MCWD
BOD. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Also during
this month, the Contractor is also conducting concrete road restoration in
this project. |
|
The partial suspension issued
by PMO for the works that are related to pipelaying is still in effect.
Contractor is presently focusing on rectifying the errors in its previous
contract. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The negative
slippage may be greatly attributed to the delay in the issuance of the
excavation permit. The PERT/CPM of the project as well as the Time Extension
is being processed. |
|
The negative slippage may be
greatly attributed to the delay in the issuance of the excavation permit and
partly on the instruction of the Brgy. Captain for the Contractor to not
proceed works along Sitio Kauswagan. The PERT/CPM of the project as well as
the Time Extension is being processed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
06 Jun 2014 |
- |
100.00% |
25.50% |
-74.50% |
Most of the mechanical and electrical materials for the Man-1
Pumping Station have yet to be procured/delivered. This, despite PMO's
repeated instruction to the Contractor to speed-up the procurement and
delivery of mechanical and electrical materials. Ending this month, the
combined accomplishment for Civil,
Mechanical, and Electrical Works is at 16.35%. |
|
Most of the mechanical and electrical materials for the Man-1
Pumping Station have yet to be procured/delivered. This, despite PMO's
repeated instruction to the Contractor to speed-up the procurement and
delivery of mechanical and electrical materials. Ending this month, the
accomplishment on Civil, Mechanical,
and Electrical Works are 85%, 11% and 0.60%, respectively. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM
for revision
|
Ending February 2015, the over-all project accomplishment is
25.50% while the slippage is -74.50%. |
|
The installation of the Ø150mm collector pipeline is ongoing;
ending this month, the Contractor had installed 132m of the 156m to be
installed under the Contract. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The PMO is processing a Revised PERT/CPM to reflect the
effect of the delay in the issuance of both the Building Permit and
Excavation Permit. |
|
Ending January 2015, the over-all project accomplishment is
24.28% while the slippage is -75.72%. The PMO is processing a Revised
PERT/CPM to reflect the effect of the delay in the issuance of both the
Building Permit and Excavation Permit. The GM had informed PMO that the
Contractor must be the one to make the request to the BOD for the revision of
the PERT/CPM. PMO had already informed the Contractor on this. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
A meeting between NCBC's
General Manager Ma'am Iting, PMO and AGM Eugene Singson was conducted on
February 20, 2015 to inform Ma'am Iting about the BOD's decision to allow the
Contractor to continue the project implementation but subject to liquidated
damages. The meeting will also serve as a new Pre-Construction Meeting for
this project. |
|
MCWD Board of Directors had
granted Contractor's request to continue implementation of the project
without time extension and to pay the corresponding liquidated damages. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Although the Contractor has
requested a specific duration to complete the project, PMO reminded the
former that MCWD is not so much after the liquidated damages but that of the
early completion of the project. PMO had also instructed Ma'am Iting to fast track
the procurement of the excavation permit and that of the materials. Ma'am
Iting was also instructed to make the request of the MCWD personnel who will
conduct the in-plant inspection of the pipes. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
A meeting between NCBC's
General Manager Ma'am Iting, PMO and AGM Eugene Singson was conducted on
February 20, 2015 to inform Ma'am Iting about the BOD's decision to allow the
Contractor to continue the project implementation but subject to liquidated
damages. The meeting will also serve as a new Pre-Construction Meeting for
this project. |
|
MCWD Board of Directors had
granted Contractor's request to continue implementation of the project
without time extension and to pay the corresponding liquidated damages. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Although the Contractor has
requested a specific duration to complete the project, PMO reminded the
former that MCWD is not so much after the liquidated damages but that of the
early completion of the project. PMO had also instructed Ma'am Iting to fast track
the procurement of materials and excavation permit. Ma'am Iting was also
instructed to make the request of the MCWD personnel who will conduct the
in-plant inspection of the pipes. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of Proposed Cub-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
- |
100.00% |
16.06% |
-83.94% |
The DI pipes are already
available and are inspected by MEQC. The flexible riser accessories had also
been inspected by MEQC and will be delivered by the supplier after full
payment by Contractor. Mechanical and electrical works are ongoing. Civil
works is completed except for the painting of perimeter fence and control
structure. |
|
Most of the activities during
this period were focused on concreting works, steel works, and installation
of pumping station discharge line. Steel doors at pump structure and entrance
gate were already installed. Electrical and mechanical conduits at slab on
grade were also installed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The negative slippage is
greatly attributable to the delayed procurement of materials. |
|
The negative slippage were
greatly attributable to the delayed procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
41.51% |
0.00% |
-41.51% |
Several coordination meetings
were conducted reminding the Contractor about fast tracking the procurement
of materials and excavation permit. Contractor is also advised to make the
request for MCWD personnel who will conduct the in-plant inspection. PMO has
also informed the Contractor that based on the PERT/CPM they (Contractor)
submitted, the project will already incur a slippage of 41.51% by the end of
this month. Contractor was also advised that a slippage beyond -15% is a
ground for termination of the project. |
|
Contractor is on the process of
securing the excavation permit and procurement of materials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
0.00% |
0.00% |
0.00% |
This project is yet to be
endorsed to PMO. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|