Name of Project  Brief Description of the Project Subdivision/Hotel/Condo Name Developer / Owner MCWD Supervising Unit Project Amount Project Duration Date Started Target Completion Date Accomplish-          ment                             To Date Remarks Previous Month's Remarks
1. Water System                  
1.0 Prop. Water Distribution System for EastGate Subdivision (Matumbo, Pusok, Lapulapu) 49.54 LM x 75mm dia EastGate Subdivision Urban Enclaves Inc. Project Management Office PhP      514,061.34 11 CD Jul 15, 2011 Jul 26, 2011 20.00% Upon site inspection by MCWD inspector, developer has installed individual service connections directly to the MCWD stub-out outside of the subdivision. It is suggesting a possibility that the contractor may cancel the project. Upon site inspection by MCWD inspector, developer has installed individual service connections directly to the MCWD stub-out outside of the subdivision. It is suggesting a possibility that the contractor may cancel the project.
2.0 Prop. PVC Water Distribution System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) pu Amara Subdivision Cebu Holdings, Inc. Project Management Office PhP   92 CD May 15, 2012 Aug 14, 2012 96.00% Contractor is on the process of purchasing the handhole cover and AV/AR head. Contractor is on the process of purchasing the handhole cover and AV/AR head.
3.0 Prop. Rerouting of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu)  1,650 LM x 150mm dia. Amara Subdivision Cebu Holdings, Inc. Project Management Office PhP   92 CD May 15, 2012 Aug 14, 2012 98.00% The only remaining work is the disinfection of a portion of the water system of the subdivision at phase 3b. The only remaining work is the disinfection of a portion of the water system of the subdivision at phase 3b.
4.0 Prop. Water Distribution System for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City) 6,920 LM x 75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia., 151 LM x 250mm dia. Pueblo De Oro Communities (Horizon, La Aldea Del Mar, and Parkplace) Pueblo De Oro Development Corp. Project Management Office PhP ############       38.00% Developer is implementing the pipelaying works on this project area by area. Four areas have already been turned-over to MCWD. Developer is implementing the pipelaying works on this project area by area. Four areas have already been turned-over to MCWD.
5.0 Prop. PVC Water Distribution System for Kaiser Townhouse II 510 LM x 100mm dia. PVC and 75mm dia. PVC water distribution line Kaiser Townhouse II Kaiser Urban Development Corp. Project Management Office PhP   1,687,773.35   Jun 24, 2013   80.00% Remaining works are hydrotesting, disinfection and interconnection. PMO has not yet accepted the project since the Developer not yet fully developed the remaining area (Phase 2). Remaining works are hydrotesting, disinfection and interconnection.
6.0 Prop. Water Distribution Systems for Mactan Plains Subdivision 114 LM x 100mm dia. PVC and 810 LM 75mm dia. PVC water distribution line Mactan Plains Subdivision Pacific Land Ventures and Property Development, Inc. Project Management Office PhP   1,617,764.80   Jun 25, 2013     Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
7.0 Prop. Water System Design for Goldmine Residences (Bangkal-Mahayahay-Soong, Lapulapu City) 236 LM x 150mm dia. PVC, 32 LM 100mm dia. PVC, 152 LM 75mm dia. PVC, 617 LM 50mm dia. PVC Goldmine Residences Heritage Supreme Land Developer, Inc. Project Management Office PhP   3,215,481.65   Oct 14, 2013     Developer is awaiting for the well to be constructed by EWRD-KC. After the well, the installation of the interconnecting pipeline will have to be done by MCWD before the water system of the subdivision will be implemented. Developer is awaiting for the well to be constructed by EWRD-KC. After the well, the installation of the interconnecting pipeline will have to be done by MCWD before the water system of the subdivision will be implemented.
8.0 Prop. Water Distribution Systems for City Homes - Mandaue (J.S. Alinsug St., Mandaue City, Cebu) 42 LM 75mm dia. PVC, 218 LM 50mm dia. PVC City Homes Mandaue Grand Land, Inc. Project Management Office PhP      870,061.25   Oct 23, 2013   85.00% Remaining works are hydrotesting, flushing and disinfection. Remaining works are hydrotesting, flushing and disinfection.
9.0 Prop. Water Sytem for Graceland 1 & Graceland Annex Subdivision (Brgy. Buaya, Mactan, Lapulapu City) 39 lm x 100mm dia PVC, 29 lm x 50mm dia PVC Graceland 1 and Graceland Annex Subdivision Kaiser Urban Development Corp. Project Management Office PhP      858,046.50 11 Working Days Jul 7, 2014 Jul 21, 2014 50.00% Pipelaying is ongoing. Pipelaying is ongoing.
10.0 Prop. Water Distribution Lines for Colorado Dos (Brgy. Cotcot, Liloan, Cebu) 338 lm x 100mm dia PVC, 570 lm x 75mm dia PVC, and 157 lm x 50mm dia PVC Colorado Dos Subdivision Primary Homes, Incorporated Project Management Office PhP   2,813,740.02 80 Working Days Aug 8, 2014 Oct 26, 2014 80.00% Remaining works are: the installation of hydrant head, and as-built drawings. Pipelaying is ongoing.
11.0 Prop. Water System Design for South Covina Subdivision (Brgy. Dumlog, Talisay City, Cebu) 42 lm x 100mm dia PVC, 110 lm x 75mm dia PVC, and 346 lm x 50mm dia PVC South Covina Subdivision Athecor Development Corporation Project Management Office PhP   1,177,338.75 71 Working Days Sep 18, 2014 Dec 17, 2014   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
12.0 Prop. Water Distribution System for Peninsula Subdivision (Sudtungan Road, Brgy. Basak, Lapulapu City) 42 lm x 100mm dia PVC, 110 lm x 75mm dia PVC, and 346 lm x 50mm dia PVC Peninsula Place Subdivision Peninsula Resort Corporation Project Management Office PhP   1,196,027.58 52 Calendar Days Oct 1, 2014 Nov 21, 2014 10.00% Pipelaying is ongoing. Pipelaying is ongoing.
13.0 Prop. Water Distribution System for Rose Pike Subdivision (Forest Hills, Kalubihan, Banawa, Brgy. Guadalupe, Cebu City) 228 lm x 50mm dia PVC Rose Pike Subdivision F.S. Baltazar Builders Project Management Office PhP   1,415,707.20 45 Calendar Days Feb 17, 2015 Apr 2, 2015 30.00% Pipelaying is ongoing. Developer is on the process of procurement of materials and excavation permit.
14.0 Prop. Water Distribution System for Villa Azalea Subdivision Phase 2 270 lm x 200mm dia PVC, 222 lm x 150mm dia PVC, 612 lm x 100mm dia PVC, 438 lm x 75mm dia PVC, and 492 lm x 50mm dia PVC Villa Azalea Subdivision Phase 2 Mega Crown Realty and Development Corp. Project Management Office PhP   5,964,029.61 225
Calendar Days
Apr 8, 2015 Nov 18, 2015 40% Pipelaying is ongoing. Pipelaying is ongoing.
15.0 Prop. Ø100mm x 373.0 lm UPVC Expansion Project for Colorado Homes Dos (Brgy. Jubay, Liloan, Cebu) 373 lm x 100mm dia PVC Colorado Homes Dos Commonwealth Estate, Inc. Project Management Office PhP   1,640,244.69 45
Calendar Days
Jul 15, 2015 Aug 28, 2015 10% Pipelaying is ongoing. A Pre-Construction Meeting was conducted on July 15, 2015.
16.0 Prop.Water Distribution System for Villa Sebastiana Subdivision (Brgy. Tawason, Mandaue City, Cebu) 126 lm x 100mm dia PVC, 72 lm x 75mm dia PVC, 438 lm x 50mm dia PVC Villa Sebastiana Subdivision Aidfaz Development Corporation Project Management Office PhP   1,343,438.70 38
Working Days
Jul 29, 2015 Sep 14, 2015   Developer is on the process of procurement of materials and excavation permit. A Pre-Construction Meeting was conducted on July 29, 2015.
Section IV.      Ongoing Subdivision/Hotel/Condo Water System Projects     10                                                                  
Name of Project  Brief Description of the Project Subdivision/Hotel/Condo Name Developer / Owner MCWD Supervising Unit Project Amount Project Duration Date Started Target Completion Date Accomplish-          ment                             To Date Remarks
2. Flowmeter Assembly and Vault                  
1.0 Prop. Ø100mm Flowmeter Enclosed in Reinforced Concrete Vault for Alegria Palms Subdivision 2 (Brgy. Gabi, Cordova, Cebu) dia.100mm flowmeter, construction of reinforced concrete vault & interconnection Alegria Palms Subdivision 2 Commonwealth Estate, Inc. Project Management Office PhP   1,216,026.49 50 CD May 29, 2013 Jul 17, 2013   No activity conducted during the month. No activity conducted during the month.
2.0 Prop. Ø100mm Flow Meter for Marco Polo Residences (Veterans Drive, Nivel Hills, Apas, Cebu City) dia. 100mm large meter assembly & interconnection Marco Polo Residences Federal Land, Inc. Project Management Office PhP      535,054.44 14 WD Mar 10, 2014 Mar 28, 2014   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
3.0 Prop. Ø100mm Surface Mounted Bulkmeter for One Pavilion Place, (Banawa, Guadalupe, Cebu City) dia. 100mm large meter assembly & interconnection One Pavilion Place Goldpeach Properties Corp. Project Management Office PhP      892,244.28 39 CD May 5, 2014     Materials are availlable already. However, DPWH had denied Developer's request for excavation permit. Developer is processing on their request to MCWD that their existing Ø 25mm pipeline be upgraded to Ø 50mm. Materials are availlable already. However, DPWH had denied their request for excavation permit. Developer is processing on their request to MCWD that their existing Ø 25mm pipeline be upgraded to Ø 50mm.
4.0 Prop. Ø75mm Surface Flow Meter for Eagle's Nest (Canduman, Mandaue City, Cebu) dia.75mm large meter, large meter assembly & interconnection Eagle's Nest Primary Homes, Incorporated Project Management Office PhP      363,680.52 15 Working Days Aug 18, 2014 Sep 1, 2014   Developer is on the process of procurement of materials and permit. Developer may have a problem  with the excavation permit from the DPWH. Developer is on the process of procurement of materials and permit.
5.0 Prop. Ø150mm Surface Flow Meter for Astana Subdivision (Calawisan, Lapulapu City) dia. 150mm large meter, large meter assembly,  10 l.m. of Ø 150mm water distribution line & interconnection Astana Subdivision Johndorf Ventures Corporation Project Management Office PhP      564,233.88 20 Working Days Sep 3, 2014 Sep 26, 2014   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
6.0 Prop. Ø150mm  Bulk Meter Connection for Sunrise Place Subdivision (Sitio Malinao Brgy. Agus, Lapulapu City) dia. 150mm large meter and assembly, 10 l.m. of Ø 150mm PVC water distribution line Sunrise Place Subdivision Filinvest Land, Inc. Project Management Office PhP      573,409.74 25 Working Days Mar 18, 2015 Apr 15, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
7.0 Prop. Ø100mm  Surface FlowMeter for Almiya Subdivision (Brgy. Canduman, Mandaue City, Cebu) dia. 100mm large meter and assembly, 7 l.m. of Ø 100mm PVC water distribution line Almiya Subdivision Aboitizland, Inc. Project Management Office PhP      378,540.42 9
Working Days
Mar 26, 2015 Apr 5, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
8.0 Prop. Ø100mm  Surface FlowMeter for Mivesa Garden Residences (Salinas Drive Extension, Brgy. Lahug, Cebu City) dia. 100mm large meter and assembly, 6 l.m. of Ø 100mm PVC water distribution line Mivesa Garden Residences Cebu Landmasters, Inc. Project Management Office PhP      793,185.53 15
Working Days
Apr 6, 2015 Apr 24, 2015   Materials are already available. Developer has already acquired the permit. Developer is on the process of procurement of materials and permit. Hopefully, the Developer can acquire the permit by next month.
9.0 Prop. Ø75mm  Surface FlowMeter for Corinthian Residences (Andres Abellana St., Guadalupe, Cebu City) dia. 75mm large meter and assembly, 12 l.m. of Ø 75mm PVC water distribution line Corinthian Residences Landtraders World Properties Corp. Project Management Office PhP      532,247.12 9
Working Days
May 6, 2015 May 16, 2015   Developer is on the process of procurement of materials. Developer is on the process of procurement of materials.
10.0 Prop. Ø75mm  Surface FlowMeter for Park Point Residences (Ayala Business Park, Cebu City) dia. 75mm large meter and assembly, 6 l.m. of Ø 150mm PVC water distribution line Park Point Residences Ayala Land, Inc. Project Management Office PhP      545,657.97 8
Working Days
Jun 3, 2015 Jun 21, 2015   Developer is on the process of procurement of materials. A Pre-Construction Meeting was conducted on June 3, 2015.
11.0 Prop. Ø150mm  Surface FlowMeter for Priveya Hills Subdivision (Talamban, Cebu City) dia. 150mm large meter and assembly, 18 l.m. of Ø 150mm PVC water distribution line Priveya Hills Subdivision Aboitizland, Inc. Project Management Office PhP      824,138.35 10
Working Days
Jun 30, 2015 Jul 18, 2015   Developer is on the process of procurement of materials. A Pre-Construction Meeting was conducted on June 30, 2015.
12.0 Prop. Ø150mm  Surface FlowMeter for Eastland Yati Village (Phase 1-3) (Yati, Liloan, Cebu) dia. 150mm large meter and assembly, 282 l.m. of Ø 150mm PVC water distribution line & interconnection Eastland Yati Village (Phase 1-3) Eastland Property Ventures, Inc. Project Management Office PhP   1,618,076.10 45
Calendar Days
Jul 14, 2015 Aug 27, 2015   Developer is on the process of procurement of materials. A Pre-Construction Meeting was conducted on July 14, 2015.
13.0 Prop. Ø100mm  Surface FlowMeter for Robinsons Galleria (Gen. Maxilom Ave., Tejero, Cebu City) dia. 100mm large meter and assembly & interconnection Robinsons Galleria Robinsons Land Corporation Project Management Office PhP      599,885.68 15
Calendar Days
Jul 30, 2015 Aug 13, 2015   Developer is on the process of procurement of materials. A Pre-Construction Meeting was conducted on July 30, 2015.
14.0 Prop. Ø100mm  Surface FlowMeter for Filinvest Cyberzone (Salinas Drive corner Geonson St., Lahug, Cebu City) dia. 100mm large meter and assembly & interconnection Filinvest Cyberzone Cyberzone Properties, Inc. Project Management Office PhP      430,929.12 20 Working Days Aug 4, 2015 Aug 31, 2015   A Pre-Construction Meeting was conducted on August 4, 2015. A Pre-Construction Meeting was conducted on July 30, 2015.
Section IV.      Ongoing Subdivision/Hotel/Condo Water System Projects    11