Name of Project  Contractor  Supply Cost Volume Contract Signing Day 1 of Delivery  Remarks
               
1.0 MCWD Bulk Water Supply Contract (Compostela-Liloan-Consolacion Injection Points) Cebu Manila Water Development Incorporated Php 24.59 / cu.m. Year 1                    : 18,000 m3/day 18 Dec 2013 *09 Dec 2014 CMWD has been delivering 18,000 cu.m./day at the 3 drop-off points (Compostela, Liloan and Consolacion) and at the Consolacion temporary main delivery point  since January 5, 2015. Under the Contract, CMWD will deliver 35,000 cu.m./day at the start of the second year. CMWD has been delivering 18,000 cu.m./day at the 3 drop-off points (Compostela, Liloan and Consolacion) and at the Consolacion temporary main delivery point  since January 5, 2015. Under the Contract, CMWD will deliver 35,000 cu.m./day at the start of the second year which will be on January 2016.
      Year 2 to Year 20 : 35,000 m3/day   +09 Dec 2015
            * - Day 1 of the 1st year of delivery per MCWD letter to CMWD dated December 5, 2014 After it failed the replacement of the temporary flowmeters, construction of flowmeter vaults, and replacement of the temporary pipes within the agreed period, CMWD had asked for an extension on or before the day 1 of the Year 2 of delivery. During the July 15, 2015 meeting of the EXECOM and PMO with CMWD, the EXECOM had granted CMWD's request but until October 2015 only. CMWD had failed to meet its commitment, as part of the agreed conditions set by MCWD for allowing CMWD to start the delivery of water, to replace the temporary flowmeters wit the approved ones and construct the flowmeter vaults by end of January and February, respectively. Construction of the flowmeter vaults has yet to start while the approved flowmeters are yet to be delivered by the supplier. 
            + - Day 1 of the 2nd year of delivery The installation of CMWD's Ø700mm transmission line going to the Casili Reservoirs has already started and ongoing.   In lieu of the required 5,000m3 capacity tank (start of the 2nd year of delivery), CMWD had proposed to construct 4 tanks with combined storage capacity of 5,000m3 and with the same hydraulic grade as the existing Casili Reservoirs. MCWD in concept had approved the proposal and required CMWD to submit the piping details and the detailed design of the tanks. 
                   
             Section II.  Ongoing Supply and Installation of Goods       5