Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. DI Rehabilitation Project
at Pajac, Lapulapu City |
Rex E. Morales Construction |
PhP |
7,093,788.30 |
|
7,093,788.30 |
12 Aug 2015 |
23 Jan 2016 |
- |
0.00% |
0.00% |
0.00% |
A
Pre-Construction Meeting with PMO and the Contractor was conducted on August
18, 2015. |
|
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
48.56% |
26.24% |
-22.32% |
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs.
Contractor has already hydrotested more than 1000 linear meters of pipes.
The same has passed hydrotesting. |
|
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
32.72% |
0.00% |
-32.72% |
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs. |
|
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
14 Apr 2015 |
07 Feb 2016 |
|
22.18% |
0.00% |
-22.18% |
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs. |
|
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
24.29% |
0.00% |
-24.29% |
The pipes from India have
already arrived at the Port of Cebu on August 12, 2015. The Contractor is
coordinating with its supplier for the release of the pipes from the Bureau
of Customs (BOC). Ending August, the pipes were still not released from the
BOC. Contractor is still processing the procurement of excavation permits
from concerned LGUs. |
|
PMO had sent a letter to the
Contractor reminding the latter of the status of the project and instructing
them (Contractor) to expedite the purchase of the pipes. PMO had also
follow-up on the Contractor's acquisition of excavation permit from the
concerned LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
100.00% |
0.00% |
-100.00% |
Contractor is still securing
the remaining materials for the project as PMO is strictly imposing that the
Contractor is not allowed to start unless all the materials have been
inspected and passed testing. PMO had sent a letter to the Contractor
reminding the latter of the status of the project and instructing them
(Contractor) to expedite the purchase of the pipes. PMO had also follow-up on
the Contractor's acquisition of excavation permit from the concerned LGU. |
|
Contractor is still securing
the remaining materials for the project as PMO is strictly imposing that the
Contractor is not allowed to start unless all the materials have been
inspected and passed testing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
29.60% |
-70.40% |
Contractor is still securing
the remaining materials for the project as PMO is strictly imposing that the
Contractor is not allowed to start unless all the materials have been
inspected and passed testing. PMO had sent a letter to the Contractor
reminding the latter of the status of the project and instructing them
(Contractor) to expedite the purchase of the pipes. PMO had also follow-up on
the Contractor's acquisition of excavation permit from the concerned LGU. |
|
Contractor has started
pipelaying works on July 31, 2015. Full implementation works on the project
is expected on August. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Construction of
Proposed Cub-1 Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
13 Mar 2015 |
100.00% |
88.90% |
-11.10% |
Leaks of the
installed DI collector pipeline has been found. Disinfection, interconnection
and commissioning is expected to be completed by September. Field testing of
the submersible pump was done. |
|
The chlorination
equipment (booster pump, suction/discharge pipings, chlorine gas tank, etc.)
have been installed. Work to locate the leak/s of the installed DI collector
pipeline is ongoing. The Visayan Electric Company (VECO) has energized the
power connection for CUB-1 on July 26, 2015. Following this, the pump field
testing is scheduled by the first week of August. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liquidated
damages reckoned from March 14, 2015 will be imposed upon the Contractor for
its failure to complete the project within the approved time. |
|
Liquidated damages reckoned
from March 14, 2015 will be imposed upon the Contractor for its failure to
complete the project within the approved time. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
The MCWD BOD had already
approved PMO's recommendation to terminate the project. The Legal Department
is handling the processing of the termination. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
31 Dec 2014 |
100.00% |
70.40% |
-29.60% |
The pump and the motor has been installed. Field testing of
the pump and motor is expected to be conducted by September. |
|
Mr. Petrious P. Dakay represented DCDC during the July 15,
2015 meeting attended by the EXECOM to discuss DCDC's unsatisfactory project
performance. During the meeting, Mr. Dakay owned up the delay and admitted
that the company had problems on the procurement of materials. On the same
meeting, Mr. Dakay asked that DCDC be allowed to continue its work and
committed to finish the project by August 31, 2015. The EXECOM has granted
the request subject to the imposition of liquidated damages. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Mactan Water
Supply Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
A meeting was conducted on July
15, 2015. The Contractor was instructed to write to MCWD a formal request for the deletion of the
areas under DPWH and to ask for approval of Variation Order No. 2 so that the
Contractor could implement the areas under the LGU that already had a permit. |
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100.00% |
99.66% |
-0.34% |
The Contractor
has wrote to PMO formally informing the latter of the former's commitment to
complete the project in three (3) months starting on August 1, 2015 to
November 2015. |
|
The Contractor has wrote to PMO
formally informing the latter of the former's commitment to complete the
project in three (3) months starting on August 1, 2015 to November 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|