Name of
Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule and
Accomplishment |
Remarks |
|
|
Previous Month's
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman Builders and Contractors |
PhP |
16,744,730.61 |
|
16,744,730.61 |
28 Apr 2010 |
06 Feb 2011 |
31 Jul 2013 |
100% |
99.66% |
-0.34% |
The materials
are already tested and passed. PMO have reminded the Contractor to start
works on the project immediately. |
|
The additional fittings for the
project have already arrived by the last week of March 2015. The Contractor
is expected to make the request for testing of these materials by the early
week of April 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
PhP |
41,920,833.99 |
05 Jan 2011 |
31 Oct 2011 |
|
100.00% |
65.88% |
-34.12% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Proposed Ø300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
17,900,658.75 |
28 Jan 2013 |
26 Jul 2013 |
20 Nov 2013 |
100.00% |
45.50% |
-54.50% |
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
The Cebu City component of the
project had been completed while the Mandaue City component, which is under
the DPWH jurisdiction, has yet to be issued an Excavation Permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The BOD had already granted the
Contractor's request and PMO's recommendation to delete the remaining
uninstalled portion of the project. The materials that were intended for the
remaining portion that is already purchased by the Contractor will not be turned-over
to MCWD. |
|
The BOD has already granted the
Contractor's request and PMO's recommendation to delete the remaining
uninstalled portion of the project. The materials that were intended for the
remaining portion that is already purchased by the Contractor will not be turned-over
to MCWD. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO will make the computation
for the final variation order to be used as basis for the final billing of
the project. |
|
PMO will make the computation
for the final closing of the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
The -54.50% project slippage
corresponds to the uninstalled Mandaue City work component. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana
Construction |
Php |
8,368,625.90 |
|
8,368,625.90 |
07 Feb 2013 |
04 Sep 2013 |
- |
100.00% |
0.00% |
-100.00% |
The
termination of this project is being handled by the Legal Department. |
|
The termination of this project
is being handled by the Legal Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Mactan Water Supply
Improvement Program - Package 3 Cluster B
G.Y. Dela Cerna, P. Rodriguez, B. Benedicto, Carajay, & Dad Cleland
Avenue |
Dakay
Construction and Development Corporation |
Php |
52,687,315.00 |
|
52,687,315.00 |
21 Jun 2013 |
17 Mar 2014 |
- |
100.00% |
30.69% |
-69.31% |
The Contractor had sent a
letter to MCWD to follow-up the latter on the formal instruction or directive
on whether or not the Contractor could proceed works on the portions along
Carajay Road and Dad Cleland Avenue in which there is still a pending variation
order. The Contractor pointed out that the total variation orders that will
be incurred is still less than 10% of the project's cost even if the
variation order for the said portions will be appproved. Contractor also
added that these portions are already granted excvation permits from the City
of Lapulapu. |
|
The Contractor had sent a
letter to MCWD to follow-up the latter on the formal instruction or directive
on whether or not the Contractor could proceed works on the portions along
Carajay Road and Dad Cleland Avenue in which there is still a pending variation
order. The Contractor pointed out that the total variation orders that will
be incurred is still less than 10% of the project's cost even if the
variation order for the said portions will be appproved. Contractor also
added that these portions are already granted excvation permits from the City
of Lapulapu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM for revision |
MCWD is still awaiting the
Contractor's official reply on the discussion between MCWD Director Eugene
Elizalde, AGM Jose Eugenio B. Singson, Jr., PMO and DCDC's Petrious P. Dakay
on February 20, 2015 related to variation order. |
|
MCWD has replied to Contractor
reminding the latter's official reply on the discussion last month related to
the variation order. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
For the 3 work areas under the
jurisdiction of DPWH, MCWD continues to coordinate with DPWH 6th Engineering
District and Region 7 offices for the issuance of excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
The project PERT/CPM will be
revised once the variation orders for Carajay Road and Dad Cleland Avenue
will be approved or if MCWD BOD will allow the Contractor to proceed works. |
|
|
|
6.0 |
Proposed Expansion/Lateral
Project for Bacayan, Pit-os |
New Culion
Builders Co. |
Php |
22,019,495.65 |
|
22,019,495.65 |
20 Nov 2013 |
17 Jun 2014 |
- |
100.00% |
68.31% |
-31.69% |
The partial
suspension of works for the project that was issued on December 15, 2014 was
lifted by PMO on March 3, 2015. The Ø 300mm
and Ø 150mm pipeline had already been installed and is awaiting for
the hydrotesting. Installation of Ø 100mm pipeline is ongoing. |
|
The partial suspension of works
for the project that was issued on December 15, 2014 was lifted by PMO on
March 3, 2015. The Ø 300mm pipeline had already been installed and is
awaiting for the hydrotesting. Installation of Ø 100mm pipeline is ongoing.
The negative slippage may be greatly attributed to the delay in the
issuance of the excavation permit. The PERT/CPM of the project as well as the
Time Extension is being processed. |
|
|
|
7.0 |
Construction of Proposed Man-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Dakay
Construction and Development Corporation |
Php |
5,739,002.00 |
|
5,739,002.00 |
06 Feb 2014 |
05 Jul 2014 |
- |
100.00% |
25.70% |
-74.30% |
There has been no progress in the implementation of the
project for sometime. The mechanical and electrical equipment/materials that
comprised bulk of the 74.30% uncompleted work have not been
procured/delivered until now. |
|
There has been no progress in the implementation of the
project for sometime. The mechanical and electrical equipment/materials that
comprised bulk of the 74.30% uncompleted work have not been
procured/delivered until now. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PERT/CPM
for revision
|
As relayed by the AGM for Technical Services, the BOD had
approved the Revised PERT/CPM prepared by PMO that reflects the delay in the
issuance of both the Building Permit and Excavation Permit. Per Revised
PERT/CPM, the new project completion date will be December 31, 2014. PMO
awaits the Board Resolution before it will prepare the corresponding request
for time extension. |
|
|
As relayed by the AGM for Technical Services, the BOD had
approved the Revised PERT/CPM prepared by PMO that reflects the delay in the
issuance of both the Building Permit and Excavation Permit. Per Revised
PERT/CPM, the new project completion date will be December 31, 2014. PMO
awaits the Board Resolution before it will prepare the corresponding request
for time extension. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 2 |
|
|
|
Name of Project |
Contractor |
Contract
Amount |
Notice to Proceed |
Completion
Date |
Schedule
and Accomplishment |
Remarks |
|
|
|
Target To Date |
Actual To Date |
Variance
To Date |
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed DI Lateral Pipeline
for Hidden View and Villa Leyson Subdivisions (Brgy. Bacayan, Cebu City) |
New Culion
Builders Co. |
Php |
7,898,571.77 |
|
7,898,571.77 |
02 Jul 2014 |
27 Jan 2015 |
- |
100.00% |
0.00% |
-100.00% |
MCWD had written a letter to
the Contractor's General Manager Ma'am Iting to submit proof until May 15,
2015 that the latter had already purchased the materials. |
|
PMO had sent a letter to NCBC
General Manager Ma'am Iting asking about the latter's intention to complete
the project. The latter had informed MCWD that they (Contractor) are
processing their letter of credit which will be used to finance the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø150mm x 515.0 LM DI
Lateral Pipeline at Sitio Pundok, Brgy. Pit-os |
New Culion
Builders Co. |
Php |
4,260,041.01 |
|
4,260,041.01 |
02 Jul 2014 |
28 Nov 2014 |
- |
100.00% |
0.00% |
-100.00% |
MCWD had written a letter to
the Contractor's General Manager Ma'am Iting to submit proof until May 15,
2015 that the latter had already purchased the materials. |
|
PMO had sent a letter to NCBC
General Manager Ma'am Iting asking about the latter's intention to complete
the project. The latter had informed MCWD that they (Contractor) are
processing their letter of credit which will be used to finance the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Construction of Proposed Cub-1
Pumping Station for the MCWD In-House Water Sourcing Program |
Geo Transport
& Construction, Inc. |
Php |
9,001,428.00 |
|
9,001,428.00 |
05 Sep 2014 |
01 Feb 2015 |
- |
100.00% |
28.11% |
-71.89% |
Pipelaying works is ongoing
with at least 30% in accomplishment.
Another test conducted by MSSD of the pump intended for the CUB-1 showed
that the pump had passed the efficiency requirement. |
|
The DI pipes and fittings had
been delivered and passed the QC inspection, however, the tapping saddles and
PE pipes (for stub-outs) have yet to be delivered. It is PMO's policy not to
allow the start of pipelaying works unless all the needed materials are
available and had passed the QC inspection. The pipelaying woks therefore,
can not start until the lacking materials have been delivered and
tested.
The pump intended for CUB-1 had been delivered. Result of the lab test
conducted by the MSSD showed it failed
to meet the effeciency requirement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The BOD had approved the
suspension of Contract Time for 40 days retroactive on the day 1 (NTP) of the
Contract. The suspended period is equivalent to the number of days from the
NTP until the Contractor secured the Excavation Permit. PMO had already issued the suspension of time to the
Contractor. |
|
The uninstalled mechanical,
electrical, and pipeline components of the project have comprised the 75.75%
uncompleted work. The BOD had approved the suspension of Contract Time for 40
days retroactive on the day 1 (NTP) of the Contract. The suspended period is
equivalent to the number of days from the NTP until the Contractor secured
the Excavation Permit. Once the Board Resolution is out, PMO will issue the
Suspension Order. With this suspension, the new contract completion date will
be March 13, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Ø200mm x 454.0LM DI
Rehabilitation Project at Pulpogan, Consolacion |
FDRCon Co.,
Inc. |
Php |
5,250,000.98 |
|
5,250,000.98 |
01 Dec 2014 |
29 Apr 2015 |
|
100.00% |
0.00% |
-100.00% |
The in-plant inspection for the
pipes and fittings were already conducted on April 22-25, 2015. During a
coordination meeting, PMO reminded the Contractor about the latter's
slippage. And that PMO will be recommending MCWD BOD for the termination of
the project. |
|
PMO had already advised the
Contractor of their (Contractor) big slippage which could be a ground for the
termination of the project. The Contractor responded by informing PMO that
they (Contractor) are still willing to complete the project despite the big
slippage. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.0 |
Proposed Water
Distribution Rehabilitation at Alaska,
Mambaling |
FDRCon Co.,
Inc. |
Php |
14,802,865.00 |
|
14,802,865.00 |
16 Feb 2015 |
29 Aug 2015 |
|
13.49% |
0.00% |
-13.49% |
Contractor is on the process of
procurement of materials. |
|
A Pre-Construction meeting was
conducted on March 6, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 1 |
PMG Ventures |
Php |
53,298,110.23 |
|
53,298,110.23 |
14 Apr 2015 |
07 Feb 2016 |
|
0.00% |
0.00% |
0.00% |
A Pre-Construction meeting was
conducted on April 29, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 2 |
JFAP
Construction |
Php |
32,133,490.95 |
|
32,133,490.95 |
17 Dec 2014 |
07 Feb 2016 |
|
0.00% |
0.00% |
0.00% |
A Pre-Construction meeting was
conducted on April 29, 2015. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 3 |
Geo-Transport
& Construction, Inc. |
Php |
63,385,179.00 |
|
63,385,179.00 |
15 Apr 2015 |
09 Jan 2016 |
|
0.00% |
0.00% |
0.00% |
A Pre-Construction meeting is
scheduled next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16.0 |
Proposed Pipelines Expansion
under Hydraulic Area 1 Package 4 |
Geo-Transport
& Construction, Inc. |
Php |
63,092,768.00 |
|
63,092,768.00 |
15 Apr 2015 |
25 Nov 2015 |
|
0.00% |
0.00% |
0.00% |
A Pre-Construction meeting is
scheduled next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section
I. Ongoing
Infrastructure Projects 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|