Name of Project  Project Beneficiary Implementing Unit Approved Budget Duration Date Started Completion Date Schedule and Accomplishment Remarks
Target            To Date Actual       To Date Variance To Date
Original Revised Original  Revised Original Revised
                                 
1. Pipeline Expansion                              
                                 
                                 
1.0 Lagtang Distribution Line[1] Sitio Tigib-Burlas, Lagtang,  Residents Construction Department PhP    2,660,000.00 PhP 68 c.d.             Implementation is being deferred pending the completion of the road widening project of DPWH. We are allowed to install our pipes in any section of the road but this is only temporary because new pipeline shall have to be installed on the utility strip provided by DPWH.  
                                  
2.0 Casili Estate Distribution Line Casili Estate Residents Construction Department PhP    1,391,000.00 PhP 21 c.d.             The chlorinator pump has already passed the test that was conducted by MCWD laboratory. Awaiting for the result of the PRF that was submitted to the HRD. Project is supposed to start on August 27, 2013. 
                                 
3.0 St. Anthony Village, Hi-way 77, 75mm dia. x 234 LM  St. Anthony Village Construction Department PhP    1,100,000.00 PhP   23 c.d.               72% of the materials are already served. The rest are being clustered.
4.0 Proposed 75mm dia. uPVC Water Distribution Mains at Campo2, Brgy. Jaclupan, Talisay City Campo 2, Brgy. Jaclupan Residents Construction Department PhP    4,820,000.00 PhP   120 c.d.             The excavation permit was held in abeyance by DPWH. DPWH is providing a new form for the application of the excavation permit.
                                 
2. Pipeline Rehabilitation                              
                                 
1.0 Proposed Ø100mm X 192 lm DI Distribution Rehabilitation   Project along I Tabura St., Brgy. Pardo, Cebu City Construction Department PhP    1,766,946.23 PhP   43 c.d.               37% of the materials are already served. The rest are being clustered.
2.0 Proposed Ø200mm X 301 lm DI Distribution Rehabilitation Project  along Datag, Maribago, Lapulapu City Datag, Maribago, Lapulapu City Construction Department PhP    4,608,000.00 PhP   45 c.d.               42% of the materials are already served. The rest are being clustered.
3.0 F. Llamas, Labangon Realignment of 200mm and 100mm uPVC                             Awaiting for the detailed drawings from ED of the cross-section of the pavement that will be affected by the pipe installation. Without the drawings, the excavation permit will not be granted by the Cebu City Engineer's Office.
4.0 Proposed Ø200mm X 440 lm DI Distribution Rehabilitation   Project at Brgy. Jubay, Liloan, Cebu Brgy. Jubay Residents Construction Department PhP    4,188,596.15 PhP   58 c.d.               PR for the requried materials was processed on April 8, 2013 with PR no. 23548-001 to 056; materials in various stages of procurement.
5.0 Proposed Decommissioning of Exisitng Ø100mm x153lm uPVC Pipeline and Transfer Tapping of Service Connections at Sitio Looc, Liloan, Cebu Sitio Looc, Liloan Residents Construction Department PhP       238,452.25 PhP   9 c.d.               Awaiting for the result of the PRF which was already submitted to the HRD.
3. Pumping Station                                 
                                 
1.0 Sta. Cruz Well (Liloan) Brgy. Sta Cruz Residents Bayanihan - C/O PDD PhP    5,590,000.00 PhP 87 c.d.         97% The materials are already available. Awaiting for the personnel who will work for the perimeter fence. There are currently no available personnel to handle the project.
                   
                                 
  2.0 Well 35 Berjame Subdivision and Barangay Talamban Residents Bayanihan - C/O PDD PhP           4 Feb  2012 30Apr2012         Awaiting for the curing period of the base preparation for the iron manganese filter tank.
  3.0 Mac 6, 7 & 8 Pumping Stations Cluster C Brgy. Pajac &  Bankal Residents in Lapulapu City Construction Department/ MSSD PhP    8,709,862.10 PhP   113 c.d.               Already clustered.
  Related Project:                        
  1.0 Mac 6 & 7 Connecting Pipeline                       See Sub-Item No. 3 Item No. 2 of Section V Projects Proposed for Implementation
  2.0 Mac 8 Connecting Pipeline                             See Sub-Item No. 4 Item No. 2 of Section V Projects Proposed for Implementation
  4.0 Mac 10 & 11 Pumping Stations Brgy. Pajac, Bankal & Agus Residents in Lapulapu City Construction Department/ MSSD PhP    6,508,756.40 PhP   36 c.d.               Already clustered.
  Related Project:                        
  1.0 Mac 10 & 11 Connecting Pipeline                             See Sub-Item No. 5 Item No. 2 of Section V Projects Proposed for Implementation
  5.0 MAC 12 Pumping Station Portville Subd.,      Brgy. Buaya, Lapulapu City Construction Department/ MSSD PhP    3,000,000.00 PhP   45 c.d.               Already clustered.
5. Infrastructure                                
  1.0 Proposed Roofing of MCWD Talamban Laboratory Terrace MCWD Compound, Nasipit, Brgy. Talamban, Cebu City Construction Department PhP         88,058.00 PhP   12 c.d.               The project will be handled by GSD.
        Section III.      Ongoing By-Administration Projects                                                                                     9

[1]
Kim:
previously: Jaclupan Distribution Line