Name of Contract |
Joint Venture Partner |
Minimum Volume |
Supply Cost |
Date of Contract Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
On the
required Data Monitoring Software (calculate/tabulate data, show graphs,
indicate under- or over-supply), AWC has the option to use either the
PWRI-developed Data Monitoring Software or the Premier Portal Web. AWC
intimated it will use the PWRI-developed software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the succesful installation and
operation of the software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On the Data Monitoring
Software, PWRI had previously provided Globe Telecom with the Data Logger
Diagram for the latter to study/analyze in order to address the reported data
transmission problem. Lately, the Globe Telecom had provided PWRI with a new
SIM card. A reconfiguration of the new SIM with the Data
Logger is scheduled early next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply Program - Talamban Injection Point |
Pilipinas Water Resources, Inc. |
3,592 |
m3/day |
PhP |
14.21 |
/m3 |
19 Nov 2010 |
19 May 2011 |
5 Dec 2011 |
The Talamban
Injection Point has been supplying water to MCWD since December 6, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On the Data Monitoring
Software, PWRI had previously provided Globe Telecom with the Data Logger
Diagram for the latter to study/analyze in order to address the reported data
transmission problem. Lately, the Globe Telecom had provided PWRI with a new
SIM card. A reconfiguration of the new SIM with the Data
Logger is scheduled early next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation and operation
of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
MRII had
informed PMO it will use the PWRI-developed Data Monitoring Software. MRII is
awaiting the successful trial run of the software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of
this Joint Venture (i.e. installation of production and supply facilities)
will be declared fully completed only after the succesful installation and
operation of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section II. On-going
Joint Venture Projects |
5 |
|
|
|
|
|
|
Name
of Contract |
Joint Venture Partner |
Minimum Volume |
Supply Cost |
Date of Contract Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
Time Extension on process |
This JV
Contract has 3 injection points strategically spread over Brgy. Guadalupe:
Guadalajara, Kabajar, and Quijada. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Guadalajara
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Since
September 2012, the Guadalajara injection point has been supplying an average of 2,400m3 of water daily to
MCWD. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kabajar
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Since the resumption of its
operation in April 3, 2013, the Kabajar injection point has been supplying an
average of 600m3 of water daily to MCWD. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Quijada
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
installation of collector main from AWC's Well G-4 going to the injection
point is now almost complete; for Well G-5, the installation of collector
main has yet to commence. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO is still
awaiting for the signed Amendment to Contract that covers the new location of
the meter vault and injection point and the revised Day 1 of delivery. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC is now
processing the Building Permit for the meter vault. Construction of the vault
will start once the permit has been issued. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Bulk Water Supply Program - Pit-os Injection Point |
Abejo Waters Corporation |
4,800 |
m3/day |
PhP |
15.68 |
/m3 |
19 June 2013 |
18 June 2014 |
|
This Joint
Venture between MCWD and AWC was signed on June 19, 2013. The signing date
also served as the NTP. Under the joint venture, AWC will deliver a minimum
volume of 4,800 m3
of water daily to MCWD . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC is awaiting from the Municipality of Consolacion the
approved Amendment to their existing MOA that will allow the former to extract additional volume of water from within the
municipality. AWC reported that the proposed amendment had already passed
thru the municipality's Committee on Laws, Committee of Commerce, Trade and
Industry, and Water Committee, and was deliberated and approved by the
Municipal Council last week of September 2013. The proposed amendment is now
at the Mayor's Office for signature/approval. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Works (e.g.
well drilling, pipelaying, etc.) will start only after AWC secures the above
Amendment and the necessary permits. AWC though had procured already the HDPE
pipes intended for its raw water collector/transmission mains. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section II. Ongoing Joint
Venture Projects
|
6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|