1.  INFRASTRUCTURE PROJECTS  
Name of Project  Location Final Project Cost Date Completed Remarks
    1.0 Prop. Tennis Court Resurfacing MCWD Compound, Talamban, Cebu City PhP          124,000.00 February 28, 2013 Certification of Project Completion was already issued to the Contractor
    2.0 Prop. D.I. Rehabilitation Project for DMA-25A, W. Cabalse and Holyname Sts. Mabolo, Cebu City PhP       2,449,834.22  May 6, 2013 Awaiting submission by Contractor of the Certificate of Acceptance of Road Restoration from Cebu City before PMO will issue the Certificate of project Completion.
    3.0 Prop. Ø 300 mm D.I Distribution Line along Pit-os, Talamban, Cebu City Talamban, Cebu City PhP     54,080,280.37 06 Nov 2013 Awaiting submission by contractor of the as-built drawings.
    4.0 Prop. Ø150mm & Ø100mm D.I Distribution Line along Umapad-Opao, Mandaue City Umapad-Opao, Mandaue City PhP     13,515,695.33 10 Sep 2013 Awaiting submission by contractor of the as-built drawings.
2. SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS  
2. 1 WATER SYSTEM
Name of Project  Location Final Project Cost Date Completed Remarks
    1.0 Prop. Water Distribution Main for CBP Resort Development Project Negros St., Cebu Business Park, Cebu City PhP          544,278.79 January 8, 2013 Already complied  with MCWD Standard Requisites  
    2.0 Prop. Water Distribution System for Alberlyn South Subdivision Cansojong, Talisay City, Cebu PhP       1,122,690.12 April 16, 2013 Already complied  with MCWD Standard Requisites  
2. 2 FLOWMETER ASSEMBLY AND VAULT              
  Name of Project  Location Final Project Cost Date Completed Remarks
    1.0 Prop. Ø150mm Flowmeter and Construction of Reinforced Concrete Vault for Amisa Private Residences Punta Engaño, Lapu-lapu City Php       1,346,387.53 March 8, 2013 Already complied  with MCWD Standard Requisites
    2.0 Prop. Ø75mm Surface Flowmeter for Baseline Condominium J. Osmeña Street, Capitol, Cebu City Php          363,410.90 November 29, 2013 Awaiting for the as-built plans.
               Section IV.      Projects Completed in 2013 11 11