Name of Project |
Brief Description of the Project |
Subdivision/Hotel/Condo Name |
Developer / Owner |
MCWD Supervising Unit |
Project Amount |
Project Duration |
Date Started |
Target Completion Date |
Accomplish-
ment
To Date |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Water System |
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Water Distribution System
for EastGate Subdivision (Matumbo, Pusok, Lapulapu) |
49.54 LM x
75mm dia |
EastGate Subdivision |
Urban Enclaves Inc. |
Project Management Office |
PhP |
514,061.34 |
11 CD |
15 Jul 2011 |
26 Jul 2011 |
0.00% |
The contractor had submitted a
proposal and said proposal was approved for implementation. No physical
activity was conducted. |
|
A meeting with the
developer was conducted to discuss matters regarding the incorrect location
of the pipes that were laid by the developer through its contractor. The
pipes were laid within the property line of the residential lots. Developer
is ordered |
|
2.0 |
Prop. Water Distribution System
for Modena Mactan Subdivision (Basak, Lapu-lapu City) |
166 LM x 100mm
dia., 1016 LM x 75mm dia. |
Modena Mactan Subdivision |
Juanito King & Sons, Inc. |
Project Management Office |
PhP |
4,011,373.95 |
95 CD |
25 Apr 2011 |
28 Jul 2011 |
97.00% |
No activity
conducted during the month. |
|
|
3.0 |
Prop. PVC Water Distribution
System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu) |
484 LM x 75mm dia., 781 LM x 100mm dia., 167
LM x 150mm dia. |
Amara Subdivision |
Cebu Holdings, Inc. |
Project Management Office |
PhP |
|
92 CD |
15 May 2012 |
14 Aug 2012 |
96.00% |
Contractor is on the process of
purchasing the handhole cover and AV/AR head. |
|
|
4.0 |
Prop. Rerouting
of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu) |
1,650 LM x 150mm dia. |
Amara
Subdivision |
Cebu Holdings, Inc. |
Project
Management Office |
PhP |
|
92 CD |
15 May 2012 |
14 Aug 2012 |
98.00% |
Remaining work
is only disinfection for portion of the subdivision at phase 3b. |
|
|
5.0 |
Prop. Water Distribution System
for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City)[1] |
6,920 LM x
75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia.,
151 LM x 250mm dia. |
Pueblo De Oro Communities
(Horizon, La Aldea Del Mar, and Parkplace) |
Pueblo De Oro Development Corp. |
Project
Management Office |
PhP |
22,980,152.33 |
|
|
|
14.00% |
Pipelaying works is on-going. |
|
|
6.0 |
Prop. Water Distribution System
for Portville Subdivision (Aviation Road, Brgy. Buaya, Lapu-lapu City)[2] |
982 LM x 75mm
dia., 269 LM x 100mm dia., 17 LM x 150mm dia. |
Portville Subdivision |
Johndorf Venture Corp. |
Project
Management Office |
PhP |
3,430,246.86 |
94 CD |
3-Sep-12 |
6-Dec-12 |
80.00% |
Remaining works are
disinfection, installation of concrete pads and barricades for stub-outs,
interconnection to overhead water tank. |
|
|
7.0 |
Prop. Water
Distribution Lines for Northwoods Residences (H. Abellana St., Canduman,
Mandaue City, Cebu |
386
LM x 75mm dia. PVC water distribution line |
Northwoods
Residence |
Priland
Development Corp. |
Project
Management Office |
PhP |
1,250,000.00 |
|
14-Feb-13 |
|
|
|
|
|
8.0 |
Prop. Water
Distribution System for Summer Ville 3 Subdivision (Brgy. Buagsong, Cordova,
Cebu) |
362
LM x 75mm dia. PVC water distribution line |
Summer Ville 3
Subdivision |
ABQ & Sons
Realty and Development Corp. |
Project
Management Office |
PhP |
2,117,087.90 |
52 CD |
30-May-13 |
20-Jul-13 |
|
|
|
|
9.0 |
Prop. PVC Water
Distribution System for Kaiser Townhouse II |
510
LM x 100mm dia. PVC and 75mm dia. PVC water distribution line |
Kaiser
Townhouse II |
Kaiser Urban
Development Corp. |
Project
Management Office |
PhP |
1,687,773.35 |
|
24-Jun-13 |
|
|
Developer has
acquired permit for the excavation at the interconnection point. |
|
|
10.0 |
Prop. Water
Distribution Systems for Mactan Plains Subdivision |
114
LM x 100mm dia. PVC and 810 LM 75mm dia. PVC water distribution line |
Mactan Plains
Subdivision |
Pacific Land
Ventures and Property Development, Inc. |
Project
Management Office |
PhP |
1,617,764.80 |
|
25-Jun-13 |
|
|
|
|
|
11.0 |
Prop. Water
Distribution Systems for Capitol Residences |
153
LM x 75mm dia. PVC |
Capitol
Residences |
Urban Enclaves
Inc. |
Project
Management Office |
PhP |
678,670.75 |
|
12-Sep-13 |
|
60.00% |
Pipelaying is
in progress while awaiting for the delivery of other materials. |
|
|
12.0 |
Prop. Water
System Design for Goldmine Residences (Bangkal-Mahayahay-Soong, Lapulapu
City) |
236
LM x 150mm dia. PVC, 32 LM 100mm dia. PVC, 152 LM 75mm dia. PVC, 617 LM 50mm
dia. PVC |
Goldmine
Residences |
Heritage Supreme
Land Developer, Inc. |
Project
Management Office |
PhP |
3,215,481.65 |
|
14-Oct-13 |
|
|
Conducted
pre-construction meeting with developer. |
|
|
13.0 |
Prop. Water
Distribution Systems for City Homes - Mandaue (J.S. Alinsug St., Mandaue
City, Cebu) |
42
LM 75mm dia. PVC, 218 LM 50mm dia. PVC |
City Homes
Mandaue |
Grand Land, Inc. |
Project
Management Office |
PhP |
870,061.25 |
|
23-Oct-13 |
|
|
Conducted
pre-construction meeting with developer. |
|
|
14.0 |
Prop. Water
Distribution Systems for Anami Homes - Mactan (Sudtungan, Basak, Lapulapu
City) |
518
LM 75mm dia. PVC |
Anami Homes
Mactan |
Softouch
Property |
Project
Management Office |
PhP |
1,312,868.15 |
|
24-Oct-13 |
|
|
Conducted
pre-construction meeting with developer. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Ongoing Subdivision/Hotel/Condo Water System Projects 8 |
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Project |
Brief Description of the Project |
Subdivision/Hotel/Condo Name |
Developer / Owner |
MCWD Supervising Unit |
Project Amount |
Project Duration |
Date Started |
Target Completion Date |
Accomplish-
ment
To Date |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2. Flowmeter Assembly
and Vault |
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Ø150mm Large Meter
Assembly for Urban Homes Mandaue |
dia.150mm
large meter, large meter assembly & interconnection |
Urban
Homes |
Fog Horn, Inc. |
Project
Management Office |
PhP |
1,428,658.31 |
46 CD |
|
|
100.00% |
Awaiting for
the final project inspection and the as-built plan. |
|
|
2.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Meter Vault for 1016
Residences |
dia.75mm
flowmeter, flowmeter assembly & interconnection |
1016
Residences |
Ayala
Land, Inc. and Cebu Holdings, Inc. |
Project
Management Office |
PhP |
952,133.26 |
30 CD |
|
|
|
Conducted
material testing. |
|
|
3.0 |
Prop. Ø75mm
Surface Flowmeter Assembly for the Padgett Place |
dia.75mm
large meter, large meter assembly & interconnection |
Padgett
Place |
Cebu
Green Peaks Development, Inc. |
Project
Management Office |
PhP |
685,113.03 |
28 CD |
19-Mar-13 |
15-Apr-13 |
40% |
Developer
has already purchased the materials except the flowmeter. |
|
|
4.0 |
Prop. Ø75mm
Surface Mounted Flowmeter Assembly for Spianada Condominium (Cor. Rahman and
E. Benedicto Sts., Cebu City) |
dia.75mm
large meter, large meter assembly & interconnection |
Spianada
Condominium |
Land
Caster Estate Ventures, Inc. |
Project
Management Office |
PhP |
638,081.16 |
20 CD |
26-Mar-13 |
14-Apr-13 |
|
Procurement
stage. |
|
|
5.0 |
Prop. Ø100mm
Surface-Mounted Bulkmeter for Citylights Garden Phase 2 (Towers 3 & 4)
(Lahug, Cebu City) |
dia.100mm
Large Meter, Large Meter Assembly & Interconnection |
Citylights
Gardens Phase 2 |
Citylights
Garden Tower 3 & 4 Condominium Corporation |
Project
Management Office |
PhP |
774,000.00 |
31 CD |
24-Apr-13 |
24-May-13 |
|
Procurement
stage. |
|
|
6.0 |
Prop. Ø75mm
Surface-Mounted Bulkmeter for Citylights Garden Phase 1 (Towers 1 & 2)
(Lahug, Cebu City) |
dia.75mm
large meter, large meter assembly & interconnection |
Citylights
Gardens Phase 1 |
Citylights
Garden Condominium Corporation |
Project
Management Office |
PhP |
689,000.00 |
37 CD |
9-May-13 |
14-Jun-13 |
|
Procurement
stage. |
|
|
7.0 |
Prop. Ø100mm
Flowmeter Enclosed in Reinforced Concrete Vault for Alegria Palms Subdivision
2 (Brgy. Gabi, Cordova, Cebu) |
dia.100mm
flowmeter, construction of reinforced concrete vault & interconnection |
Alegria
Palms Subdivision 2 |
Commonwealth
Estate, Inc. |
Project
Management Office |
PhP |
1,216,026.49 |
50 CD |
29-May-13 |
17-Jul-13 |
|
No
activity conducted during the month. |
|
|
8.0 |
Prop. Ø75mm
Surface Flowmeter for Baseline Condominium (J. Osmeña Street, Capitol, Cebu
City) |
dia.100mm
flowmeter, construction of reinforced concrete vault & interconnection |
Baseline
Condominium |
Cebu
Landmasters, Inc. |
Project
Management Office |
PhP |
363,410.90 |
|
19-Jul-13 |
|
100% |
Completed
on November 29, 2013. Awaiting for the as-built plans. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section IV. Ongoing Subdivision/Hotel/Condo Water System Projects 9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|