REPORT SUMMARY AS OF MAY 2013 |
|
|
|
|
|
A. SECTION
II. ON-GOING INFRASTRUCTURE PROJECTS |
|
|
|
|
Name
of Project |
Contractor |
Contract Amount |
Notice to Proceed |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
LATEST UPDATE AS OF MAY 2013 |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman
Builders and Contractors |
PhP |
16,744,730.61 |
|
|
28 Apr 2010 |
06 Feb 2011 |
31 Jul 13 |
|
93.7% |
|
The
Contractor, Felman Builders, has already completed the replacement of the
defective HDPE pipes along M. Ceniza St., Mandaue City. |
|
Completed along M. Ceniza |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO suggested
to the Contractor to disinfect the completed lines so that they can partially
turn it over to MCWD. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
is currently working on the replacement of the defective pipes along Lola
Saling, Mandaue City. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
A Meeting was
conducted between MCWD, Felman Builders, Road Concreting Contractor and
Tingub Barangay Captain to thresh out any potential problems with regards to
the implementation of the replacement of defective HDPE pipes along Barangay
Tingub and Tabok areas. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO verbally
reminded the contractor, Felman Builders, about their terminal date which is
on July 31, 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
|
|
05 Jan 2011 |
01 Nov 2011 |
PERT/CPM to be revised |
- |
64.09% |
- |
PMO reminded
Ana Construction to complete the installation of the remaining section of the
528 l.m. Steel Pipelines along Pajac-Maribago Road, Lapu-lapu City to avoid
prolonging the inconvenience that this project has caused and to pave the way
for the concreting project of the LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of the PERT/CPM is under evaluation |
Lapu-lapu
Acting Asst. for the City Engineer’s Office issued an ultimatum to MCWD to
complete and finish the 528 l.m. Steel Pipelines along Pajac-Maribago Road
within 7 calendar days from receipt of their letter otherwise the granted
excavation permit will be revoked and the City will immediately undertake the
road restoration chargeable to the bank guarantee that was put up for this
project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO will
request for reconsideration on the ultimatum and will ask for an extension to
the 7 calendar day deadline. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Prop. Ř 300 mm D.I Distribution
Line along Pit-os, Talamban, Cebu City |
New Culion
Builders Company |
PhP |
54,099,956.35 |
|
|
15 Mar 2012 |
9 Dec 2012 |
30-Jun-13 |
|
85.28% |
|
MCWD thru PMO
has already approved the Contractors’ request for Time Extension No. 3. With
the approval, the new terminal date will be on June 30, 2013 |
|
On the last phase of the
project. Pipelaying already completed. |
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
The Project is
in the Final Stage. So it is expected that the Contractor will be able to
turn-over the entire project before the Terminal Date. |
|
Hopefully by third week of june
this will be completed |
|
|
|
|
Related Project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Pit-os Injection Point |
|
|
|
|
|
|
|
|
|
|
|
See Part E Section VI Subsection E.1.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. Ř150mm & Ř100mm D.I
Distribution Line along Umapad-Opao, Mandaue City |
New Culion
Builders Company |
PhP |
15,726,332.82 |
|
|
15 Mar 2012 |
9 Nov 2012 |
30-Mar-13 |
|
47.48% |
|
PMO is still
waiting from the Contractor to submit their supporting documents in relation
to their request for Time Extension due to the new requirement by the Mandaue
City Engineers’ Instruction to put 8” thick lean concrete before their final
Asphalt Restoration. |
|
TE 3 is on process. Corplan
will be adding an extra work. |
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
The Contractor
has started the hydrotesting activities on the 150mm dia D.I. pipes along
Plaridel Street, Mandaue City. |
|
Mandaue City advised MCWD to
instruct contractor to complete the restoration in 10 days ( as of June 2013) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Concrete
Protection on the 100mm dia D.I. pipes along Batiller St., Mandaue City has
already been completed. This protection is needed to secure our pipes from
any possible contamination since these pipes are submerged in water. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO reiterate
to the Contractor to fast track all their activities in order to be able to
complete the project as soon as possible. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Jaclupan Desilting |
WT
Construction |
PhP |
8,000,000.00 |
|
|
17 Jun 2012 |
17 Dec 2013 |
|
25.00% |
5.44% |
-19.56% |
Contractor has
problem with its manpower and equipment. It has only 3 dumptruck and 1
backhoe. Contractor has completed 5.44%. |
|
completed: 5.44%. Slippage:
-19.56%. It has now 3 dumptrucks already. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary
2 |
|
|
|
|
|
REPORT SUMMARY AS OF MAY 2013 |
|
|
|
|
|
A. SECTION
II. ON-GOING INFRASTRUCTURE PROJECTS |
|
|
|
|
Name
of Project |
Contractor |
Contract Amount |
Notice to Proceed |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Prop. D.I. Expansion Project at
Monterrazas de Cebu |
Dakay Construction and
Development Corporation |
Php |
18,288,888.00 |
|
|
01 Nov 2012 |
14 May 2013 |
19 Jul 2013 |
|
0.00% |
0.00% |
Minor physical activity as far
as accomplishment is concerned. The Contractor is doing cutting of asphalt
pavement in preparation for their pipelaying activities. |
|
Arrival of pipes from India.
Works done were mostly cutting of the pavement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
The D.I. Pipes
and Fittings have already arrived and the Contractor is on the process of
securing the needed documents for the release of their goods from the
customs. Inspections of their D.I. pipes and fittings are expected on the
early week of June. |
|
TE 1 is approved. It is about
the instruction from corplan deffering the procurement and the processing of
visa. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Proposed Ř250 mm D.I. Water
Distribution Line along Sitio Malinao, Agus-Marigondon, Lapulapu City |
Geo Transport &
Construction, Inc. |
Php |
7,488,159.00 |
|
|
28 Jan 2013 |
01 Jul 2013 |
|
51.65% |
0.00% |
-51.65% |
The D.I. pipes and fittings
intended for this project has already arrived. The Contractor is on the
process of securing the documents for the release of their goods from the
customs. Inspections of their D.I. pipes and fittings are expected on the
early week of June. |
|
contractor and city already
conducted site investigation for the processing of the permit. Pipes are
already in the stock yard. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
GTCI informed PMO that their
application for excavation permit submitted last February 14, 2013 was not
yet acted upon by the concerned agency. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Expected Extension of Time is
sought by the Contractor due to delay in granting the necessary excavation
permit which is beyond their control. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Ř300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
|
28 Jan 2013 |
26 Jul 2013 |
|
24.21% |
0.00% |
-24.21% |
The D.I. pipes and fittings
intended for this project has already arrived. The Contractor is on the
process of securing the documents for the release of their goods from the
customs. Inspections of their D.I. pipes and fittings are expected on the
early week of June. |
|
Contractor already paid the
permit fee and the cash bond. No permit were issued yet. For the mandaue
portion, Mandaue questioned why the pipeline is on the roadway and not on the
sidewalk. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
GTCI informed PMO that their
application for excavation permit submitted last March 14, 2013 for Mandaue
portion was not yet acted upon by the concerned agency while for the
Cebu City portion of their contract
which was submitted last March 26, 2013 also did not yield any positive
result. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Expected Extension of Time is
sought by the Contractor due to delay in granting the necessary excavation
permit which is beyond their control. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ř150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana Construction |
Php |
8,368,625.90 |
|
|
07 Feb 2013 |
04 Sep 2013 |
|
0.00% |
0.00% |
0.00% |
Excavation Permit is still
pending to date. No physical Accomplishment so far. |
|
LLC is on the "wait and
see basis." |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.0 |
Proposed Design and
Construction of 10000 M3 Modular Water Tank for JV Water Sourcing Program |
Houston
Hydrotech Products and System Inc. |
Php |
10,650,121.15 |
|
|
03 May 2013 |
29 Nov 2013 |
|
0.00% |
0.00% |
0.00% |
Pre
Construction Meeting was conducted on May 23, 2013. The Contractor tapped the
services of Engr. Cipriano Ramientos as Soil Foundation Engineer and at the
same time Structural Engineer. The contractor has now started actual Soil Investigation and
Laoratory Analysis. |
|
Soil investigation and analysis
expected to come out within the week. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|