REPORT SUMMARY |
|
|
|
|
C.
SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS |
|
|
|
|
|
|
Name
of Project |
Project Beneficiary |
Implementing Unit |
Approved Budget |
Duration |
Date Started |
Completion Date |
Schedule
and Accomplishment |
Remarks |
|
LATEST UPDATE AS OF MARCH 2013 |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
Original |
Revised |
Original |
Revised |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C.1 Pipeline Expansion |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Lagtang Distribution Line[1] |
Sitio Tigib-Burlas, Lagtang, Residents |
Construction Department |
PhP |
2,660,000.00 |
PhP |
|
68 c.d. |
|
|
|
|
|
|
|
The Legal
Department is still awaiting for the amount of Cash Bond for road restoration
works to be set by the Cebu 2nd Engineering District, DPWH. |
|
Until now the Cebu 2nd
Engineering District DPWH has not given us the amount for cash bond for road
restoration works. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Casili Estate Distribution Line |
Casili Estate Residents |
Construction Department |
PhP |
1,391,000.00 |
PhP |
|
21 c.d. |
|
|
|
|
|
|
|
The
electromagnetic metering chlorine injector is being distributed to respective
supplier for their quotation. |
|
No quotation has been returned
from the suppliers until now. |
follow up IDA on
booster procurement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Pusok,
Lapu-Lapu (Matumbo), Pipe laying 96 LM x 75mm dia. & 126 LM x 150mm dia.
D.I. |
Pusok, Lapu-lapu |
Construction
Department |
PhP |
2,292,548.83 |
PhP |
|
145 c.d. |
|
11 Feb 2013 |
21 May 2013 |
|
50.00% |
85.00% |
35.00% |
The
project is now 85% complete and scheduled for completion on May 21, 2013. It
was ahead of the target accomplishment of 35%. Hopefully project will be
completed before target date. |
|
Hopefully project will be
completed before target date. |
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Prop. Water Distribution
System for East Gate Subdivision
(Matumbo, Pusok, Lapulapu) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part D
Section V Subsection D.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
St. Anthony Village, Hi-way 77,
75mm dia. x 234 LM |
St. Anthony Village |
Construction Department |
PhP |
1,100,000.00 |
PhP |
|
23 c.d. |
|
|
|
|
|
|
|
The 75mm PVC
pipes previously rejected by MCWD due to its undersized diameters were
already retrieved by the supplier and the former is awaiting for the latter's
confirmation whether to replace the said pipes or not. If they will be no
longer interested to replace said pipes, MCWD will award to the second lowest
bidder. |
|
Pipes are already on pier. Waiting for supplier to deliver to
Talamban. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Water Distribution
System for Biasong Relocation Site |
P. West Road, Brgy. Biasong,
Talisay City |
Construction Department |
PhP |
1,300,000.00 |
|
|
36 c.d. |
|
|
|
|
|
|
|
The Legal
Department is still awaiting for the amount of Cash Bond for the road
restoration works to be set by the City Engineer's Office of Talisay. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C.2 Pipeline
Rehabilitation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Ø100mm
X 192 lm DI Distribution Rehabilitation
Project along I Tabura St., |
Brgy. Pardo,
Cebu City |
Construction
Department |
PhP |
1,766,946.23 |
PhP |
|
43 c.d. |
|
|
|
|
|
|
|
The
procurement status of this project is still being clustered. |
|
|
|
|
2.0 |
Proposed Ø200mm
X 301 lm DI Distribution Rehabilitation Project along Datag, Maribago, Lapulapu City |
Datag, Maribago,
Lapulapu City |
Construction
Department |
PhP |
4,608,000.00 |
PhP |
|
45 c.d. |
|
|
|
|
|
|
|
The
procurement status of this project is still being clustered. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 6 |
|
|
REPORT SUMMARY |
|
|
|
|
|
|
|
C.
SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS |
|
|
|
|
|
|
|
|
Name
of Project |
Project Beneficiary |
Implementing Unit |
Approved Budget |
Duration |
Date Started |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
Original |
Revised |
Original |
Revised |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C.3 Pumping Station |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Sta. Cruz Well (Liloan) |
Brgy. Sta Cruz Residents |
Bayanihan - C/O PDD |
PhP |
5,590,000.00 |
PhP |
|
87 c.d. |
|
|
|
|
|
97% |
|
The pumping station has been
operational since July 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The remaining project component
is the construction of perimeter fence and gate. Some materials are delivered
and available. Construction of fence will commence anytime if the materials
needed are completed. |
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Sta. Cruz Distribution
Line, Lilo-an, Cebu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part C
Section VII Subsection F.2.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Well 35 |
Berjame
Subdivision and Barangay Talamban Residents |
Bayanihan - C/O PDD |
PhP |
|
|
|
|
|
4 Feb 2012 |
30Apr2012 |
|
|
98% |
|
During
the well testing , PDD/Laboratory personnel had detected the presence of high
level Iron Manganese on the water. PDD is planning to install a filter media
(Iron Manganese Treatment Device) to
remove the Iron Manganese. The testing of berm is already done. Berm is the
replacement of sand. The budget for the abovementioned undertaking is now at
CAPEX for budget allocation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Related Projects: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Berjame Subdivision, Tigbao
Talamban, 100mm dia. x 211LM, 75mm dia. x 391 LM, 50mm dia. x 141 LM |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 Ø100mm Interconnecting
Pipeline (W35) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Already
completed. See Part F Section VII Subsection F.2.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Mac 6, 7 &
8 Pumping Stations Cluster C |
Brgy. Pajac
& Bankal Residents in Lapulapu
City |
Construction
Department/ MSSD |
PhP |
8,709,862.10 |
PhP |
|
113 c.d. |
|
|
|
|
|
|
|
All
the pumping stations' road right of way have already been acquired. The road
rights of way for the connecting lines of these pumping stations are still on
process. |
|
Waiting for issuance for writ
of possession from court. Mac 8 pumping station is allowed to be constructed
ahead of pipe route. |
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mac 6 & 7 Connecting
Pipeline |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part E
Section VI Subsection E.2 of the Report Summary |
|
|
|
2.0 Mac 8 Connecting Pipeline |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part E
Section VI Subsection E.2 of the Report Summary |
|
|
4.0 |
Mac 10 & 11
Pumping Stations |
Brgy. Pajac,
Bankal & Agus Residents in Lapulapu City |
Construction
Department/ MSSD |
PhP |
6,508,756.40 |
PhP |
|
36 c.d. |
|
|
|
|
|
|
|
Awaiting
for the procurement of materials. |
|
as is |
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mac 10 & 11 Connecting
Pipeline |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part E
Section VI Subsection E.2 of the Report Summary |
|
|
5.0 |
Portville (MAC 12) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
special budget appropriation is already approved. Encoding via BMS of
materials is on-going. |
|
Stopped. Cancelled. Deleted. |
|
|
C.4 Transfer
Tapping and Decommissioning |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Transfer
Tapping and Deccommissioning at U. Alviola, Tres de Abril, V. Rama and JM
Basa Streets, Cebu City |
Residents at U.
Alviola, Tres de Abril, V. Rama and JM Basa Sts. |
Construction Department |
PhP |
2,737,000.00 |
|
|
74 c.d. |
|
|
Oct. 8, 2012 |
Jan. 4, 2013 |
|
98% |
|
Inspite
of the occurrence of intervening work, the project is ahead of the target
completion. The project is expected to be completed first week of January
2013. |
|
|
|
|
|
Related Projects: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prop. Replacement of Existing
Distribution Mains Along Tres De Abril, U Alviola, JM Basa and V Rama
Streets, Cebu City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Already
completed. See Part F Section VII Subsection F.1.2 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 7 |
|
|
|
|
|
|
|
|
|
|
|
` |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|