REPORT SUMMARY |
|
|
|
|
|
A. SECTION
II. ON-GOING INFRASTRUCTURE PROJECTS |
|
|
|
|
Name
of Project |
Contractor |
Contract Amount |
Notice to Proceed |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
LATEST UPDATE AS OF MARCH 2013 |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman
Builders and Contractors |
PhP |
16,744,730.61 |
|
|
28 Apr 2010 |
06 Feb 2011 |
Time Extension No. 2 is on
process |
100% |
93.7% |
-6.30% |
Minor physical
activity was done for the month of February. The Contractor, Felman Builders,
conducted asphalt pavement cutting and breaking along M. Ceniza St., Mandaue
City in preparation for the replacement of the defective HDPE pipes. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
An on-going
concreting works along Tingub by the Mandaue LGU poses a problem in replacing
the defective HDPE pipelines since portion of the road where our defective
pipelines were situated have already been concreted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO advises
the Contractor to inform the Mandaue City Engineers’ Office about the plan to
replace the defective pipelines along Tingub area. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
|
|
05 Jan 2011 |
01 Nov 2011 |
Project under suspension. |
- |
61.32% |
- |
Ana
Construction had already installed and hydrotested 342 l.m. of 300mm dia
cc/cl steel pipes along Pajak-Maribago Road. The schedule completion as
agreed for this particular area which is 45 calendar days did not materialize
due to delays attributed to the minor obstruction along the pipeline route as
well as lost time due to equipment breakdown. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of the PERT/CPM is under evaluation |
Project
Management Office reminded the Contractor to fast track and work double time
in order not to hamper the on-going concreting works by the Lapu-lapu LGU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Engr. Allan
Pedrigal, OIC, Lapu-Lapu City Engineer informs PMO about the on-going
concreting works along Sitio Abuno near BF Homes, Pajak-Maribago Road. For
the meantime, Engr. Pedrigal is delaying the concreting works along this area
to pave the way for the installation of 200mm dia x 300m HDPE pipes. However,
it was agreed that the installation should only commence once the contractor
or the water district has acquired the required excavation permit from the
Lapu-lapu Local Government Unit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Prop. Ř 300 mm D.I Distribution
Line along Pit-os, Talamban, Cebu City |
New Culion
Builders Company |
PhP |
54,099,956.35 |
|
|
15 Mar 2012 |
9 Dec 2012 |
30-Mar-13 |
|
69.75% |
|
To date, the
Contractor has already asphalted 2,694 l.m. stretch of pavement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
is eager to complete the asphalting works as soon as possible in order that
their suspension by the Talamban Barangay Council will be lifted and to
resume the installation of the remaining pipelines in Talamban area. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
The Contractor
informs PMO about the delays in their procurement and delivery of butterfly
valves which is beyond their control. This will be the basis for the
contractor to seek for additional time. |
|
|
|
|
|
|
Related Project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Pit-os Injection Point |
|
|
|
|
|
|
|
|
|
|
|
See Part E Section VI Subsection E.1.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. Ř150mm & Ř100mm D.I
Distribution Line along Umapad-Opao, Mandaue City |
New Culion
Builders Company |
PhP |
15,726,332.82 |
|
|
15 Mar 2012 |
9 Nov 2012 |
30-Mar-13 |
|
42.15% |
|
The Contractor
was not able to complete the installation of their pipelines particularly on
the 150mm diameter since some fittings were not yet available. Likewise, they
have difficulty in renting the needed backhoe breaker for the demolition of
concrete pavement on the vicinity of the intersection of U.N. Avenue and
Plaridel St., Mandaue City. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
PMO reminded
the Contractor of their time table to complete the remaining works since
their terminal date is on March 30, 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
however, did submit a request for additional time due to the new requirement
by the Mandaue City Engineer instructing them to put 8” thick lean concrete
before their final Asphalt Restoration. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO is still
evaluating their request for time extension. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Jaclupan Desilting |
WT
Construction |
PhP |
8,000,000.00 |
|
|
17 Jun 2012 |
17 Dec 2013 |
|
|
3.06% |
-10.83% |
Permit from
PENRO is already released on March 5, 2013. Silts already retrieved: 12,244
cu.m. - 3.06% of total volume. |
|
Permit is already released on
March 5, 2013. Silts already retrieved: 12,244 cu.m. - 3.06% of total volume. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary
2 |
|
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
|
A. SECTION
II. ON-GOING INFRASTRUCTURE PROJECTS |
|
|
|
|
Name
of Project |
Contractor |
Contract Amount |
Notice to Proceed |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Prop. D.I. Expansion Project at
Monterrazas de Cebu |
Dakay Construction and
Development Corporation |
Php |
18,288,888.00 |
|
|
01 Nov 2012 |
14 May 2013 |
|
38.89% |
0.00% |
-38.89% |
No physical activity as far as
accomplishment is concerned. The Contractor is still awaiting the arrival of
their D.I. pipes intended for the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
has already secured the excavation permit from the Cebu City Government.
However, such permit will allow them to conduct their activities on night
time from 9pm to 5 am. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO advises
the Contractor to seek for an exemption on the working hours considering that
the area is a residential area and doing night work will create public
disturbance. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO is still
evaluating the Contractors’ request for time extension. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PMO is
reminding the Contractor to constantly follow up the delivery of their needed
D.I. pipes considering that their terminal date is fast approaching. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Prop. D.I. Rehabilitation
Project for DMA-25A, W. Cabalse and Holyname Sts., Mabolo, Cebu City |
Fdrcon Co. |
Php |
2,449,834.22 |
|
|
24 Dec 2012 |
24 Feb 2013 |
|
|
|
|
This is a 'grant project'
funded by JICA thru Yokohama Water Company Limited. This rehabilitation
project that aims to improve the NRW of DMA-25A in Brgy. Mabolo, Cebu City,
involves the installation of approximately 350m Ř100mm PVC pipeline along W.
Cabalse Street and 24m Ř100mm PVC connecting line at corner W. Cabalse and
Holyname Streets. MCWD will handle (c/o PMG) the installation of stub-outs
and transfer-tapping of service connections including the decommissioning of the existing waterline
along W. Cabalse Street. |
|
Remaining works:
Interconnection, restoration, |
|
|
|
|
JICA-YOKOHAMA-MCWD Special
Project |
|
|
|
|
|
|
|
|
|
|
|
Pipelaying activity has been
completed. It already passed hydrostatic testing. Initial flushing and disinfection were also completed on March
27, 2013. Interconnection works is scheduled on the first week of April 2013.
The contractor had experienced difficulty in exploring the existing Ř350 mm
CI pipe along MJ Cuenco Ave. due to its depthness. The actual depth is 2.30
m. from the road surface. . Lean concreting is on going and about 70% completed. The contractor has
also started installing fire hydrants
and its barricades. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On the other hand, PMG has
already commence the installation of
stub-outs. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Ř250 mm D.I. Water
Distribution Line along Sitio Malinao, Agus-Marigondon, Lapulapu City |
Geo Transport &
Construction, Inc. |
Php |
7,488,159.00 |
|
|
28 Jan 2013 |
01 Jul 2013 |
|
0.00% |
0.00% |
0.00% |
4 representatives composing of
PMO, Quality Control Personnel and PMG were able to travel to Kolkata, India
for the In-plant Inspection last March 19-24, 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With this development, the
Contractor is now awaiting for the delivery of their ordered D.I. pipes and
Fittings. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For the meantime, the
Contractor is coordinating with the Local Government Unit of the respective
city for the application of the required excavation permit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ř300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
|
28 Jan 2013 |
26 Jul 2013 |
|
0.00% |
0.00% |
0.00% |
4 representatives composing of
PMO, Quality Control Personnel and PMG were able to travel to Kolkata, India
for the In-plant Inspection last March 19-24, 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With this development, the
Contractor is now awaiting for the delivery of their ordered D.I. pipes and
Fittings. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
For the meantime, the
Contractor is coordinating with Mandaue as well as Cebu City for their
application of Excavation Permit since the project involves two cities. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Ř150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City (for Modena Subdivision) |
Ana Construction |
Php |
8,368,625.90 |
|
|
07 Feb 2013 |
04 Sep 2013 |
|
0.00% |
0.00% |
0.00% |
No physical accomplishment for
this particular project considering that the Lapu-Lapu City Government is
awaiting and evaluating the performance of the Contractor, Ana Construction,
toward the completion of the installation of 300mm dia cc/cl steel pipelines
along Pajak-Maribago Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Excavation Permit is still
pending to date. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|