|
Name of Proposed Project |
Over-all Responsible Unit |
Status of
Work |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
Survey |
Right of Way |
Design |
Estimate |
Bid Documents |
MOA |
|
|
|
1. Projects
for Implementation Thru Joint Venture |
|
|
|
|
|
|
|
|
|
|
|
1.1 Bulk
Water Supply (w/ sources confirmed) |
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Gabi Injection
Point |
JV Committee |
n/a |
n/a |
n/a |
n/a |
n/a |
|
Awaiting
for resolution by the court for the motion for reconsideration filed by
Mactan Rock pertaining to the preliminary injunction. |
|
|
|
2.0 |
Cabancalan
Injection Point |
JV Committee |
n/a |
n/a |
n/a |
n/a |
n/a |
|
Published for competitive
challenge last June 17, 2013. End of publication will be on July 18, 2013. No
company hade submitted their price challenge.
This is for award to Abejo Water Corporation (AWC). Scheduled for
Contract Signing. |
|
|
|
2. Pipeline
Expansion |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Mactan Bubbles-
MAC 6 & 7 (Cluster F)-Connecting Pipelines |
Engineering
Department |
completed |
on
going; LD had issued ROW assurance for Mac 6 only |
completed |
completed |
n/a |
n/a |
ROW
for MAC 6 proposed connecting line was already issued LD while Mac 7 is
recommended for expropriation. LD had prepared PR for Professional fee of
Geodetic Engineer to sign and attest the technical description of the lot to
be expropriated. |
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mactan Bubbles - MAC 6, 7
& 8 (Cluster D) - Pumping Station |
|
|
|
|
|
|
|
See Sub-Item
No. 3 Item No. 3 of Section III - Ongoing By-Administration Projects |
|
|
|
|
2.0 |
Mactan Bubbles - MAC 8
Connecting Pipeline |
Engineering Department |
ongoing |
on
going |
|
|
|
|
On-going
negotiation with the new member of the Joint Venture of the lot owners
involved. Awaiting for feedback from the lot owners. |
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mactan Bubbles - MAC 6, 7
& 8 (Cluster D) - Pumping Station |
|
|
|
|
|
|
|
See Sub-Item
No. 3 Item No. 3 of Section III - Ongoing By-Administration Projects |
|
|
|
|
3.0 |
MAC 10 & MAC 11 Pipeline Network (Mutual Homes) |
Engineering Department |
completed |
completed |
completed |
completed |
|
n/a |
Technical
Services Group to ask ED to resubmit detailed design and estimates for Mac 10
and Mac 11 pipe network. |
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mactan Bubbles - MAC 10,
& 11 (Cluster D) - Pumping Station |
|
|
|
|
|
|
|
See Sub-Item
No. 4 Item No. 3 of Section III - Ongoing By-Administration Projects |
|
|
|
4.0 |
Proposed 200mm
dia. D.I. Water Distribution Mains Along E. Bascon St., Dumlog, Talisay City |
Engineering
Department |
completed |
on going |
completed |
completed |
n/a |
n/a |
Right of Way
Clearance is still on process. |
|
|
|
7.0 |
Proposed 150mm
dia. D.I. Lateral Expansion for Sitio Pundok, Brgy. Pit-os, Cebu City |
Engineering
Department |
completed |
on going |
completed |
completed |
n/a |
n/a |
As
per Atty Panares, ROW is already cleared. No ROW clearance forwarded to ED
yet, as of July 12,2013. |
|
|
|
5.0 |
Proposed D.I.
Lateral Pipelines for Hidden View and Villa Leyson Brgy. Bacayan, Cebu City |
Engineering
Department |
completed |
on going |
completed |
completed |
n/a |
n/a |
Awaiting
for ROW clearance from Legal Dept. There is a problem with the MOA provision
with Hidden View Subd. Pipe route for 75mm at Hidden view has a problem with
acquiring the clearance sice there is no legitimate homeowners in this area.
ED decided to revise plan estimate removing ø75mm pipelines. |
|
|
|
6.0 |
Proposed
Expansion/Lateral Project for Pit-os and Bacayan (Pit-os Extension Pipelines
Project and Sitio Kauswagan) |
Engineering
Department |
completed |
completed |
completed |
completed |
n/a |
n/a |
Already
on BAC. For negotiation with contractor for possible negotiation mode of
contract. |
|
|
|
7.0 |
Proposed 100mm
dia. D.I. Extension Project for Urbanville Homes, Brgy. Pit-os, Cebu City |
Engineering
Department |
completed |
on going |
|
|
n/a |
n/a |
Removed
from original design and estimate on
ø300mm Extension Pipelines for Brgy. Pit-os. THe prop. Ø100mm pipeline is to
be transferred to the opposite side of the road. Negotiation of ROW clearance
is still on process. ED to revise plan and estimate. |
|
|
|
8.0 |
Proposed 100mm
dia. D.I. Expansion Project at Sitio Curva, San Vicente, Liloan, Cebu |
Engineering
Department |
completed |
completed |
completed |
completed |
n/a |
n/a |
Already
indorsed for Special Budget Appropriation to FMD and already included for
agenda on the next Board Meeting on August 15, 2013 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section V. Projects Proposed for Implementation |
14 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Proposed Project |
Over-all Responsible Unit |
Status of
Work |
Remarks |
|
|
|
|
|
|
Survey |
Right of Way |
Design |
Estimate |
Bid Documents |
MOA |
|
|
|
Hydrauli
Area 1: |
|
|
|
|
|
|
|
|
|
|
|
|
Mainland: |
|
|
|
|
|
|
|
|
|
|
|
7.0 |
Cluster 1: Prop. D.I Expansion Project |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
|
a. Poblacion,
Compostela (Ex_Com_15-1) |
Engineering
Department |
completed |
|
|
|
|
|
on-going
plotting of plans |
|
|
|
|
b. Poblacion,
Compostela (Ex_Com_15-2) |
Engineering
Department |
completed |
|
on-going |
|
|
|
|
|
|
|
|
c. Poblacion,
Compostela (Ex_Com_15-3) |
Engineering
Department |
completed |
|
|
|
|
|
on-going
plotting of plans |
|
|
|
8.0 |
Cluster 2: Prop D.I Expansion Project at Poblacion Compostela
(Ex_Com_15-4) |
Engineering
Department |
completed |
|
on-going |
|
|
|
|
|
|
|
9.0 |
Cluster 3:
Prop. DI Expansion Project at Jubay, Liloan (Ex_Lil_15-1) |
Engineering
Department |
completed |
|
|
|
|
|
for
design (no assigned personnel yet) |
|
|
|
10.0 |
Cluster 4: Prop. DI Expansion Project at Poblacion, Catarman, Liloan
(Ex_Lil_15-2) |
Engineering
Department |
completed |
|
|
|
|
|
for
design (no assigned personnel yet) |
|
|
|
11.0 |
Cluster 5: Prop. DI Expansion Project at Tayud, Consolacion (Ex_Cons_15-1) |
Engineering
Department |
on going |
|
|
|
|
|
The target schedule for the completion of route
survey for all Hydraulic Area -1
Expansion Projects will be on the last
week of October 2013 |
|
|
|
12.0 |
Cluster 6: Prop. DI Expansion Project at Tayud,
Consolacion |
Engineering
Department |
on going |
|
|
|
|
|
|
|
|
|
a. Tayud,
Consolacion (Ex_Cons_15-1a) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
2 |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c. Tayud,
Consolacion (Ex_Cons_15-2b) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
13.0 |
Cluster 7: Prop. DI Expansion Project at Tayud, Consolacion |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a. Tayud,
Consolacion (Ex_Cons_15-1b) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Tayud,
Consolacion (Ex_Cons_15-2c) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c. Tayud,
Consolacion (Ex_Cons_15-2d) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
d. Tayud,
Consolacion (Ex_Cons_15-2e) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
14.0 |
Cluster 8: Prop. DI Expansion Project
at Tayud, Consolacion |
Engineering
Department |
completed |
on going |
|
|
|
|
|
|
|
|
a. Tayud,
Consolacion (Ex_Cons_15-2f) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Tayud,
Consolacion (Ex_Cons_15-2g) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c. Tayud,
Consolacion (Ex_Cons_15-2h) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
15.0 |
Cluster 9: Prop. DI Expansion Project at Tayud,
Consolacion |
Engineering
Department |
completed |
on going |
|
|
|
|
|
|
|
|
a. Tayud,
Consolacion (Ex_Cons_15-1c) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Tayud,
Consolacion (Ex_Cons_15-2i) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
15.0 |
Cluster 10: Prop. DI Expansion
Project at Labogon, Mandaue |
Engineering
Department |
completed |
on going |
|
|
|
|
|
|
|
|
a. Labogon,
Mandaue (Ex_Man_15-1a) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Labogon,
Mandaue (Ex_Man_15-1b) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c. Labogon,
Mandaue (Ex_Man_15-1c) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
16.0 |
Cluster 11: Prop. DI Expansion
Project at Tabok Mandaue |
Engineering
Department |
completed |
on going |
|
|
|
|
|
|
|
|
a. Tabok,
Mandaue (Ex_Man_15-2a) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Tabok,
Mandaue (Ex_Man_15-2b) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
Mactan Island: |
Engineering
Department |
|
|
|
|
|
|
|
|
|
17.0 |
Cluster 1: Prop. D.I Expansion Project for Pajo-Poblacion, Lapu-lapu (
Ex_Lap_15-4) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
18.0 |
Cluster 2: Prop
D.I Expansion Project at Poblacion Lapu-lapu |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a. Poblacion
(Ex_Lap_15-1) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Poblacion
(Ex_Lap_15-12) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c Pajo-
Poblacion (Ex_Lap_15-13) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
19.0 |
Cluster 3: Prop
D.I Expansion Project at Poblacion Cordova |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a. Poblacion
(Ex_Cord_15-3) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Poblacion
(Ex_Cord_15-14) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
20.0 |
Cluster 4: Prop D.I Expansion Project at Poblacion Cordova |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a. Poblacion
(Ex_Cord_15-1) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Poblacion
(Ex_Cord_15-2) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
20.0 |
Cluster 5: Prop
D.I Expansion Project at Marigondon-Maribago |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a.
Marigondon-Maribago (Ex_Lap_15-7) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section V. Projects Proposed for Implementation |
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Proposed Project |
Over-all Responsible Unit |
Status of
Work |
Remarks |
|
|
|
|
|
|
Survey |
Right of Way |
Design |
Estimate |
Bid Documents |
MOA |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The target schedule for the completion of route survey for all
Hydraulic Area-1 Expansion Projects will be on the last week of October 2013 |
|
|
|
21.0 |
Cluster 6: Prop D.I Expansion Project at Maribago |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a. Maribago
(Ex_Lap_16a) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Maribago
(Ex_Lap_16b) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c. Maribago
(Ex_Lap_16c) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
22.0 |
Cluster 7: Prop D.I Expansion Project at Mactan |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
a. Mactan
(Ex_Lap_15-5a) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
b. Mactan
(Ex_Lap_15-5b) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
c. Mactan
(Ex_Lap_15-5c) |
Engineering
Department |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Pipeline Rehabilitation |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Expansion/Rehabilitation
Pipelines Project for Mactan Water Distribution System (Cluster F) : |
Engineering Department |
|
|
|
|
|
|
|
|
|
|
|
a. Road to Tambuli |
completed |
completed |
completed |
completed |
|
n/a |
ROW
acquisition is still on process. |
|
|
|
|
b. Road to Mactan Rock |
completed |
completed |
completed |
completed |
|
n/a |
Brgy.
Marigondon Officials had just informed MCWD that prop. pipe route is no
longer part of their jurisdiction, but with Suba Basbas already. ROW
clearance request is to be transferred to Brgy. Subabasbas. |
|
|
|
|
c. Pajac |
completed |
completed |
completed |
completed |
|
n/a |
ROW
already clearred |
|
|
|
|
d. Sitio Angasil |
completed |
completed |
completed |
completed |
|
n/a |
ROW
already clearred |
|
|
|
2.0 |
MEPZ-1 Gate2 & Gate3 |
Engineering
Department |
completed |
|
completed |
completed |
|
n/a |
Forwarded
to FMD for budget verification. |
|
|
|
3.0 |
Poblacion, Consolacion (H. Pepito) |
Engineering
Department |
completed |
|
completed |
completed |
|
n/a |
ROW clearance
is still on process. |
|
|
|
4.0 |
San Vicente Liloan |
Engineering
Department |
completed |
|
|
|
|
n/a |
scheduled for
detailed design and estimates |
|
|
|
5.0 |
Calero, Liloan |
Engineering
Department |
completed |
|
|
|
|
n/a |
For hydraulic
analysis |
|
|
|
6.0 |
Babag 1, Lapu-lapu City |
Engineering
Department |
completed |
|
on-going |
on-going |
|
|
|
|
|
|
7.0 |
Beside Narciso Road, Pulpogan,
Consolacion |
Engineering
Department |
completed |
on going |
completed |
completed |
|
|
|
|
|
|
8.0 |
Panagdait, Kasambagan |
Engineering
Department |
completed |
on-going |
completed |
completed |
|
|
|
|
|
|
9.0 |
IPI Village, Mactan |
Engineering
Department |
completed |
|
|
|
|
|
for
Hydraulic Analysis |
|
|
|
10.0 |
Palm Hills, Mandaue City |
Engineering
Department |
completed |
|
on-going |
on-going |
|
|
|
|
|
|
11.0 |
Palm Hills, Mandaue City (additional) |
Engineering
Department |
completed |
|
|
|
|
|
for
design |
|
|
|
12.0 |
Poblacion, Consolacion |
Engineering
Department |
completed |
|
completed |
completed |
|
|
for
design |
|
|
|
13.0 |
Soong, Maribago |
Engineering
Department |
completed |
|
|
|
|
|
for
design |
|
|
|
14.0 |
Bulacao, Pardo cor. Villa Bulsita
(973m) |
Engineering
Department |
completed |
|
|
|
|
|
for
design |
|
|
|
4. Pumping
Station |
|
|
|
|
|
|
|
n/a |
|
|
|
|
1.0 |
Well T-1 |
Engineering
Department |
|
on-going |
|
|
|
|
ROW
assurance already issued by LD. Payment has already been made. Awaiting for
the Deed of Absolute Sale. Scheduled for survey then detailed design |
|
|
|
3.0 |
Well L-8 |
Engineering Department |
completed |
n/a |
on-going |
on-going |
|
n/a |
Detailed Design on-going. Target to be
completed on October 2013. |
|
|
|
4.0 |
In-house Water
Sourcing Cluster- B (MC-23 and G-10) |
|
|
|
|
|
|
|
|
|
|
|
|
a. MC 23 |
Engineering Department |
on going |
completed |
|
|
|
|
Proposed new
pipe route is scheduled for route survey . Detailed design and estimate will
then follow. |
|
|
|
|
b. G-10 |
Engineering
Department |
completed |
completed |
completed |
completed |
|
|
MC 23 &
G-10 is one cluster for the implementation. Thus, G-10 implementation is
dependent on the completion of MC 23 detailed design and estimates. |
|
|
|
5.0 |
CUB-1 |
Engineering
Department |
completed |
completed |
completed |
completed |
|
n/a |
Request for
budget augmentation to FMD is already approved. For endorsement to TSG for
implementation. |
|
|
|
6.0 |
MAN- 1 |
Engineering
Department |
completed |
completed |
completed |
completed |
|
|
Already with
BAC-2 for bidding. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section V. Projects Proposed for Implementation |
16 |
|
|
|
|
|
Name
of Proposed Project |
Over-all Responsible Unit |
Status of
Work |
Remarks |
|
|
|
|
|
|
Survey |
Right of Way |
Design |
Estimate |
Bid Documents |
MOA |
|
|
|
5.
Reservoir |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
500 cu.m. Nivel Hills Concrete Reservoir / Busay |
Engineering Department |
completed |
|
see
remarks |
see
remarks |
|
n/a |
Deferred, as per Engr. Singson advisory due to
the possible increase of storage capacity coming from the JV Bulk Water
Supplier. For review of final capacity based on the ideal required volume for the area. |
|
|
|
2.0 |
500m3
Concrete Reservoir at Oprra |
Engineering
Department |
completed |
|
see
remarks |
see
remarks |
|
n/a |
|
|
|
|
6.
Other Projects |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed MSSD
Building |
Engineering
Department |
completed |
completed |
completed |
completed |
|
|
Detailed
design, estimates and specifications were already completed. It was then
forwarded to AGM for Technical Services for presentation with EXECOM. |
|
|
|
|
2.0 |
Septage |
MCWD |
|
see remarks |
see remarks |
see remarks |
|
|
For Cordova:
The Honorable Municipal Council of Cordova had already passed its Septage
Ordinance. Cordova is the town where the proposed Septage Treatment Plant
will be constructed. This treatment plant will cater Cordova, Lapulapu City
and part of Mandaue City. For now
implementation for said Treatment Plant has been deferred pending passing of
Lapulapu City Septage Ordinance. A
copy of TOR from Baliuag Water District is now at Corplan for reference of
implemenation scheme. |
|
|
|
|
|
|
|
|
|
|
|
|
For Lapulapu : MCWD made a
follow up on the resumption on the regular meeting between MCWD and Lapulapu
City Government for the preparation/drafting of the Proposed Amendments of
the Existing Septage Ordinance but no response yet. As per information Lapulapu
City is still awaiting the Chairmanship of Committe on Environment whom the
Charirperson would be coming from Lapulapu City Councilor. |
|
|
|
|
|
|
|
|
|
|
|
|
For Cebu City: JICA has proposed with Cebu Ctiy LGU to put
up a dewatering machine along with a feasibility study on Septage Management.
However, the finality awaits on the institutional arrangement that should
govern the project for effective implementation and sustainabilty. The said
facility will soon be erected at STP site in North Reclemation Area ( at the
back of SM ) |
|
|
|
7. WASEC Projects |
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Mactan Plains
Subdivision (Mother Meter) |
Engineering
Department |
completed |
n/a |
completed |
completed |
n/a |
|
awaiting
for the realization of interconnecting pipelines project and lateral
pipelines for of Sitio Angasil (Cluster F). ROW clearances for Tambuli and
Road to Mactan Rock (projects included in cluster F) are still on process. |
|
|
|
2.0 |
Summerville 2
Subdivision |
Engineering
Department |
completed |
n/a |
completed |
completed |
n/a |
|
Lot
ownership issue of the subdivision is yet to be settled by the developer. So
far, no feedback from the developer with regards on their resuqest. |
|
|
|
3.0 |
Pasadena
Subdivision Phase 2 |
Engineering
Department |
completed |
n/a |
completed |
completed |
n/a |
|
The
draft MOA was forwarded to the Developer. Put on hold until further notice by
the Developer. No feedback from the developer. Phase 1 is currently connected
with our system. |
|
|
|
4.0 |
Proposed Ø75mm
Surface Mounted Flowmeter for Bamboo Bay Community at Subangdaku, Mandaue
City |
Engineering
Department |
completed |
n/a |
completed |
completed |
n/a |
|
No
feedback from the developer yet. |
|
|
|
5.0 |
Proposed Ø75mm
Surface Mounted Flowmeter for Midori Residences at A.S. Fortuna Ave., Mandaue
City |
Engineering
Department |
completed |
n/a |
completed |
completed |
n/a |
|
No
feedback from the developer yet. |
|
|
|
6.0 |
Proposed Ø100mm
Surface Mounted Flowmeter for One Pavilion Place at Banawa, Guadalupe, Cebu
City |
Engineering
Department |
completed |
n/a |
completed |
completed |
n/a |
|
Currently
connected with our system using 2" meter assembly. NO feedback on the
proposed upsizing of meter assembly. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section V. Projects Proposed for Implementation |
17 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|