REPORT SUMMARY
C. SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS
Name of Project  Project Beneficiary Implementing Unit Approved Budget Duration Date Started Completion Date Schedule and Accomplishment Remarks LATEST UPDATE AS OF FEBRUARY 2013
Target            To Date Actual       To Date Variance To Date
Original Revised Original  Revised Original Revised
                                 
C.1 Pipeline Expansion                              
                                 
                                 
1.0 Lagtang Distribution Line[1] Sitio Tigib-Burlas, Lagtang,  Residents Construction Department PhP    2,660,000.00 PhP 68 c.d.             The MCWD & DPWH had already conducted the Scheduled Site Inspection of the area January 28, 2013. The latter instructed us to reflect the sketch cross-section of trench excavation & existing road on the plan, for them to evaluate the exact area & volume of the damage road pavement. However, the DPWH assured us that they will initiate the processing of the excavation permit, even before the said sketch is submitted to.  
                                  
2.0 Casili Estate Distribution Line Casili Estate Residents Construction Department PhP    1,391,000.00 PhP   21 c.d.               There is no movement in the processing of the Electromagnetic Metering Chlorine Injector. It is still in the BAC TWG as of thie writing. follow up IDA on booster procurement
3.0 Pusok, Lapu-Lapu (Matumbo), Pipe laying 96 LM x 75mm dia. & 126 LM x 150mm dia. D.I. Pusok, Lapu-lapu Construction Department PhP    2,292,548.83 PhP   145 c.d.   11 Feb 2013 21 May 2013         The project is scheduled to commence on February 11, 2013 with the completion date on May 21, 2013. Project has started as scheduled.
  Related Project:                        
  1.0 Prop. Water Distribution System for  East Gate Subdivision (Matumbo, Pusok, Lapulapu)                       See Part D Section V Subsection D.1 of the Report Summary
                         
4.0 St. Anthony Village, Hi-way 77, 75mm dia. x 234 LM  St. Anthony Village Construction Department PhP    1,100,000.00 PhP   23 c.d.               The project is still awaiting the delivery of pipes & other materials. The pipes intended for this project delivered by the supplier in January 2013 had been rejected because they have been found to be not in standard size as ordered. The excavation permit has already been applied by Legal Department.
                         
5.0 Berjame Subdivision, Tigbao Talamban, 100mm dia. x 211LM, 75mm dia. x 391 LM, 50mm dia. x 141 LM Berjame Subdivision Construction Department PhP    2,027,423.69 PhP   42 c.d.   11 Feb 2013 21 May 2013         The project is scheduled to commence on February 11, 2013 with the completion date on March 16, 2013. Project has already started. Expected to be completed by March 16, 2013.
                           
  Related Projects:                        
  1.0  Well 35                       See Part C Section IV Subsection C.3 of the Report Summary
  2.0 Ø100mm Interconnecting Pipeline (W35)                       See Part C Section VII Subsection F.2.1 of the Report Summary
                         
6.0 Alberlyn South Road, Cansojong Talisay Alberlyn South Road Subdivision Construction Department/ Pipeline Maintenance Group Central (PMG) PhP    1,596,881.63 PhP   52 c.d.               The installed pipeline has already passed the hydrotesting & chlorinator test. The remaining works to be done is restoration works of the damaged pavement.
  Related Project:                        
  1.0 Prop. Water Distribution System for Alberlyn South Subdivision (Cansojong, Talisay City, Cebu)                              See Part D Section V Subsection D.1 of the Report Summary
7.0 Proposed Water Distribution System for Biasong Relocation Site P. West Road, Brgy. Biasong, Talisay City Construction Department PhP    1,300,000.00 36 c.d.             The procurement status of the Ø100mm & Ø150mm PVC pipes are still being clustered by BAC. The excavation permit has already been applied by Legal Department. Schedule of delivery of pipes is in the last week of February 2013. The granting of the excavation permit is expected on the first week of March 2013.
                         
                                 
C.2 Pipeline Rehabilitation                              
                                 
1.0 Proposed Ø100mm X 192 lm DI Distribution Rehabilitation   Project along I Tabura St., Brgy. Pardo, Cebu City Construction Department PhP    1,766,946.23 PhP   43 c.d.               The procurement status of this project is still being clustered.
2.0 Proposed Ø200mm X 301 lm DI Distribution Rehabilitation Project  Datag, Maribago, Lapulapu City Construction Department PhP    4,608,000.00 PhP   45 c.d.               The procurement status of this project is still being clustered.
Section I. Summary   6  
REPORT SUMMARY
C. SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS
Name of Project  Project Beneficiary Implementing Unit Approved Budget Duration Date Started Completion Date Schedule and Accomplishment Remarks
Target            To Date Actual       To Date Variance To Date
Original Revised Original  Revised Original Revised
                     
C.3 Pumping Station                                 
                                 
1.0 Sta. Cruz Well (Liloan) Brgy. Sta Cruz Residents Bayanihan - C/O PDD PhP    5,590,000.00 PhP 87 c.d.         97% The pumping station has been operational since July 2012.
                    The remaining project component is the construction of perimeter fence and gate. Some materials are delivered and available. Construction of fence will commence anytime if the materials needed are completed. 
  Related Project:                        
  1.0 Sta. Cruz Distribution Line, Lilo-an, Cebu                       See Part C Section VII Subsection F.2.1 of the Report Summary 
                                 
  2.0 Well 35 Berjame Subdivision and Barangay Talamban Residents Bayanihan - C/O PDD PhP           4 Feb  2012 30Apr2012     98%   During the well testing , PDD/Laboratory personnel had detected the presence of high level Iron Manganese on the water. PDD is planning to install a filter media (Iron Manganese Treatment Device)  to remove the Iron Manganese. The testing of berm is already done. Berm is the replacement of sand. The budget for the abovementioned undertaking is now at CAPEX for budget allocation.
                           
  Related Projects:                        
  1.0 Berjame Subdivision, Tigbao Talamban, 100mm dia. x 211LM, 75mm dia. x 391 LM, 50mm dia. x 141 LM                        
  2.0 Ø100mm Interconnecting Pipeline (W35)                       Already completed. See Part F Section VII Subsection F.2.1 of the Report Summary
                                 
  3.0 Mac 6, 7 & 8 Pumping Stations Cluster C Brgy. Pajac &  Bankal Residents in Lapulapu City Construction Department/ MSSD PhP    8,709,862.10 PhP   113 c.d.               No PR is being prepared yet. The BMS has not been approved by FMD because the ROW of these pumping stations have not been acquired yet.
  Related Project:                        
  1.0 Mac 6 & 7 Connecting Pipeline                       See Part E Section VI Subsection E.2 of the Report Summary
  2.0 Mac 8 Connecting Pipeline                             See Part E Section VI Subsection E.2 of the Report Summary
  4.0 Mac 10 & 11 Pumping Stations Brgy. Pajac, Bankal & Agus Residents in Lapulapu City Construction Department/ MSSD PhP    6,508,756.40 PhP   36 c.d.               The PR of these two pumping stations have already been prepared.
  Related Project:                        
  1.0 Mac 10 & 11 Connecting Pipeline                             See Part E Section VI Subsection E.2 of the Report Summary
  5.0 MAC 12 PUMPING STATION                             For Special Budget Appropriation (SBA).
C.4 Transfer Tapping and Decommissioning                                    
1.0 Transfer Tapping and Deccommissioning at U. Alviola, Tres de Abril, V. Rama and JM Basa Streets, Cebu City Residents at U. Alviola, Tres de Abril, V. Rama and JM Basa Sts. Construction Department PhP    2,737,000.00     74 c.d.     Oct. 8, 2012 Jan. 4, 2013   98%   Inspite of the occurrence of intervening work, the project is ahead of the target completion. The project is expected to be completed first week of January 2013.