|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
|
|
|
|
|
B. SECTION
III. ON-GOING JOINT VENTURE UNDERTAKINGS |
|
|
|
Name
of Contract |
Joint Venture Partner |
Minimum Volume |
Supply Cost |
Date of Contract Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
LATEST UPDATE AS OF FEBRUARY 2013 |
|
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Bulk Water Supply Program - BC Homes Injection Point |
Abejo Waters Corporation |
2,000 |
m3/day |
PhP |
16.48 |
/m3 |
29 Apr 2010 |
29 Oct 2010 |
31 Aug 2012 |
The Apas
Injection Point (originally at BC Homes) has been supplying water to MCWD
since December 21, 2011. |
|
Awaiting advice from PWRI or
abejo which program to use. Additional 45 calendar days for the 4 projects.
As of Feb. on going joint inspection for chloring and data. |
|
|
|
|
|
|
|
|
|
|
|
|
|
On the
required Data Monitoring Software (calculate/tabulate/ data, show graphs,
indicate under- or over-supply), the Bulk Water Suppliers during the 21
February 2013 meeting were given the option to use the PWRI-developed Data Monitoring Software
or the Premier Portal Web. PMO is awaiting official advice from AWC of its
choice. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Related to the
Ø150mm x 1.60kms AWC pipeline and booster station which were turned-over to
MCWD, VECO has yet to activate the power supply of the booster station. As
relayed by AWC, though, VECO will activate the power supply early March. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Bulk Water Supply Program - Banawa Injection Point |
Pilipinas Water Resources, Inc. |
1,500 |
m3/day |
PhP |
14.68 |
/m3 |
18 May 2010 |
18 Nov 2010 |
02 Jan 2011 |
The Banawa
Injection Point has been supplying water to MCWD since December 9, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The PWRI-developed Data
Monitoring Software had been found acceptable
after its trial run. MCWD however, during the 21 February 2013 meeting
with the Bulk Water Suppliers, had required PWRI to include some features on
the software. PWRI had asked 45 calendar days to deliver the final version of
the software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production and supply facilities) will be
declared fully completed only after the succesful installation of the
software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Bulk Water Supply Program - Talamban Injection Point |
Pilipinas Water Resources, Inc. |
3,592 |
m3/day |
PhP |
14.21 |
/m3 |
19 Nov 2010 |
19 May 2011 |
5 Dec 2011 |
The Talamban
Injection Point has been supplying water to MCWD since December 6, 2011. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The PWRI-developed Data
Monitoring Software had been found acceptable
after its trial run. MCWD however, during the 21 February 2013 meeting
with the Bulk Water Suppliers, had required PWRI to include some features on
the software. PWRI had asked 45 calendar days to deliver the final version of
the software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Phase I of this Joint
Venture (i.e. installation of production / supply facilities and supply of
bulk water) will be declared fully completed after the successful
installation of the data monitoring software. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Bulk Water Supply Program - Marigondon-Gabi Injection Point |
Mactan Rock Industries, Inc. |
5,000 |
m3/day |
PhP |
26.72 |
/m3 |
signing: 06 Dec
2010
effectivity:
01 Jan 2011 |
01 Jul 2011 |
8 Jan 2012 |
The
Marigondon-Gabi Injection Point has been supplying water to MCWD since
February 17, 2012. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On the
required Data Monitoring Software (calculate/tabulate/ data, show graphs,
indicate under- or over-supply), the Bulk Water Suppliers during the 21
February 2013 meeting were given the option to use the PWRI-developed Data Monitoring Software
or the Premier Portal Web. PMO is awaiting official advice from AWC of its
choice. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On the
installed pH and Chlorine Instrument, the
joint monitoring/observation by MCWD Laboratory and MRII personnel of
the pH and chlorine readings is ongoing. The result of the observation will
be known early March. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 4 |
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
|
|
|
|
|
B. SECTION
III. ON-GOING JOINT VENTURE UNDERTAKINGS |
|
|
|
Name
of Contract |
Joint Venture Partner |
Minimum Volume |
Supply Cost |
Date of Contract Signing / Notice to Proceed |
Day 1
Delivery Date |
Remarks |
|
|
|
|
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Bulk Water Supply Program - Guadalupe Injection Point |
Abejo Waters Corporation |
3,000 |
m3/day |
PhP |
14.98 |
/m3 |
07 Dec 2011 |
06 Dec 2012 |
Time Extension on process |
This JV
Contract has 3 injection points spread over Brgy. Guadalupe: Guadalajara,
Kabajar, and Quijada. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Guadalajara
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The additional
partial delivery requested by AWC and approved by MCWD is now in effect. From
800 cum/day previously, it is now 2,400 cum/day. The water is sourced from
Wells G-1 and G-2. |
|
presently supplying 2400 cu.m.
daily. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kabajar
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWC has
temporarily stopped the partial delivery of water at the Kabajar Injection
Point. This as AWC removed the pump of Well G-3 and transferred it to Well
G-5 for the chemical and physical test of the latter. |
|
presently supplying 0 cu.m.
transfer of pump. PMO endorsed 6 months t.e.. PMO is still waiting advice
from pdd regarding the |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Quijada
Injection Point : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MCWD c/o the
office of AGM Delco is still evaluating the proposal of AWC to relocate the
Quijada injection point. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Ø250mm
MCWD distribution line along Quijada Street, to which the AWC supply line
will connect, has yet to be installed. Installation of said Ø250mm
distribution line is presently undertaken by Dakay Construction and
Development Corporation under the project DI Expansion at Monterazzas de
Cebu. The project is expected to be completed by May 2013. For this reason,
the MCWD Execom had approved the extension of the intended Day 1 of delivery
for the Guadalupe Joint Venture is until June 30, 2013. |
|
|
|
|
|
Related Project (for Quijada Injection Point only): |
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Monterrazas Pipelaying
Project |
|
|
|
|
|
|
|
|
|
See Part E Section VI Subsection E.2 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|