REPORT SUMMARY |
|
|
|
|
|
A. SECTION
II. ON-GOING INFRASTRUCTURE PROJECTS |
|
|
|
|
Name
of Project |
Contractor |
Contract Amount |
Notice to Proceed |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
LATEST UPDATE AS OF MARCH 2013 |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Prop. Pipeline Expansion for
Cabancalan Bulk Water Supply |
Felman
Builders and Contractors |
PhP |
16,744,730.61 |
|
|
28 Apr 2010 |
06 Feb 2011 |
Time Extension No. 2 is on
process |
100% |
93.7% |
-6.30% |
Felman
Builders were reminded pertaining to their terminal date which is on July 31,
2013 to finish their project otherwise Liquidated Damages will be imposed. So
far, no physical activities pertaining to the replacement of the inferior
HDPE pipes were being conducted as the contractor is preparing their
resources such as manpower and equipment. Portion of the 307 lengths
replacement HDPE pipelines composing of diameters 75mm, 100mm and 150mm
passed the various test conducted by MCWD Quality Control Personnel.
Remaining replacement pipes are still due for delivery by their supplier,
MIGS System. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Prop. Mactan Water System
Improvement Program - Package 5 |
Ana Construction |
PhP |
38,443,210.45 |
|
|
05 Jan 2011 |
01 Nov 2011 |
Project under suspension. |
- |
61.32% |
- |
The Lapu-Lapu City Government thru the City Engineer’s Office
has granted the Contractor via MCWD an Excavation Permit for the Proposed
Mactan Water System Improvement Program (MWSIP) Package 5 specifically the
528 l.m. 300mm dia cc/cl steel pipes along Pajak-Maribago Road. Project
Management Office is coordinating closely with the Contractor regarding the
implementation and insisted that the project should be completed on or before
the set deadline which is 45 calendar days. PMO informs the Contractor that
the early completion of this segment will motivate the Lapu-Lapu City
Government to approve the permit intended for the remaining areas under
Package 5. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of the PERT/CPM is under evaluation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Prop. Ø 300 mm D.I Distribution
Line along Pit-os, Talamban, Cebu City |
New Culion
Builders Company |
PhP |
54,099,956.35 |
|
|
15 Mar 2012 |
9 Dec 2012 |
30-Mar-13 |
|
60.72% |
|
To date, the
Contractor has laid 3,088.71 l.m. of 300mm dia. D.I. pipes wherein 2,801.71
l.m. were already hydrotested. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Contractor
was not able to complete the pipelaying works since they are concentrating on
the installation of lean concrete in preparation for final asphalt
overlay. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
A total length
of 2,239 l.m. of pavement was already placed with lean concrete. The
Contractor is only allowed to install lean concrete on pavement during Friday
and Saturday to avoid traffic caused by the curing of the lean concrete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The SP/Cl
Steel pipes along the Bacayan Bridge have already passed the hydrotesting
test. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contractor’s
request for Variation Order is on the final stage of evaluation. Likewise,
their request for time extension was approved by MCWD Management. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New Terminal
Date of Completion will be on March 30, 2013. |
|
|
|
|
|
|
Related Project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Pit-os Injection Point |
|
|
|
|
|
|
|
|
|
|
|
See Part E Section VI Subsection E.1.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
Prop. Ø150mm & Ø100mm D.I
Distribution Line along Umapad-Opao, Mandaue City |
New Culion
Builders Company |
PhP |
15,726,332.82 |
|
|
15 Mar 2012 |
9 Nov 2012 |
30-Mar-13 |
|
42.15% |
|
The Contractor
did maximize the installation of D.I. pipes for the month of February after
its delivery last January. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revision of PERT/CPM is on process |
A total of 486
l.m. of 100mm dia and 247.50 l.m. of 150mm dia D.I. pipes were installed for
the month of February. They are expected to complete their pipelaying works
by next month. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
installation of G.I. Pipes along Paknaan Bridge is already complete and will
be subjected to hydrotesting activities. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MCWD
Management already approved the Contractor’s request for additional time due
to the change of tapping saddles and the delays in procuring the revised
saddles. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With the
approval, the Contractor’s new terminal date is on March 30, 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Jaclupan Desilting |
WT
Construction |
PhP |
8,000,000.00 |
|
|
17 Jun 2012 |
17 Dec 2013 |
- |
|
|
|
The total
physical volume percentage covered on the removal of silt, sand and gravel at
sedimentation basin, river channel, and weir is already 1.91% as of January
31, 2013. This is equivalent to 7,640 cu. m.. Contractor WT Construction is
still awaiting for the permit to be issued by PENRO. |
|
|
|
|
Section I. Summary
2 |
|
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
|
A. SECTION
II. ON-GOING INFRASTRUCTURE PROJECTS |
|
|
|
|
Name
of Project |
Contractor |
Contract Amount |
Notice to Proceed |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
At Award |
Present |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.0 |
Prop. D.I. Expansion Project at
Monterrazas de Cebu |
Dakay Construction and
Development Corporation |
Php |
18,288,888.00 |
|
|
01 Nov 2012 |
14 May 2013 |
|
38.89% |
0.00% |
-38.89% |
The Contractor requested for an
exemption for the In-Plant Inspection to Kolkata, India due to the recent
change in policy for granting Business Visa to enter India which took so long
to process and thus delaying the inspection of the needed materials as well
as its delivery. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MCWD
Management approved the request for exemption provided that the Contractor
will submit the Manufacturer’s Certification stating that the D.I. pipes and
fittings conform to the standards and specification as prescribed in ISO 2531
as well as they will guarantee and take the full responsibility of the
materials delivered and installed in the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With the
approved exemption, PMO expects that the Contractor will coordinate with
their agent, Waterkonsult, for the processing of documents and for the
delivery of the D.I. pipes and materials. |
|
|
|
|
7.0 |
Prop. D.I. Rehabilitation
Project for DMA-25A, W. Cabalse and Holyname Sts., Mabolo, Cebu City |
Fdrcon Co. |
Php |
2,449,834.22 |
|
|
24 Dec 2012 |
24 Feb 2013 |
|
|
|
|
This is a 'grant project'
funded by JICA thru Yokohama Water Company Limited. This rehabilitation
project that aims to improve the NRW of DMA-25A in Brgy. Mabolo, Cebu City,
involves the installation of approximately 350m Ø100mm PVC pipeline along W.
Cabalse Street and 24m Ø100mm PVC connecting line at corner W. Cabalse and
Holyname Streets. MCWD will handle (c/o PMG) the installation of stub-outs
and transfer-tapping of service connections including the decommissioning of the existing waterline
along W. Cabalse Street. |
|
|
|
|
|
|
JICA-YOKOHAMA-MCWD Special
Project |
|
|
|
|
|
|
|
|
|
|
|
The Contractor had requested a
time extension until March 14, 2013 as the the Excavation Permit was granted
by the Cebu City Government only on January 28, 2013 after the Sinulog Festivities. The request
for time extension was granted. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Project Schedule and Target
Accomplishment will be revised following the grant of time extension. Ending
February, the actual project accomplishment is 52.53%. Pipelaying and related
works are ongoing and expected to be completed within the revised completion date. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8.0 |
Proposed Ø250 mm D.I. Water
Distribution Line along Sitio Malinao, Agus-Marigondon, Lapulapu City |
Geo Transport &
Construction, Inc. |
Php |
7,488,159.00 |
|
|
28 Jan 2013 |
01 Jul 2013 |
|
0.00% |
0.00% |
0.00% |
Pre-Construction Meeting was
held last February 7, 2013. The Project was awarded to Geo-Transport and
Construction Inc. Notice to Proceed was given last January 28, 2013 with a
Contract Duration of 155 Calendar Days. The Project is expected to be completed
on July 1, 2013. Important matters and procedures for the smooth
implementation of the project were discussed thoroughly. PMO approved the
Contractor’s shop drawings of pipes and fittings. The Contractor is now
coordinating with their agent, Waterkonsult, for the application of the
Business Visa to India for the In-Plant Inspection. 5 representatives composing of PMO,
Engineering and PMG personnel will be tasked to inspect the D.I. pipes and
Fittings in Kolkata, India. The Contractor is now securing the necessary
excavation permit from the City of Lapu-Lapu. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9.0 |
Proposed Ø300 mm D.I. Water
Distribution Main - Canduman, Mandaue
City to Tigbao, Talamban, Cebu City |
Geo Transport &
Construction, Inc. |
Php |
17,900,658.75 |
|
|
28 Jan 2013 |
26 Jul 2013 |
|
0.00% |
0.00% |
0.00% |
Pre-Construction Meeting was
held last February 7, 2013. The Project was awarded to Geo-Transport and
Construction Inc. Notice to Proceed was given last January 28, 2013 with a
Contract Duration of 180 Calendar Days. The Project is expected to be completed
on July 26, 2013. Important matters and procedures for the smooth
implementation of the project were discussed thoroughly. PMO approved the
Contractor’s shop drawings of pipes and fittings. The Contractor is now
coordinating with their agent, Waterkonsult, for the application of the
Business Visa to India for the In-Plant Inspection. 5 representatives composing of PMO,
Engineering and PMG personnel will be tasked to inspect the D.I. pipes and
Fittings in Kolkata, India. The Contractor is now securing the necessary
excavation permit from 2 Local Government Units namely Mandaue City and Cebu
City. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.0 |
Proposed Ø150 mm Water
Distribution Mains - Basak-Babag, Lapulapu City |
Ana Construction |
Php |
8,368,625.90 |
|
|
07 Feb 2013 |
04 Sep 2013 |
|
0.00% |
0.00% |
0.00% |
Pre-Construction Meeting was
held last February 15, 2013. The Project was awarded to Ana Construction.
Notice to Proceed was given last February 7, 2013 with a Contract Duration of
210 Calendar Days. The Project is expected to be completed on September 4,
2013. Important matters and procedures for the smooth implementation of the
project were discussed thoroughly. The Contractor is reminded to submit shop
drawings for all the materials intended for the project. MCWD in behalf of
the Contractor is securing the necessary excavation permit from the City of
Lapu-Lapu. |
|
|
|
|