REPORT SUMMARY |
|
|
|
|
|
|
|
F.
SECTION VII. PROJECTS COMPLETED IN
2012 - 2013 |
|
|
|
|
|
|
|
|
|
SUMMARY OF COMPLETED PROJECTS FROM JANUARY 2012 -
APRIL 2013: |
|
|
|
|
|
|
|
|
|
|
|
F.1.
INFRASTRUCTURE PROJECTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of
Project |
Location |
Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
1.0 |
Prop. Ø 300mm
HDPE Expansion Project for BC Homes Water Supply (Extension Line) |
BC
Homes, Lahug, Cebu City |
PhP |
6,349,019.67 |
May 21, 2012 |
Already complied with MCWD Standard Requisites.
Certification of Project Completion was already issued to the Contractor |
|
|
|
|
|
|
2.0 |
Prop.
Replacement of Existing Distribution Mains Along Tres De Abril, U Alviola, JM
Basa and V Rama Streets, Cebu City |
Tres
de Abril, U Alviola, JM Basa and V Rama Streets, Cebu City |
PhP |
12,742,433.09 |
July 30, 2012 |
Already complied with MCWD Standard Requisites.
Certification of Project Completion was already issued to the Contractor |
|
|
|
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Transfer Tapping and Deccommissioning at U.
Alviola, Tres de Abril, V. Rama and JM Basa Streets, Cebu City |
|
|
|
|
|
See Part C Section VI Subsection C.2 of the
Report Summary |
|
|
|
|
|
|
3.0 |
Construction of
Proposed Pumping Station for MCWD In-House Water Sourcing Program - Cluster A |
Brgy.
Buhisan and Talamban, Cebu City |
PhP |
10,783,223.92 |
August 24, 2012 |
Already complied with MCWD Standard Requisites.
Certification of Project Completion was already issued to the Contractor |
|
|
|
|
|
|
4.0 |
Interim Measure
to Protect Existing Ø800mm Transmission Line Across Maghaway River in Brgy.
Jaclupan |
Brgy.
Jaclupan, Talisay City |
PhP |
2,492,796.64 |
August 28,
2012 |
Already complied with MCWD Standard Requisites.
Certification of Project Completion was already issued to the Contractor |
|
|
|
|
|
|
5.0 |
Prop. Tennis
Court Resurfacing |
MCWD
Compound, Talamban, Cebu City |
PhP |
124,000.00 |
February 28,
2013 |
Certification of Project Completion was already
issued to the Contractor |
|
|
|
|
|
|
6.0 |
Prop. Ø75mm
Surface Mounted Bulkmeter for TPA-LTHAI |
Tipolo,
Mandaue City |
PhP |
701,581.31 |
|
|
|
|
|
## |
Prop. D.I. Rehabilitation Project
for DMA-25A
JICA-YOKOHAMA-MCWD Special Project |
W. Cabalse and Holyname Sts., Mabolo, Cebu
City |
PhP |
2,449,834.22 |
May 6, 2013 |
Transfer tapping and decommissioning, all of
which are 100% completed, are done by PMG. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F.2. 'BY
ADMINISTRATION' PROJECTS |
|
|
|
|
|
|
|
|
|
|
F.2.1 PIPELINE EXPANSION |
|
|
|
|
|
|
|
|
|
|
Name of
Project |
Location |
Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
1.0 |
Upper Canduman
Distribution Line |
Upper Canduman Residents |
PhP |
1,583,332.00 |
19-May-12 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
2.0 |
Ø100mm
Interconnection Pipeline from W35 |
Berjame Subd., Tigbao, Talamban, Cebu City |
PhP |
|
23-May-12 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
for as built to
coordinate with ED |
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Berjame Subdivision, Tigbao
Talamban, 100mm dia. x 211LM, 75mm dia. x 391 LM, 50mm dia. x 141 LM |
|
|
|
|
|
See Part C Section IV Subsection C.1 of the
Report Summary |
|
|
|
|
|
|
3.0 |
Sta. Cruz Distribution Line |
Brgy. Sta Cruz, Liloan, Cebu |
PhP |
5,134,317.40 |
15-June-12 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Sta. Cruz Well Rehabilitation |
|
|
|
|
|
See Part C Section IV Subsection C.2 of the
Report Summary |
|
|
|
|
|
|
4.0 |
Prop. Water Distribution System for
Alberlyn South Subdivision |
Brgy. Cansojong, Talisay City, Cebu |
PhP |
1,596,881.63 |
7-Feb-2013 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Prop. Water Distribution
System for Alberlyn South Subdivision (Cansojong, Talisay City, Cebu) |
|
|
|
|
|
See Part D Section V Subsection D.2 of the
Report Summary |
|
|
|
|
|
|
5.0 |
Berjame Subdivision, Tigbao Talamban |
Brgy. Talamban, Cebu City |
PhP |
2,027,423.69 |
16-Mar-2013 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
|
|
|
|
Related Projects: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Well 35 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 Ø100mm Interconnecting
Pipeline (W35) |
|
|
|
|
|
See Part D Section V Subsection D.2 of the
Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 13 |
|
|
|
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F.2. 2 WATER SOURCE
DEVELOPMENT |
|
|
|
|
|
|
|
|
|
|
Name of
Project |
Location |
Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
1.0 |
Well 34B |
Tigbao,
Talamban, Cebu City |
PhP |
2,446,034.34 |
June 21, 2012 |
Already complied with MCWD Standard Requisites. |
|
|
|
|
|
F.
SECTION VII. PROJECTS COMPLETED IN
2012 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F.3. SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F.3. 1 WATER SYSTEM |
|
|
|
|
|
|
|
|
|
|
Name of
Project |
Location |
Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
1.0 |
Prop. Water
Distribution System for Colorado Homes |
Cotcot, Liloan,
Cebu |
PhP |
11,043,583.41 |
January 17,
2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
2.0 |
Prop. Water Distribution System
for Phebz Subdivision (Phase IB, II & III) |
Bag-ong Dan Road, Brgy. Tayud,
Liloan |
PhP |
2,051,167.51 |
January 31,
2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
3.0 |
Prop. Water Distribution System
for The Heritage Subdivision |
Brgy. Jagobiao, Mandaue City,
Cebu |
PhP |
6,836,134.93 |
May 18,
2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
4.0 |
Prop. Water Distribution System
for Montserrat Subdivision |
Brgy. Bankal, Lapu-lapu City |
PhP |
5,458,623.83 |
October29,
2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
5.0 |
Prop. Water Distribution Main
for CBP Resort Development Project |
Negros St., Cebu Business Park,
Cebu City |
PhP |
544,278.79 |
January 8,
2013 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
6.0 |
Prop. Water Distribution System
for Alberlyn South Subdivision |
Cansojong, Talisay City, Cebu |
PhP |
1,122,690.12 |
April 16,
2013 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F.3. 2 FLOWMETER
ASSEMBLY AND VAULT |
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Project Cost |
Date Completed |
Remarks |
|
|
|
|
|
|
|
1.0 |
Prop. 100mm
Flowmeter Enclosed in Concrete Vault for Fleur de Ville Subdivision |
Brgy Mactan,
Lapulapu City |
Php |
900,500.00 |
December 26, 2011 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
|
2.0 |
Prop. 150mm Flowmeter Concrete
Vault for Mactan Newtown Project |
Brgy Mactan, Lapulapu City |
Php |
944,081.06 |
January 18, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
|
3.0 |
Prop. 75mm Flowmeter and
Construction of Reinforced Concrete Vault for Rustan's Shopwise |
Cebu South Road, Mambaling, Cebu
City |
Php |
923,788.26 |
February 9, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
4.0 |
Prop. Flowmeter and Construction of Reinforced Concrete Vault
for Villa Lucila Subdivision |
Poblacion,
Liloan, Cebu |
Php |
819,000.00 |
February 4, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
|
5.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Vault for Tune Hotel |
Arch.
Reyes Avenue, Cebu City |
PhP |
977,339.12 |
March 27, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
|
6.0 |
Prop. Ø75mm Flowmeter and
Const. of Reinforced Concrete Vault for St. Bernadette Subd. |
Sudtungan,
Lapulapu City |
Php |
918,127.92 |
April 25, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
|
7.0 |
Prop. 100mm
Flowmeter and Construction of Reinforced Concrete Vault for J-Center |
Bakilid,
Mandaue City |
Php |
1,148,915.68 |
June 14, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
8.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Vault for Avalon |
Cebu Business
Park, Cebu City |
Php |
950,246.82 |
June 28, 2012 |
Already complied with MCWD Standard Requisites |
|
|
|
|
|
9.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Vault for Corinthians
Subdivision |
Sudtungan,
Lapulapu City |
Php |
1,064,555.79 |
July 19, 2012 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
10.0 |
Prop. Ø100mm
Flowmeter and Construction of Reinforced Concrete Vault for Alegria Palms |
Cordova, Cebu |
Php |
1,083,474.59 |
July 26, 2012 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
11.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Vault for Pacific Grande
(Formerly Mactan Oasis Subdivision) |
Carajay Road,
Gun-ob, Lapu-lapu City |
Php |
955,486.22 |
December 6, 2012 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
12.0 |
Prop. Ø75mm
Flowmeter and Construction of Reinforced Concrete Vault for Blue Coast
Residences |
Punta Engaño,
Lapu-lapu City |
Php |
833,000.00 |
December 11, 2012 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
13.0 |
Prop. Ø150mm
Flowmeter and Construction of Reinforced Concrete Vault for Amisa Private
Residences |
Punta Engaño,
Lapu-lapu City |
Php |
1,346,387.53 |
March 8, 2013 |
Already complied with MCWD
Standard Requisites |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 14 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F.4. SERVICE CONNECTION
TRANSFER TAPPING AND DECOMMISSIONING |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project |
Location |
Project Cost |
Date Completed |
Remarks |
|
|
|
1.0 |
Transfer
Tapping Along Plaridel Street |
Plaridel
St., Mandaue City |
PhP |
973,000.00 |
March 1, 2012 |
|
|
|
|
|
2.0 |
Transfer Tapping Along Mabini
Street |
Mabini St.,
Mandaue City |
PhP |
1,300,000.00 |
March 27, 2012 |
|
|
|
|
|
3.0 |
Transfer Tapping and
Deccommissioning at U. Alviola, Tres de Abril, V. Rama and JM Basa Streets,
Cebu City |
U. Alviola,
Tres de Abril, V. Rama and JM Basa Streets, Cebu City |
PhP |
2,737,000.00 |
January 4, 2013 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|