D. SECTION V. ON-GOING SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS
Under a Memorandum of Agreement (MOA), the developer/owner shall fund and implement the project and  turn-over  it to MCWD upon completion. MCWD is obligated to prepare the detailed design and estimates and provide supervision during the implementation of the project.
Name of Project  Brief Description of the Project Subdivision/Hotel/Condo Name Developer / Owner MCWD Supervising Unit Project Amount Project Duration Date Started Target Completion Date Accomplish-          ment                             To Date Remarks LATEST UPDATE AS OF FEBRUARY 2013
D.1 Water System                  
1.0 Prop. Water Distribution System for EastGate Subdivision (Matumbo, Pusok, Lapulapu) 49.54 LM x 75mm dia EastGate Subdivision Urban Enclaves Inc. Project Management Office PhP      514,061.34 11 CD 15 Jul 2011 26 Jul 2011 0.00% No activity conducted for the month.   contractor and subcontractor is on meeting…
                   
  Related Project:                  
  1.0 Pusok, Lapu-Lapu (Matumbo), Pipe laying 96 LM x 75mm dia. & 126 LM x 150mm dia. D.I.               See Part C Section IV Subsection C.1 of the Report Summary  
                           
2.0 Prop. Water Distribution System for Modena Mactan Subdivision (Basak, Lapu-lapu City) 166 LM x 100mm dia., 1016 LM x 75mm dia. Modena Mactan Subdivision Juanito King & Sons, Inc. Project Management Office PhP   4,011,373.95 95 CD 25 Apr 2011 28 Jul 2011 97.00% For issuance of substantial project completion after restoration works is finished.   Corplan has worked out the minor problems.
                     
  Related Project:                  
  1.0 Modena Subdivision (Interconnecting Pipeline)                     See Part A Section II Subsection 10 of the Report Summary  
3.0 Prop. PVC Water Distribution System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu)  484 LM x 75mm dia., 781 LM x 100mm dia., 167 LM x 150mm dia. Amara Subdivision Cebu Holdings, Inc. Project Management Office PhP   92 CD 15 May 2012 14 Aug 2012 96.00% Contractor is on the process of purchasing the handhole cover and AV/AR head.   A meeting was held. It will be turned-over by July 2013.
  Related Project:                  
  1.0 Amara Waterline Project (MCWD  Counterpart)                 See Part C Section IV of the Report Summary
  2.0 Prop. Rerouting of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu)                     See Part D Section V of the Report Summary
4.0 Prop. Rerouting of PVC Water Distribution Line for Amara Subdivision (Catarman, Liloan, Cebu)  1,650 LM x 150mm dia. Amara Subdivision Cebu Holdings, Inc. Project Management Office PhP   92 CD 15 May 2012 14 Aug 2012 96.00%[1] Remaining works are:disinfection and interconnection. Interconnection to the water tank is already completed. Remaining work is only disinfection. This will be included with the project turnover above.
  Related Project:                    
  1.0 Amara Waterline Project (MCWD  Counterpart)                   See Part C Section IV of the Report Summary
    2.0 Prop. PVC Water Distribution System for Amara Subdivision - Phase 6 (Catarman, Liloan, Cebu)                     See Part D Section V of the Report Summary
   
Section I. Summary    8
REPORT SUMMARY
D. SECTION V. ON-GOING SUBDIVISION/HOTEL/CONDO WATER SYSTEM PROJECTS
Name of Project  Brief Description of the Project Subdivision/Hotel/Condo Name Developer / Owner MCWD Supervising Unit Project Amount Project Duration Date Started Target Completion Date Accomplish-          ment                             To Date Remarks
6.0 Prop. Water Distribution System for Pueblo De Oro Communities (Sitio Judas Belt, Babag II, Lapu-lapu City)[2] 6,920 LM x 75mm dia., 2,071 LM x 100mm dia., 1,286 LM x 150mm dia., 49 LM x 200mm dia., 151 LM x 250mm dia. Pueblo De Oro Communities (Horizon, La Aldea Del Mar, and Parkplace) Pueblo De Oro Development Corp. Project Management Office PhP   22,980,152.33       10.00% No activity conducted for the month. currently doing pipelaying works..
7.0 Prop. Water Distribution System for Portville Subdivision (Aviation Road, Brgy. Buaya, Lapu-lapu City)[3] 982 LM x 75mm dia., 269 LM x 100mm dia., 17 LM x 150mm dia. Portville Subdivision Johndorf Venture Corp. Project Management Office PhP     3,430,246.86 94 CD 3-Sep-12 6-Dec-12 50.00% Waiting for the materials that were allegedly stolen.
D.2 Flowmeter Assembly and Vault                  
1.0 Prop. Ř150mm Large Meter Assembly for Urban Homes Mandaue dia.150mm Large Meter, Large Meter Assembly & Interconnection Urban Homes Fog Horn, Inc. Project Management Office PhP   1,428,658.31 46 CD       Developer has requested the testing of materials. Request material inspection
2.0 Prop. Ř75mm Flowmeter and Construction of Reinforced Concrete Meter Vault for 1016 Residences dia.75mm Flowmeter, Flowmeter Assembly & Interconnection 1016 Residences Ayala Land, Inc. and Cebu Holdings, Inc. Project Management Office PhP      952,133.26 30 CD       No communication with the developer. same
Section I. Summary    9 

[1]
JuliusM:
For the MCWD project only.
[2]
Inspector:
Rene Cabardo
[3]
Inspector:
Rene P. Cabardo