REPORT SUMMARY
C. SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS
Name of Project  Project Beneficiary Implementing Unit Approved Budget Duration Date Started Completion Date Schedule and Accomplishment Remarks LATEST UPDATE AS OF APRIL 2013
Target            To Date Actual       To Date Variance To Date
Original Revised Original  Revised Original Revised
                                 
C.1 Pipeline Expansion                              
                                 
                                 
1.0 Lagtang Distribution Line[1] Sitio Tigib-Burlas, Lagtang,  Residents Construction Department PhP    2,660,000.00 PhP 68 c.d.             Engineering Department has done already the typical trench section and it is already submitted by Legal Department to Cebu 2nd Engineering District. This is the third cross sections requested by the said Engineering District. MCWD is awaiting for the amount of cash bond for road restoration works.   Cebu 2nd eng district requires another trench section.
                                  
2.0 Casili Estate Distribution Line Casili Estate Residents Construction Department PhP    1,391,000.00 PhP 21 c.d.             The electromagnetic metering chlorine injector is being distributed to respective supplier for their quotation and to date there are still no respond from suppliers. Until now no quotation being returned from suppliers. follow up IDA on booster procurement
                                   
3.0 Pusok, Lapu-Lapu (Matumbo), Pipe laying 96 LM x 75mm dia. & 126 LM x 150mm dia. D.I. Pusok, Lapu-lapu Construction Department PhP    2,292,548.83 PhP   145 c.d.   11 Feb 2013 21 May 2013   100.00% 100.00% 0.00% The project is completed on April 30, 2013. The date of completion is ahead as scheduled. The project is already inspected by other concerned departments for any possible missing items. Completed April 30, 2013. Ahead…
  Related Project:                        
  1.0 Prop. Water Distribution System for  East Gate Subdivision (Matumbo, Pusok, Lapulapu)                       See Part D Section V Subsection D.1 of the Report Summary
                         
4.0 St. Anthony Village, Hi-way 77, 75mm dia. x 234 LM  St. Anthony Village Construction Department PhP    1,100,000.00 PhP   23 c.d.               The 75mm PVC pipes previously rejected by MCWD due to its undersized diameters were already retrieved by the supplier and the former is awaiting for the latter's confirmation whether to replace the said pipes or not. If they will be no longer interested to replace said pipes, MCWD will award to the second lowest bidder. However, to date the supplier has shown signs of replacing the said rejected pipes but with no definite date in the replacement according to MMD. No replacement was ever made. It will be bid out again.
                         
5.0 Proposed Water Distribution System for Biasong Relocation Site P. West Road, Brgy. Biasong, Talisay City Construction Department PhP    1,300,000.00     36 c.d.               The City Engineer's Office of Talisay has already set the required amount of cash bond for road restoration works. The Legal Department has forwarded the said amount to the Accounting Department and is still awaiting of its release. LD has request money from finance. Tentatively will start on May 14, 2013
                         
                                 
C.2 Pipeline Rehabilitation                              
                                 
1.0 Proposed Ř100mm X 192 lm DI Distribution Rehabilitation   Project along I Tabura St., Brgy. Pardo, Cebu City Construction Department PhP    1,766,946.23 PhP   43 c.d.               The procurement status of this project is still being clustered. Procurement stage.
2.0 Proposed Ř200mm X 301 lm DI Distribution Rehabilitation Project  along Datag, Maribago, Lapulapu City Datag, Maribago, Lapulapu City Construction Department PhP    4,608,000.00 PhP   45 c.d.               The procurement status of this project is still being clustered. Procurement stage.
3.0 F. Llamas, Labangon Realignment of 200mm and 100mm uPVC                             The Engineering Department and Construction Department have conducted the site assessment of the project and has found out that there is a revision of the original plan prepared by Engineering Department. Since the pipeline to be altered is not only traversing the school, the covered court and the barangay hall therefore there is a need for a resurvey and redesign of the project.
Section I. Summary   6  
REPORT SUMMARY
C. SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS
Name of Project  Project Beneficiary Implementing Unit Approved Budget Duration Date Started Completion Date Schedule and Accomplishment Remarks
Target            To Date Actual       To Date Variance To Date
Original Revised Original  Revised Original Revised
                     
C.3 Pumping Station                                 
                                 
1.0 Sta. Cruz Well (Liloan) Brgy. Sta Cruz Residents Bayanihan - C/O PDD PhP    5,590,000.00 PhP 87 c.d.         97% The pumping station has been operational since July 2012. Materials for fencing and gate already in talamban. Waiting for available trucks so as to deliver materials on site.
                    The remaining project component is the construction of perimeter fence and gate. Some materials are delivered and available. Construction of fence will commence anytime if the materials needed are completed. 
  Related Project:                        
  1.0 Sta. Cruz Distribution Line, Lilo-an, Cebu                       See Part C Section VII Subsection F.2.1 of the Report Summary 
                                 
  2.0 Well 35 Berjame Subdivision and Barangay Talamban Residents Bayanihan - C/O PDD PhP           4 Feb  2012 30Apr2012     98%   During the well testing , PDD/Laboratory personnel had detected the presence of high level Iron Manganese on the water. PDD is planning to install a filter media (Iron Manganese Treatment Device)  to remove the Iron Manganese. The testing of berm is already done. Berm is the replacement of sand. The budget for the abovementioned undertaking is now at CAPEX for budget allocation. Iron manganese "getting worse". High level of iron manganese. Supposedly for capex but due to high level of iron manganese, this is put on hold. Still under experimentation to resolve the presence of high level of iron manganese.
                           
  Related Projects:                        
  1.0 Berjame Subdivision, Tigbao Talamban, 100mm dia. x 211LM, 75mm dia. x 391 LM, 50mm dia. x 141 LM                        
  2.0 Ř100mm Interconnecting Pipeline (W35)                       Already completed. See Part F Section VII Subsection F.2.1 of the Report Summary
                                 
  3.0 Mac 6, 7 & 8 Pumping Stations Cluster C Brgy. Pajac &  Bankal Residents in Lapulapu City Construction Department/ MSSD PhP    8,709,862.10 PhP   113 c.d.               For clustering as of April 29,2013. For clustering as of april 29,2013.
  Related Project:                        
  1.0 Mac 6 & 7 Connecting Pipeline                       See Part E Section VI Subsection E.2 of the Report Summary
  2.0 Mac 8 Connecting Pipeline                             See Part E Section VI Subsection E.2 of the Report Summary
  4.0 Mac 10 & 11 Pumping Stations Brgy. Pajac, Bankal & Agus Residents in Lapulapu City Construction Department/ MSSD PhP    6,508,756.40 PhP   36 c.d.               For clustering as of December 3, 2012. for clustering as of dec 3, 2012
  Related Project:                        
  1.0 Mac 10 & 11 Connecting Pipeline                             See Part E Section VI Subsection E.2 of the Report Summary
  5.0 Portville (MAC 12)                             The special budget appropriation is already approved. Encoding via BMS of materials is on-going. for segregation.
C.4 Transfer Tapping and Decommissioning                                    
1.0 Transfer Tapping and Deccommissioning at U. Alviola, Tres de Abril, V. Rama and JM Basa Streets, Cebu City Residents at U. Alviola, Tres de Abril, V. Rama and JM Basa Sts. Construction Department PhP    2,737,000.00     74 c.d.     Oct. 8, 2012 Jan. 4, 2013   98%   Inspite of the occurrence of intervening work, the project is ahead of the target completion. The project is expected to be completed first week of January 2013.
  Related Projects:                    
  Prop. Replacement of Existing Distribution Mains Along Tres De Abril, U Alviola, JM Basa and V Rama Streets, Cebu City                             Already completed. See Part F Section VII Subsection F.1.2 of the Report Summary
Section I. Summary   7  
`

[1]
Kim:
previously: Jaclupan Distribution Line