|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REPORT SUMMARY |
|
|
|
|
C.
SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS |
|
|
|
|
|
|
Name
of Project |
Project Beneficiary |
Implementing Unit |
Approved Budget |
Duration |
Date Started |
Completion Date |
Schedule
and Accomplishment |
Remarks |
|
LATEST UPDATE AS OF APRIL 2013 |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
|
Original |
Revised |
Original |
Revised |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C.1 Pipeline Expansion |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Lagtang Distribution Line[1] |
Sitio Tigib-Burlas,
Lagtang, Residents |
Construction Department |
PhP |
2,660,000.00 |
PhP |
|
68 c.d. |
|
|
|
|
|
|
|
Engineering
Department has done already the typical trench section and it is already
submitted by Legal Department to Cebu 2nd Engineering District. This is the
third cross sections requested by the said Engineering District. MCWD is
awaiting for the amount of cash bond for road restoration works. |
|
Cebu 2nd eng district requires
another trench section. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Casili Estate Distribution Line |
Casili Estate Residents |
Construction Department |
PhP |
1,391,000.00 |
PhP |
|
21 c.d. |
|
|
|
|
|
|
|
The
electromagnetic metering chlorine injector is being distributed to respective
supplier for their quotation and to date there are still no respond from
suppliers. |
|
Until now no quotation being
returned from suppliers. |
follow up IDA on
booster procurement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Pusok,
Lapu-Lapu (Matumbo), Pipe laying 96 LM x 75mm dia. & 126 LM x 150mm dia.
D.I. |
Pusok, Lapu-lapu |
Construction
Department |
PhP |
2,292,548.83 |
PhP |
|
145 c.d. |
|
11 Feb 2013 |
21 May 2013 |
|
100.00% |
100.00% |
0.00% |
The
project is completed on April 30, 2013. The date of completion is ahead as
scheduled. The project is already inspected by other concerned departments
for any possible missing items. |
|
Completed April 30, 2013.
Ahead… |
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Prop. Water Distribution
System for East Gate Subdivision
(Matumbo, Pusok, Lapulapu) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part D
Section V Subsection D.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.0 |
St. Anthony Village, Hi-way 77,
75mm dia. x 234 LM |
St. Anthony Village |
Construction Department |
PhP |
1,100,000.00 |
PhP |
|
23 c.d. |
|
|
|
|
|
|
|
The 75mm PVC
pipes previously rejected by MCWD due to its undersized diameters were
already retrieved by the supplier and the former is awaiting for the latter's
confirmation whether to replace the said pipes or not. If they will be no
longer interested to replace said pipes, MCWD will award to the second lowest
bidder. However, to date the supplier has shown signs of replacing the said
rejected pipes but with no definite date in the replacement according to MMD. |
|
No replacement was ever made. It will be bid out again. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.0 |
Proposed Water Distribution
System for Biasong Relocation Site |
P. West Road, Brgy. Biasong,
Talisay City |
Construction Department |
PhP |
1,300,000.00 |
|
|
36 c.d. |
|
|
|
|
|
|
|
The City
Engineer's Office of Talisay has already set the required amount of cash bond
for road restoration works. The Legal Department has forwarded the said
amount to the Accounting Department and is still awaiting of its release. |
|
LD has request money from
finance. Tentatively will start on May 14, 2013 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C.2 Pipeline
Rehabilitation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Proposed Ř100mm
X 192 lm DI Distribution Rehabilitation
Project along I Tabura St., |
Brgy. Pardo,
Cebu City |
Construction
Department |
PhP |
1,766,946.23 |
PhP |
|
43 c.d. |
|
|
|
|
|
|
|
The
procurement status of this project is still being clustered. |
|
Procurement stage. |
|
|
2.0 |
Proposed Ř200mm
X 301 lm DI Distribution Rehabilitation Project along Datag, Maribago, Lapulapu City |
Datag, Maribago,
Lapulapu City |
Construction
Department |
PhP |
4,608,000.00 |
PhP |
|
45 c.d. |
|
|
|
|
|
|
|
The
procurement status of this project is still being clustered. |
|
Procurement stage. |
|
|
3.0 |
F. Llamas,
Labangon Realignment of 200mm and 100mm uPVC |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
Engineering Department and Construction Department have conducted the site
assessment of the project and has found out that there is a revision of the
original plan prepared by Engineering Department. Since the pipeline to be
altered is not only traversing the school, the covered court and the barangay
hall therefore there is a need for a resurvey and redesign of the project. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 6 |
|
|
REPORT SUMMARY |
|
|
|
|
|
|
|
C.
SECTION IV ON-GOING 'BY ADMINISTRATION' PROJECTS |
|
|
|
|
|
|
|
|
Name
of Project |
Project Beneficiary |
Implementing Unit |
Approved Budget |
Duration |
Date Started |
Completion Date |
Schedule and
Accomplishment |
Remarks |
|
|
Target To Date |
Actual To Date |
Variance To Date |
|
|
Original |
Revised |
Original |
Revised |
Original |
Revised |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C.3 Pumping Station |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Sta. Cruz Well (Liloan) |
Brgy. Sta Cruz Residents |
Bayanihan - C/O PDD |
PhP |
5,590,000.00 |
PhP |
|
87 c.d. |
|
|
|
|
|
97% |
|
The pumping station has been
operational since July 2012. |
|
Materials for fencing
and gate already in talamban. Waiting for available trucks so as to deliver
materials on site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The remaining project component
is the construction of perimeter fence and gate. Some materials are delivered
and available. Construction of fence will commence anytime if the materials
needed are completed. |
|
|
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Sta. Cruz Distribution
Line, Lilo-an, Cebu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part C
Section VII Subsection F.2.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 |
Well 35 |
Berjame
Subdivision and Barangay Talamban Residents |
Bayanihan - C/O PDD |
PhP |
|
|
|
|
|
4 Feb 2012 |
30Apr2012 |
|
|
98% |
|
During
the well testing , PDD/Laboratory personnel had detected the presence of high
level Iron Manganese on the water. PDD is planning to install a filter media
(Iron Manganese Treatment Device) to
remove the Iron Manganese. The testing of berm is already done. Berm is the
replacement of sand. The budget for the abovementioned undertaking is now at
CAPEX for budget allocation. |
|
Iron manganese "getting
worse". High level of iron manganese. Supposedly for capex but due to
high level of iron manganese, this is put on hold. Still under
experimentation to resolve the presence of high level of iron manganese. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Related Projects: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Berjame Subdivision, Tigbao
Talamban, 100mm dia. x 211LM, 75mm dia. x 391 LM, 50mm dia. x 141 LM |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.0 Ř100mm Interconnecting
Pipeline (W35) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Already
completed. See Part F Section VII Subsection F.2.1 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.0 |
Mac 6, 7 &
8 Pumping Stations Cluster C |
Brgy. Pajac
& Bankal Residents in Lapulapu
City |
Construction
Department/ MSSD |
PhP |
8,709,862.10 |
PhP |
|
113 c.d. |
|
|
|
|
|
|
|
For
clustering as of April 29,2013. |
|
For clustering as of april
29,2013. |
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mac 6 & 7 Connecting
Pipeline |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part E
Section VI Subsection E.2 of the Report Summary |
|
|
|
2.0 Mac 8 Connecting Pipeline |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part E
Section VI Subsection E.2 of the Report Summary |
|
|
4.0 |
Mac 10 & 11
Pumping Stations |
Brgy. Pajac,
Bankal & Agus Residents in Lapulapu City |
Construction
Department/ MSSD |
PhP |
6,508,756.40 |
PhP |
|
36 c.d. |
|
|
|
|
|
|
|
For
clustering as of December 3, 2012. |
|
for clustering as of dec 3, 2012 |
|
|
|
Related Project: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 Mac 10 & 11 Connecting
Pipeline |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
See Part E
Section VI Subsection E.2 of the Report Summary |
|
|
5.0 |
Portville (MAC 12) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
special budget appropriation is already approved. Encoding via BMS of
materials is on-going. |
|
for segregation. |
|
|
C.4 Transfer
Tapping and Decommissioning |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.0 |
Transfer
Tapping and Deccommissioning at U. Alviola, Tres de Abril, V. Rama and JM
Basa Streets, Cebu City |
Residents at U.
Alviola, Tres de Abril, V. Rama and JM Basa Sts. |
Construction Department |
PhP |
2,737,000.00 |
|
|
74 c.d. |
|
|
Oct. 8, 2012 |
Jan. 4, 2013 |
|
98% |
|
Inspite
of the occurrence of intervening work, the project is ahead of the target
completion. The project is expected to be completed first week of January
2013. |
|
|
|
|
|
Related Projects: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prop. Replacement of Existing
Distribution Mains Along Tres De Abril, U Alviola, JM Basa and V Rama
Streets, Cebu City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Already
completed. See Part F Section VII Subsection F.1.2 of the Report Summary |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Section I. Summary 7 |
|
|
|
|
|
|
|
|
|
|
|
` |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|